Hundred-billion project in Da Nang deployed for nearly 15 years still has no investment policy

Nguyễn Hoàng |

Da Nang - An urban project worth more than 442.9 billion VND has been implemented since 2011, but so far there has been no decision allowing investment according to regulations.

Da Nang Inspectorate has just issued a Conclusion clearly pointing out a series of shortcomings of the 50m land use strip project along Nguyen Tat Thanh extended road (section from National Highway 1A to the end of the Golden Hills City project boundary), invested by Trung Nam Joint Stock Company, implemented since 2011, but has not been completely completed to date.

According to the inspection conclusion, after several planning adjustments, the project of the 50m strip of Nguyen Tat Thanh extended road - the area adjacent to the west of Nguyen Luong Bang road to Nam O bridge, with a total planned area of nearly 295,000 m2.

The project is implemented in the area of Hoa Lien commune, former Hoa Vang district and Hoa Hiep Nam ward, former Lien Chieu district, now Hoa Lien commune and Hai Van ward, Da Nang city.

According to the investor's report, the total investment of the project is more than 442.9 billion VND; of which the technical infrastructure is more than 296.3 billion VND, excluding the investment cost of social housing projects of more than 146.5 billion VND.

Da Nang City Inspectorate determined that the project did not carry out procedures for selecting investors, deciding to allow investment, but only issued an official dispatch from the Chairman of Da Nang City People's Committee in August 2011, assigning Trung Nam Joint Stock Company as the investor. This does not ensure the order and procedures according to regulations.

Notably, by the time of inspection, the project had not yet been approved for investment policy by competent authorities. The inspection determined that this was a prolonged shortcoming, affecting the progress of completing legal procedures, land, finance and project implementation.

Because the project does not have an investment permit decision or investment policy from a competent authority, there are no contents or criteria for project management and implementation such as project name, implementation time, progress, objectives, investment scale, total investment, land allocation method, investor selection, planned area, transfer of part of the project...

Hàng trăm biệt thự xuống cấp trong khu đô thị sinh thái Golden Hills City bỏ hoang ở Đà Nẵng, gây lãng phí nguồn lực đất đai. Ảnh: Trường An
Trung Nam Joint Stock Company is also the investor of Golden Hills City Ecological Urban Area, Da Nang, with hundreds of villas in a state of abandonment and degradation. Photo: Truong An

In the field of planning, the Department of Construction was determined to have advised on approving and adjusting the 1/500 detailed plan of the project in the 2011-2013 period inconsistent with the general plan approved by the Prime Minister in Decision 1465/QD-TTg dated June 17, 2002. In addition, the process of preparing and advising on the 1/500 detailed plan of the project did not consider determining and allocating land funds for social housing construction according to regulations.

Regarding land, the Inspectorate of Da Nang City clearly pointed out that the Department of Agriculture and Environment's advice on allocating land to Trung Nam Joint Stock Company for management, to invest in projects without going through land use right auctions or bidding to select investors, is not guaranteed by regulations. Land allocation is also carried out when the project has not yet had an investment permit decision or investment policy.

Another shortcoming is that the project has changed planning many times but has not re-determined financial obligations. The Inspectorate of Da Nang City said that this makes it difficult for functional agencies to have sufficient grounds to carry out the next procedures related to site agreement, detailed planning adjustment, and adjustment of land allocation and land lease decisions.

Although the investor reported that about 95% of technical infrastructure has been completed, the project is still facing obstacles in site clearance, resettlement, relocation of graves, land legality and issuance of land use right certificates. The prolongation from 2011 to now has made the project area unable to be completed synchronously, affecting people's lives and the urban embellishment process in the northwest of Da Nang.

Một hộ dân tại Đà Nẵng cầu cứu vì vướng mắc đền bù liên quan đến dự án
A household in Da Nang reflected to Lao Dong Newspaper about compensation problems related to the 50m Nguyen Tat Thanh extended road project. Photo: Nguyen Linh

Da Nang City Inspectorate assessed that the project basically meets the requirements of infrastructure connection, urban embellishment, expansion of urban development space and serving resettlement and people's needs in the area, however, the implementation process still has many shortcomings and prolonged obstacles that need to be handled so that the project can complete procedures and continue to be implemented.

Chief Inspector of Da Nang City proposed that the City People's Committee direct departments, branches, localities and Trung Nam Joint Stock Company to review and handle existing problems and obstacles of the project; organize self-criticism, rectification, and drawing experience for relevant collectives and individuals.

The inspection conclusion also proposed that relevant units base on specific mechanisms and policies to remove difficulties, complete legal procedures, land, financial obligations, and site clearance, thereby soon putting the project into operation, contributing to improving the quality of social infrastructure and people's lives in the area.

Nguyễn Hoàng
RELATED NEWS

Da Nang spends 169 billion VND to clear ground for coastal flood prevention roads

|

Da Nang - Da Nang City People's Committee approves a site clearance compensation project worth more than 169 billion VND to build a road combined with a drainage culvert.

Unfinished bridges and roads, deserted villas, waste in Da Nang

|

Da Nang - Trillions of VND poured into infrastructure, but many roads, bridges, and resorts are still deserted, overgrown with weeds, wasting resources.

Da Nang Inspectorate proposes review of 240 collectives and individuals who made mistakes in 2025

|

Da Nang - A series of violations were detected, Da Nang Inspectorate proposed to review 81 collectives and 159 individuals in 2025.

Russia launches massive attacks on fuel tanks and Ukrainian military cargo ships

|

Seaport infrastructure and waterway supply continue to be priority targets in Russia's campaign to weaken the logistics of the Ukrainian army.

New low pressure strengthens into Typhoon Nangka, forecast direction in the next 24 hours

|

Tropical storm Nangka formed from a low pressure area and is currently more than 2,000km north of the northern tip of Luzon Island, moving eastward.

Thanh Hoa faces pressure to compensate for the gap to grow by 11%

|

Thanh Hoa - GRDP in 6 months increased by 7.21%, while public investment slowed down, putting great pressure on the growth target of 11% in 2026.

Weather today August 13: Northern region continues to be intensely hot

|

Weather today August 13, Northern region hot sunny day, hot sunny in some places, especially Lai Chau and Dien Bien sunny day, hot sunny in some places.

Product matrix for treating erectile dysfunction with "complete cure" commitment

|

Faced with the "matrix" of erectile dysfunction treatment products on the market, doctors warn men not to arbitrarily use the product without examination.

Da Nang spends 169 billion VND to clear ground for coastal flood prevention roads

Nguyễn Linh |

Da Nang - Da Nang City People's Committee approves a site clearance compensation project worth more than 169 billion VND to build a road combined with a drainage culvert.

Unfinished bridges and roads, deserted villas, waste in Da Nang

Nguyễn Hoàng |

Da Nang - Trillions of VND poured into infrastructure, but many roads, bridges, and resorts are still deserted, overgrown with weeds, wasting resources.

Da Nang Inspectorate proposes review of 240 collectives and individuals who made mistakes in 2025

Nguyễn Hoàng |

Da Nang - A series of violations were detected, Da Nang Inspectorate proposed to review 81 collectives and 159 individuals in 2025.