Road construction project worth over VND631 billion in Thanh Hoa behind schedule

QUÁCH DU |

Thanh Hoa - The road project is over 2km long, with an investment capital of over VND631 billion, and is behind schedule due to many reasons.

According to research, the Thanh Hoa - Sam Son landscape axis road project will start construction in 2023. The scale of the route is more than 2.3km long, with an investment of more than 631 billion VND.

Du an tuyen duong truc canh quan Thanh Hoa – Sam Son (phuong Sam Son, tinh Thanh Hoa) nhin tu tren cao. Anh: QUACH DU
Thanh Hoa - Sam Son landscape axis road project (Sam Son ward, Thanh Hoa province) seen from above. Photo: QUACH DU

The project is invested by the Sam Son City Construction Investment Project Management Board (now the Sam Son Construction Investment Project Management Board), expected to be completed in 2025.

However, according to the reporter of Lao Dong Newspaper, the project is currently behind schedule compared to the plan. Many locations have not been cleared, and the current status of the project is still in disarray.

Viec giai phong mat bang thuoc du an dang gap kho khan. Anh: QUACH DU
Site clearance for the project is facing difficulties. Photo: QUACH DU

The project has a total site clearance area of over 17 hectares, with 589 households affected. To date, the area handed over for construction has reached 13 hectares/424 households; the remaining 4.2 hectares/165 households have not been inventoried and compensation prices have been applied. In some cases, compensation plans have been approved but people have not agreed to receive the money.

The representative of the Sam Son Ward People's Committee said that the project is behind schedule due to many reasons, including slow site clearance and not yet arranged a resettlement area. In addition, the construction route passes through many locations with canals, ditches, and irrigation works, so it is difficult to implement.

Khu mo to cua 2 dong ho nam trong khu vuc thi cong du an. Anh: QUACH DU
The ancestral tombs of the two clans are located in the project construction area. Photo: QUACH DU

Notably, on the construction road there is a ancestral tomb of two families, making site clearance even more complicated. The investor has inventoried and approved the compensation and support plan, but the people have not yet agreed.

To speed up the progress, on December 2, the People's Committee of Thanh Hoa province issued a document directing and requesting relevant units to review the area of land that has not been cleared, at the same time arrange resettlement and study the plan to relocate the cemetery.

Canh ngon ngang tren cong truong thi cong tuyen duong hon 630 ti dong dang cham tien do. Anh: QUACH DU
The messy scene at the construction site of the more than 631 billion VND road is behind schedule. Photo: QUACH DU

The Provincial People's Committee also requested the locality to organize conferences, mobilize and propagate so that people can agree on compensation and resettlement support plans, and soon complete site clearance work for project construction.

QUÁCH DU
RELATED NEWS

General review of slow-progressing projects in Nghe An

|

Nghe An - Units review and fully update the status of the project behind schedule to advise the Provincial People's Committee to develop an inspection plan for 2026.

The road connecting Do Duc Duc Duc - Me Tri becomes a black spot for waste due to project delays

|

Hanoi - The road connecting Do Duc Duc - Me Tri is degraded, flooded with garbage and odor, causing danger to people while the project has been behind schedule for many years.

7 years of living next to a slow-progressing project in Tam Trinh

|

Hanoi - For the past 7 years, people living next to the Tam Trinh road expansion project have had to endure dust and chaos due to the project's long schedule.

Vietnam vs Myanmar women's football match schedule at SEA Games 33

|

The Vietnam women's team will face Myanmar in the final match of the 33rd SEA Games group stage, taking place at 4:00 p.m. on December 11.

Chairman of Son Hai Group raised problems with land obligations in Quang Tri

|

At the 5th session of the Quang Tri Provincial People's Council, Chairman of the Board of Members of Son Hai Group raised many problems arising from land obligations in the province.

Airline must compensate passengers for flight cancellations

|

The Civil Aviation Law has added many obligations of airlines towards passengers in allowing flights to be delayed or canceled.

Salary statement for the entire company when applying for CT3 Kim Chung social housing - unreasonable requirement

|

Hanoi - People submitting documents at the CT3 Kim Chung social housing project said that they were required to present the salary table of the entire agency.

Live SEA Games 33 today (December 10): Vietnamese sports delegation takes part

|

Live updated competition events of Vietnamese sports at today's 33rd SEA Games (December 10).

General review of slow-progressing projects in Nghe An

QUANG ĐẠI |

Nghe An - Units review and fully update the status of the project behind schedule to advise the Provincial People's Committee to develop an inspection plan for 2026.

The road connecting Do Duc Duc Duc - Me Tri becomes a black spot for waste due to project delays

HỮU VŨ |

Hanoi - The road connecting Do Duc Duc - Me Tri is degraded, flooded with garbage and odor, causing danger to people while the project has been behind schedule for many years.

Dự án chậm tiến độ, người mua nhà khó đủ đường

Bảo Chương |

TPHCM - Người mua nhà dự án chung cư Dream Home Riverside bức xúc vì đã đóng hơn 70% số tiền nhưng quá thời hạn bàn giao, dự án vẫn đứng hình.

7 years of living next to a slow-progressing project in Tam Trinh

Hữu Vũ |

Hanoi - For the past 7 years, people living next to the Tam Trinh road expansion project have had to endure dust and chaos due to the project's long schedule.