Hanoi technically opens underpass tunnel, Ring Road 2.5 nearly 2 million billion VND

SÓNG HỮU |

Hanoi - The 2.5 Ring Road - National Highway 1A intersection underpass project and 1.6km of 2.5 Ring Road section Dam Hong - National Highway 1A technically opened to traffic this morning (February 10).

On the morning of February 10, the Ring Road 2.5 project, Dam Hong - National Highway 1A section, officially opened to technical traffic after 12 years of construction.

The project is invested under the BT (build - transfer) contract form with a length of 1.6km, total investment of about 1,317 billion VND.

ávvsv
Ring Road 2.5 project, Dam Hong - National Highway 1A section (Hanoi) technically opened to traffic after 12 years of construction. Photo: Song Huu

The Ring Road 2.5 project, Dam Hong - National Highway 1A section, started in 2014, and was expected to be completed in 2017 but was delayed.

By 2020, the project was temporarily suspended when it had only reached about 40% of the workload. The reason was obstacles in site clearance and extension of the BT contract appendix.

cưqc
Vehicles traveling on Ring Road 2.5. Photo: Song Huu

After 5 years of suspension, by the end of May 2025, with the permission of the Hanoi People's Committee, Hoang Mai - Hanoi Construction Investment Co., Ltd. (the project enterprise) organized the Groundbreaking Ceremony for the 2.5 Ring Road construction project, Dam Hong - National Highway 1A section.

To date, the project has basically completed the main items.

The technically opened road ensures synchronous connection with the technical opening plan of the Ring Road 2.5 - Giai Phong intersection underpass project (National Highway 1A), serving people to travel to welcome the Binh Ngo Lunar New Year.

a
Underpass at the Ring Road 2.5 - Giai Phong intersection. Photo: Song Huu

The underpass construction project at the Ring Road 2.5 - Giai Phong intersection was started in October 2022.

The project has a total length of tunnel and access road of 890m in the direction of Ring Road 2.5, of which the closed tunnel is 140m long, the open tunnel is 320m long. The section through the tunnel has 2 lanes in each direction, 3.5m wide/lane, and the section outside the tunnel has 3 lanes in each direction, 3.5m wide/lane.

The underpass project has a total investment of 778 billion VND, invested by the Hanoi Traffic Construction Investment Project Management Board.

This is the 5th underpass in the Capital built from 2009 to date, after Kim Lien, Trung Hoa, Thanh Xuan, and Le Van Luong tunnels.

a
Overview of the underpass at the Ring Road 2.5 - Giai Phong intersection. Photo: Song Huu

On the evening of February 9th, the Hanoi Department of Construction issued a notice to temporarily organize traffic flow for vehicles participating in road traffic through the tunnel and the intersection area of Giai Phong street - Kim Dong street - Ring Road 2.5 under the Ring Road 2.5 underpass project with Giai Phong (QL1A) and the Ring Road 2.5 construction project (from Dam Hong to QL1A section).

Time from February 10 to March 31, 2026.

See the traffic diversion plan here.

SÓNG HỮU
RELATED NEWS

Hanoi temporarily diverts traffic through Kim Dong - Giai Phong underpass

|

Hanoi - From February 10 to March 31, temporary traffic diversion will be organized through the Kim Dong - Giai Phong underpass and intersection.

Ring Road 2.5 Project: Many recommendations on land acquisition and site clearance

|

Hanoi - Many households within the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, raised recommendations on land compensation prices, support policies, resettlement...

Ring Road 2.5: Consider adjusting compensation and resettlement plans

|

Hanoi - People's recommendations on the Ring Road 2.5 project will be reported to higher levels for consideration and adjustment of compensation plans in accordance with regulations and practice.

Russia declares destruction of Ukrainian military airport and equipment

|

On February 9, Russian troops raided the infrastructure of a military airport and energy, fuel and transport facilities serving the Ukrainian army.

Ring Road 4 parallel road project: Many bidding packages are about to be completed

|

Hanoi - The bidding packages for the Ring Road 4 parallel road project are ensuring the set progress, including one bidding package that will be completed in March.

Calligraphy on cantaloupe, seasonal workers earn millions of VND per day

|

Vinh Long - In the days leading up to Tet, seasonal workers participate in painting calligraphy on cantaloupe, both creating product highlights and bringing in millions of VND in daily income.

Government sets deadline for operating gold and cryptocurrencies exchanges

|

The Government requests to urgently put into operation cryptocurrency trading markets, gold exchanges, and real estate before February 28, 2026.

Chairman of Vietnam General Confederation of Labour presents Tet gifts at Ha Bac Fertilizer and Chemical Joint Stock Company

|

VGCL President Nguyen Dinh Khang wishes Tet and gives gifts to union members and employees of Ha Bac Fertilizer and Chemical Joint Stock Company (Bac Ninh).

Hanoi temporarily diverts traffic through Kim Dong - Giai Phong underpass

Minh Hạnh |

Hanoi - From February 10 to March 31, temporary traffic diversion will be organized through the Kim Dong - Giai Phong underpass and intersection.

Ring Road 2.5 Project: Many recommendations on land acquisition and site clearance

SÓNG HỮU |

Hanoi - Many households within the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, raised recommendations on land compensation prices, support policies, resettlement...

Ring Road 2.5: Consider adjusting compensation and resettlement plans

SÓNG HỮU |

Hanoi - People's recommendations on the Ring Road 2.5 project will be reported to higher levels for consideration and adjustment of compensation plans in accordance with regulations and practice.