Ring Road 2.5 project through Khuong Dinh ward basically completed site clearance

HỮU CHÁNH |

Hanoi - Khuong Dinh Ward basically completed site clearance for the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, involving 736 cases.

The Ring Road 2.5 project, Nguyen Trai section (National Highway 6) - Dam Hong (Khuong Dinh ward, Hanoi) has a total length of about 1.52 km, with a cross-section scale of 40m of roadbed.

The total investment of the project is more than 2,432 billion VND, of which site clearance costs account for more than 2,001 billion VND.

To implement the project, Khuong Dinh ward must recover over 60,900 m2 of land, involving 736 cases, including 720 households, individuals and 16 organizations.

This is a large-scale project with a wide scope of impact, a very large and complex volume of site clearance work.

Talking to Lao Dong Newspaper, a representative of Khuong Dinh ward said that the ward has identified site clearance for the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, as a key political task, of particular importance to the development of the locality.

Therefore, the Party Committee and government of Khuong Dinh ward have focused on leading and directing drastically and synchronously.

The Site Clearance Steering Committee was established, clearly assigning people and tasks, promoting the role and responsibility of each individual and unit.

Ward leaders regularly directly go to the grassroots level to listen to and promptly resolve the legitimate thoughts and aspirations of the people, and remove arising difficulties and obstacles.

d
Secretary of the Party Committee of Khuong Dinh Ward Vo Dang Dung (white shirt) and Chairman of Khuong Dinh Ward People's Committee Nguyen Sy Doan regularly go to the scene to remove difficulties and obstacles arising when land is recovered for the Ring Road 2.5 project. Photo: Song Huu

Propaganda work is deployed flexibly with many diverse forms, from focused conferences, public dialogues to individual mobilization.

Accordingly, the ward has established 7 propaganda teams according to the area, "going through each alley, knocking on each house", closely following each household, thereby having an appropriate and effective approach. At the same time, 16 opinions-gathering conferences and 5 dialogue conferences have been organized publicly and transparently, contributing to creating high consensus in society.

By May 20, Khuong Dinh ward had completed the approval of the entire compensation, support, and resettlement plan for cases according to regulations.

Notably, most households agreed with the plan, of which 99% of households proactively handed over the land.

In addition, in order to support people to soon stabilize their lives and accelerate the project progress, the ward has mobilized socialization to support households to hand over land early with a level of 10 million VND/household, with a total cost of nearly 1.9 billion VND.

Households in difficult circumstances are also supported by the "For the Poor" Fund, showing the humanitarian spirit and responsibility of the local government.

To date, the ward has paid over 486 billion VND in compensation and support; completed the relocation of 100% of graves within the project area; and at the same time organized the dismantling of over 400 works of households that have handed over land.

s
Ring Road 2.5 project section passing through Khuong Dinh ward has basically completed site clearance. Photo: Song Huu

According to a representative of Khuong Dinh ward, the results achieved not only show the determination and responsibility of the Party Committee and local government but also affirm the spirit of consensus, for the common interests of the community and people of Khuong Dinh ward.

In the coming time, Khuong Dinh ward will continue to focus on paying compensation money, coordinating to hand over resettlement houses to people, and at the same time accelerate the progress of dismantling the remaining works, and soon hand over clean ground to the construction unit.

HỮU CHÁNH
RELATED NEWS

Hanoi sets deadline for completing site clearance of 3 bridges over the Red River, Ring Road 2.5

|

Hanoi City is focusing on deploying site clearance for a number of key transport projects such as 3 bridges over the Red River, and ring roads.

Can Gio - Vung Tau sea-crossing road project expected to be submitted to Ho Chi Minh City People's Council in June

|

Ho Chi Minh City accelerates completion of dossiers and procedures to submit to Ho Chi Minh City People's Council for consideration of investment policy for the sea-crossing road project connecting Can Gio - Vung Tau in June.

Increasing the capacity of Da Phuoc landfill landfill will go against the green city goal

|

Ho Chi Minh City - Increasing the landfill capacity of Da Phuoc landfill from 24 to 41 million tons not only increases the risk of pollution but also goes against the goal of developing green cities.

Government Inspectorate receives 7 deployed People's Police officers

|

The Government Inspectorate announced the decision to receive a public assignment for a limited time for 7 People's Police officers.

GPMB đường Vành đai 2,5 tại phường Thanh Xuân hoàn thành sau hơn 4 tháng

HOÀI ANH |

Hà Nội - Công tác giải phóng mặt bằng dự án đường Vành đai 2,5 đoạn Ngụy Như Kon Tum - Nguyễn Trãi về đích trong một thời gian ngắn (hơn 4 tháng).

Phường Thanh Xuân về đích trong công tác GPMB dự án đường Vành đai 2,5

HOÀI ANH |

Hà Nội - Tính đến thời điểm hiện tại, phường Thanh Xuân đã cơ bản hoàn thành công tác GPMB dự án đường Vành đai 2,5.

Hanoi sets deadline for completing site clearance of 3 bridges over the Red River, Ring Road 2.5

Anh Tuấn |

Hanoi City is focusing on deploying site clearance for a number of key transport projects such as 3 bridges over the Red River, and ring roads.