Ho Chi Minh City gateway expansion project: The district has completed site reporting, the investor says there are still problems

MINH QUÂN |

HCMC - The National Highway 50 expansion project reported by Binh Chanh District has completed site clearance, but the investor said there are still 3 areas that have not been handed over.

The National Highway 50 expansion project is invested by the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board), starting construction at the end of 2022.

The total investment capital of the project is about 1,500 billion VND and the implementation period will last until 2025.

The entire route is nearly 7 km long, passing through Binh Chanh district, including two main items: building a new parallel road 4.2 km long and expanding the existing National Highway 50 section from a cross-section of 7 m to 34 m with 6 lanes for traffic.

This is a key project to reduce traffic pressure and improve regional connectivity between Ho Chi Minh City and the Western provinces.

On December 30, 2024, a parallel road section of about 2 km long (from near the intersection of Trinh Quang Nghi Street to the entrance to National Highway 50) was technically opened to traffic, contributing to "resolving" the initial bottleneck for this traffic axis.

Up to now, the parallel section has been constructed at about 90% of the volume; the entire project has reached about 67%.

In a recent document sent to Binh Chanh District, the Traffic Department said that the project still has 3 locations that have not been handed over.

At the parallel section of National Highway 50, a household near the intersection of Trinh Quang Nghi Street has not yet handed over the site despite having begun cleaning. According to the scheduled schedule, this household will hand over on May 15.

At the existing National Highway 50 expansion section, a household has not agreed to hand over land due to not completing the procedures to receive resettlement land.

In addition, in the Ong Thin bridge area, a household, although previously handed over the site, has suddenly obstructed construction since April 26, 2025 until now with the reason of not receiving compensation.

It is worth mentioning that in the report sent to the Ho Chi Minh City People's Committee on April 23, the Binh Chanh District People's Committee affirmed that the site clearance work for the National Highway 50 project has been completed.

According to the report, after the process of contacting, mobilizing and persuading, all affected households demolished their houses and works and agreed to hand over the land.

Faced with the above situation, the Ho Chi Minh City Traffic Construction Investment Project Management Board has recommended that the People's Committee of Binh Chanh District continue to work with relevant units, especially households still stuck, to quickly hand over the site and ensure project progress.

MINH QUÂN
TIN LIÊN QUAN

The 1,500 billion VND project to expand the southern gateway of Ho Chi Minh City has completed 100% of the site

|

HCMC - The National Highway 50 expansion project, the southern gateway of HCMC, with a total capital of VND1,500 billion, through Binh Chanh district has completed 100% of the site.

1,500 billion VND project to expand gateway to Ho Chi Minh City is stuck with 5 land plots

|

HCMC - The project to expand National Highway 50, the southern gateway of HCMC, with a total capital of VND1,500 billion, is still stuck with 5 sites, affecting the construction progress.

The 1,500 billion VND project to expand the gateway to Ho Chi Minh City is "stuck" because of 8 houses

|

HCMC - The 1,500 billion VND National Highway 50 expansion project has been stalled because 8 houses have not been cleared, causing the parallel road to be interrupted even though it is 75% complete.

male shipper was beaten by lightning while delivering goods in heavy rain

|

Quang Tri - A young man working as a shipper was hit by a lightning while riding a motorbike in the rain, and is currently being treated in a deep coma.

Live football Hanoi Police 0-0 Hong Linh Ha Tinh: End of the first half

|

Live match between Hanoi Police and Hong Linh Ha Tinh in round 22 of V.League 2024-2025, taking place at 7:15 p.m. today (May 9).

Green credit and confidence in the future of Vietnam's circular economy

|

Green credit is not simply a supporting cash flow, but a belief that promotes a Vietnam developing towards a circular and sustainable economy.

The final concert of Say Hi Brother, ticket brokers are bustling across My Dinh

|

Hanoi - Before the final concert of Say Hi Brother at My Dinh, ticket brokers were active, while audiences flocked to the capital to meet their idol in the first season for the last time.

Green credit requires a separate mechanism for green industrial parks

|

The Standing Deputy Governor of the State Bank of Vietnam (SBV) said that there should be a separate policy mechanism for green credit in green industrial parks.

The 1,500 billion VND project to expand the southern gateway of Ho Chi Minh City has completed 100% of the site

Minh Tâm |

HCMC - The National Highway 50 expansion project, the southern gateway of HCMC, with a total capital of VND1,500 billion, through Binh Chanh district has completed 100% of the site.

1,500 billion VND project to expand gateway to Ho Chi Minh City is stuck with 5 land plots

MINH QUÂN |

HCMC - The project to expand National Highway 50, the southern gateway of HCMC, with a total capital of VND1,500 billion, is still stuck with 5 sites, affecting the construction progress.

The 1,500 billion VND project to expand the gateway to Ho Chi Minh City is "stuck" because of 8 houses

MINH QUÂN |

HCMC - The 1,500 billion VND National Highway 50 expansion project has been stalled because 8 houses have not been cleared, causing the parallel road to be interrupted even though it is 75% complete.