Quang Tri airport project commits to implementing dust reduction solutions

HƯNG THƠ |

Quang Tri - After reflecting on the dust situation at the Quang Tri airport project overflowing into residential areas, the investor has proposed remedial solutions.

On July 24, according to a representative of the Quang Tri Airport Project Management Board, the construction area of the Quang Tri Airport (airport) Project entered the peak of prolonged hot and dry weather, directly affected by southwest wind (Laos wind) with very high intensity. This is an objective weather factor that strongly increases the phenomenon of dust spreading at the construction site.

In particular, the project scale has a very large ground with a length of about 3 km, a width of about 500 m, the airport ground elevation has been elevated according to the technical design. Therefore, when encountering strong winds blowing through, the fine layer of dust on the construction surface easily rolls up and spreads widely to surrounding residential areas.

To limit the impact on people, a representative of the unit said that the construction site currently maintains 7 specialized water trucks, operating in rotation continuously from 5:00 am to 6:00 pm daily on official roads and key areas. However, due to the extremely dry weather, dust suppression work still faces many challenges.

Faced with the above situation, the Project Management Board is committed to synchronously implementing many technical solutions and reorganizing construction to more thoroughly control pollution in the coming time.

Specifically, construction vehicles will be planned and diverted to move centrally along fixed service roads to optimize watering and dust suppression. Use K90 soil (a type of soil with high humidity and adhesion, serving for later finishing grass planting) to immediately cover surface areas that have met the conditions to prevent dust from spreading.

In addition, the Quang Tri Airport Project Management Board requested contractors to review and reduce the number of vehicles operating regularly from 250 vehicles to about 30-40 vehicles/day. Closely coordinate with local authorities and departments and branches to arrange more water supply points, and at the same time mobilize more specialized irrigation vehicles to serve the construction site.

Previously, Lao Dong Newspaper reflected the situation of a "dust storm" swirling from the construction site into Nhi Ha village (Cua Viet commune), causing the lives of dozens of households to be seriously disrupted. Notably, fine dust covering the area makes visibility limited, many families are forced to take young children to other places to "evacuate" and must wear masks even when inside the house.

Quang Tri airport project is invested in the form of public-private partnership (PPP), started in July 2024 with a total investment of more than 5,800 billion VND. Recently, the project has officially been adjusted from a 4C-class airport to a 4E-class, allowing the reception of modern wide-body aircraft such as Boeing 787 and Airbus A350.

Currently, items such as air traffic control towers and passenger terminals have basically completed the main structural items. The runway item has been completed.

HƯNG THƠ
RELATED NEWS

Fine dust at Quang Tri airport project continues to flood into residential areas

|

Quang Tri - Fine dust from the construction site of Quang Tri airport is rolling up, disrupting people's lives, many households have to take young children to other places to evacuate.

Quang Tri airport accelerates progress after conclusion of Government Inspectorate

|

Quang Tri - After the Government Inspectorate clearly pointed out the shortcomings and violations, relevant units focused on overcoming them and accelerating the progress of the Quang Tri Airport Project.

Quang Tri airport project commits to implementing dust reduction solutions

|

Quang Tri - After reflecting on the dust situation at the Quang Tri airport project overflowing into residential areas, the investor has proposed remedial solutions.

Waiting for coach Kim Sang-sik's talent in using troops at ASEAN Cup 2026

|

According to expert Phan Anh Tu, the core of the Vietnamese team at ASEAN Cup 2026 is not any individual but the team playing under the talent of coach Kim Sang-sik.

Moment of choking up receiving back the portrait of the martyr's father

|

Old photos are restored, helping to preserve memories of the martyrs and return them to generations of relatives.

Proposal to increase minimum wage by 7.8%, workers have more hope of taking their children to school

|

The proposal to increase the minimum wage by 7.8% has received much expectation from many workers, contributing to helping them reduce spending pressure, especially the cost of raising children to study.

For the beauty queen to perform swimsuits in front of dozens of students, the Organizing Committee apologizes

|

Quang Ngai - The Organizing Committee of the Miss contest admitted to lacking flexibility in coordination, causing students to sit and watch the beauty queen perform in a swimsuit.

Fine dust at Quang Tri airport project continues to flood into residential areas

HƯNG THƠ |

Quang Tri - Fine dust from the construction site of Quang Tri airport is rolling up, disrupting people's lives, many households have to take young children to other places to evacuate.

Quang Tri airport accelerates progress after conclusion of Government Inspectorate

HƯNG THƠ |

Quang Tri - After the Government Inspectorate clearly pointed out the shortcomings and violations, relevant units focused on overcoming them and accelerating the progress of the Quang Tri Airport Project.

Dự án sân bay Quảng Trị sẽ giúp địa phương cất cánh bay lên

HƯNG THƠ |

Dự án đầu tư xây dựng Cảng hàng không Quảng Trị (sân bay Quảng Trị) đã chính thức khởi công xây dựng. Dự kiến dự án sẽ đi vào khai thác từ tháng 7.2026, đáp ứng nhu cầu vận tải đường hàng không ngày càng tăng cao, góp phần thúc đẩy phát triển chính trị, kinh tế, xã hội.