On February 20 (ie, the 4th day of the Lunar New Year of Binh Ngo), Secretary of the Party Committee, Chairman of the People's Council of Khuong Dinh ward (Hanoi) organized a meeting, wished Tet and encouraged the forces directly implementing site clearance (GPMB) for the Ring Road 2.5 project, Nguyen Trai section (National Highway 6) to Dam Hong.
The meeting took place in a urgent and responsible atmosphere right from the early days of the new Spring, showing the high political determination of Khuong Dinh ward in focusing on implementing the key tasks of 2026.
Mr. Nguyen Sy Doan - Chairman of the Ward People's Committee, Chairman of the Compensation, Support and Resettlement Council directly maintained the working regime throughout Tet, received citizens, listened to and answered opinions and recommendations related to the draft plan to ensure the progress of completing the compensation, support, and resettlement plan.
Many specific contents were discussed such as determining the origin of land, recovered area, policies to support stable living, temporary housing rental support, conditions and criteria for resettlement arrangement.
For cases that need further verification, the Council assigns specialized officials to continue reviewing dossiers, ensuring the legitimate and lawful rights and interests of the people, and at the same time maintaining discipline and compliance with legal regulations.
Speaking at the meeting, Mr. Vo Dang Dung - Secretary of the Party Committee, Chairman of the People's Council of Khuong Dinh ward emphasized that the site clearance for the Ring Road 2.5 project is a particularly important political task, of great significance for the development of transport infrastructure, reducing congestion and promoting socio-economic development in the ward.
Mr. Dung requested units to continue to promote the spirit of solidarity, close coordination; closely follow each time milestone, each specific task; promote propaganda, publicity, and transparency of information; promptly advise on removing difficulties and obstacles arising; be determined to complete targets and progress according to the set plan, creating a premise for the project to be implemented soon.
The Ring Road 2.5 project, Nguyen Trai - Dam Hong section, has a length of 1,520m, a cross-section scale of 40m of roadbed. The project is invested by Khuong Dinh Ward People's Committee, with a total investment of 2,433 billion VND.
According to the report of the Khuong Dinh Ward Investment - Infrastructure Project Management Board, the Ring Road 2.5 project passing through the ward has a total recovered area of more than 60,900 m2, involving 736 cases, including organizations and households, and individuals.
For 36 cases according to Decision No. 15/QD-UBND dated January 24, 2003, the plan was approved from the previous phase, the Ward People's Committee has promoted propaganda, mobilization and completed the demolition and handover of the site.