National Highway 13 expansion project: Reviewing legal documents and outstanding issues

ĐÌNH TRỌNG |

Ho Chi Minh City - Departments and branches of Ho Chi Minh City are reviewing legal documents and outstanding issues related to the project to upgrade and expand National Highway 13 section through the old Binh Duong province.

According to the Ho Chi Minh City People's Committee, the city has issued a document on reviewing contents related to the BOT project - upgrading and expanding National Highway 13 section through the old Binh Duong province.

Accordingly, the Ho Chi Minh City People's Committee agreed with the proposal of the Ho Chi Minh City Department of Finance to establish a Working Group to resolve problems related to the project, review legal documents and related backlogs. At the same time, advise on handling and resolving the conclusions and directions of the old Inspectorate of the Ministry of Planning and Investment, the Inspectorate of the Ministry of Finance and the State Audit of Region IV.

Currently, the Department of Construction is coordinating with departments and branches to implement tasks to ensure progress according to the direction of the Ho Chi Minh City People's Committee.

Đoạn dài khoảng 9,5km đã cơ bản hoàn thành mở rộng lên 9 làn xe. Ảnh: Đình Trọng
The section about 9.5km long has basically been completed and expanded to 8 lanes. Photo: Dinh Trong

It is known that the project to expand National Highway 13 from 6 to 8 lanes, a section nearly 15km long, was started in early 2022. The initial investment capital was 1,400 billion VND, then approved for adjustment to 6,255 billion VND.

This project was implemented in BOT form and was approved for investment policy by the old Binh Duong Provincial People's Council from 2019, then the investment policy was adjusted in 2024. After the State Audit Office gave opinions on the project, in June 2025, the old Binh Duong Provincial People's Council continued to approve the investment policy adjustment.

According to records, the 9.5km section from Ong Bo bridge intersection to Le Hong Phong intersection has completed asphalt paving to expand from 6 to 8 lanes. The remaining section is being accelerated in construction progress.

Đây là dự án quan trọng cửa ngõ vào trung tâm TPHCM. Ảnh: Đình Trọng
This is an important project at the gateway to the center of Ho Chi Minh City. Photo: Dinh Trong
Sau 4 năm khởi công, dự án vẫn chưa hoàn thành. Ảnh: Đình Trọng
After 4 years of construction, the project is still not completed. Photo: Dinh Trong
ĐÌNH TRỌNG
RELATED NEWS

The 6km section of the National Highway 13 expansion project in Ho Chi Minh City is expected to be completed in 2025

|

HCMC - The project to upgrade and expand National Highway 13 is making efforts to speed up the construction progress in sections that have been cleared.

Messy images at the construction site of Highway 13 expansion project

|

The project to upgrade and expand National Highway 13 in Binh Duong is behind schedule, the construction site is still messy, causing many inconveniences and difficulties for the people.

Ho Chi Minh City tells heritage stories using digital platforms

|

Not only promoting destinations, Ho Chi Minh City applies digital platforms to tell stories about heritage and culture, thereby bringing traditional values closer to the public.

Road congestion leading to the bridge in Da Nang, people face difficulties when traveling

|

Da Nang - Technical opening to traffic from the end of March 2025, but Quang Da bridge has not yet been able to operate due to congestion on the access road. Local people are worried about traffic unsafety.

Chemistry answer key for the 2026 high school graduation exam, full set of exam codes

|

Suggested answers for the full set of Chemistry exam codes in the 2026 high school graduation exam are quickly and accurately updated by Lao Dong Newspaper.

Answer key for Physics subject of the 2026 high school graduation exam, full set of exam codes

|

Suggested answers for the full set of Physics exam codes in the 2026 high school graduation exam are quickly and accurately updated by Lao Dong Newspaper.

The 6km section of the National Highway 13 expansion project in Ho Chi Minh City is expected to be completed in 2025

ĐÌNH TRỌNG |

HCMC - The project to upgrade and expand National Highway 13 is making efforts to speed up the construction progress in sections that have been cleared.

Messy images at the construction site of Highway 13 expansion project

ĐÌNH TRỌNG |

The project to upgrade and expand National Highway 13 in Binh Duong is behind schedule, the construction site is still messy, causing many inconveniences and difficulties for the people.

TPHCM xác định thời điểm khởi công dự án mở rộng Quốc lộ 13

MINH QUÂN |

TPHCM - Dự án mở rộng Quốc lộ 13 lên 53 - 60m, tổng vốn khoảng 13.851 tỉ đồng được lên kế hoạch khởi công dịp 30.4.2025.