Hanoi Ring Road 4 project faces obstacles, risk of missing the completion date by the end of this year

SÓNG HỮU |

Hanoi - 11/17 wards and communes have not yet handed over enough land to the contractor, causing the project to build the Ring Road 4 parallel road to risk missing the completion date by the end of 2025.

Construction site is as good as it is

According to the reporter of Lao Dong Newspaper, in package No. 9 of the Ring Road 4 parallel road project in the Capital Region through Duong Hoa commune (Hanoi), dozens of machines and workers are implementing the asphalt paving project.

Mr. Nguyen Hoang Hai - Commander of Package 9, Vietnam Construction and Import-Export Corporation (Vinaconex) said that after about 2 years of construction, up to now, Package 9, nearly 22km long, has completed about 68% of the value of the package.

s
The parallel road of Ring Road 4 in the Capital Region through Duong Hoa Commune (Hanoi), afternoon of August 4. Photo: Song Huu
u
w
The asphalt paving items are being implemented by the contractor. Photo: Song Huu
Cong nhan lai may lam viec tren cong truong du an. Anh: Song Huu
Workers operate machinery at the project site. Photo: Song Huu

To complete the project by the end of this year, Mr. Hai said that the unit has deployed many construction teams, constructing "3 shifts"... trying to complete it according to the set schedule. However, the project implementation process has encountered many difficulties when there are still nearly 3km of the package that have not been cleared.

"Due to lack of clean land, these sections have been cut off, greatly affecting the simultaneous implementation of the entire route. In addition, all areas lacking land have not been implemented, which risks slowing down the overall progress of the entire project" - Mr. Nguyen Hoang Hai said.

Explaining the lack of land will greatly affect the progress of the parallel road by the end of this year, the commander of package 9 said that after having a clean site, the contractor can start construction, it will take at least 6 months to complete, while it is now the beginning of August.

There are still 18 points with land clearance problems

The project to build the parallel road of Ring Road 4 in the Capital Region through Hanoi city is about 57.52km, passing through 17 wards and communes.

According to the representative of the Hanoi Traffic Infrastructure Construction Investment Project Management Board, up to now, the capital has approved the plan and reclaimed 792.73/802.85 hectares of land. The remaining area of 10.12ha of 11/17 wards and communes; 590/953 households have been handed over residential land, of which 436/734 households have been resettled. The tomb was moved 10,338/10,345, with 7 remaining tombs.

In addition, the project has completed the relocation of high-voltage power. Localities are mobilizing technical infrastructure (medium-voltage, low-voltage, information systems, water supply, etc.) in the areas of 15/17 wards and communes. The volume of travel with this item reached about 70%. It is expected to complete the relocation of technical infrastructure items in August 2025 for the area not related to residential land.

Also according to the representative of the Hanoi Traffic Infrastructure Construction Investment Project Management Board, the site clearance rate for the entire project is currently nearly 99%. There are 18 interruptions on the route, which have not been cleared, mainly residential land.

Vanh dai 4 doan nut giao voi Quoc lo 32 (xa Hoai Duc, Ha Noi) chua duoc giai phong mat bang. Anh: Song Huu
The section of Ring Road 4 at the intersection with National Highway 32 (Hoai Duc Commune, Hanoi) has not been cleared. Photo: Song Huu

This is the most difficult part and needs to be completed as soon as possible to ensure overall progress. In addition, the supply of commercial construction materials is very scarce, pushing up costs, seriously affecting the progress and construction costs of many projects.

The Hanoi Traffic Infrastructure Construction Investment Project Management Board recommends that localities focus on resolving remaining difficulties and problems in site clearance, and promptly hand over the remaining site in September 2025.

SÓNG HỮU
RELATED NEWS

Struggling in the hot sun to construct the Ring Road 4 parallel road

|

Under the scorching sun, workers and laborers at the Ring Road 4 construction site are still working hard, determined to complete the project on schedule, with the highest quality and efficiency.

Workers " sunlight" to the peak, racing to progress the Ring Road 4 project in the Capital region

|

Hanoi - Under the harsh heat, workers are still actively constructing the Ring Road 4 parallel road project, completing the project as soon as possible, ensuring quality.

Ring Road 4 still has many households, Hanoi delays site clearance completion

|

Hanoi - The site clearance for the Ring Road 4 construction project has been postponed to the third quarter to resolve some remaining difficulties and problems.

HCMC proposes two options to apply the 2026 land price list

|

The Department of Agriculture and Environment of Ho Chi Minh City has just proposed two options to apply the land price list from 2026.

Vietnam women's team beat Indonesia 7-0 in Southeast Asia tournament

|

On the evening of August 9, the Vietnam women's team beat Indonesia 7-0 at the 2025 Southeast Asian Women's Football Championship.

Gia Lai discovers 100 tons of odorful frozen pork, unknown origin

|

Gia Lai - The authorities are handling and destroying 100 tons of stinking frozen pork, causing a change in color at the warehouse of a business household.

India stops buying US weapons after Mr. Trump's tariff imposition

|

India-US defense relations have been affected as plans for new weapons purchases have stalled due to trade tensions.

Emptiness in regulations to turn collecting USD for sale on the black market into a fatty cake

|

A familiar USD collection ring for bank employees returns after 3 years, taking advantage of loopholes to legalize transactions, threatening to stabilize the foreign exchange market.

Struggling in the hot sun to construct the Ring Road 4 parallel road

Hữu Chánh |

Under the scorching sun, workers and laborers at the Ring Road 4 construction site are still working hard, determined to complete the project on schedule, with the highest quality and efficiency.

Workers " sunlight" to the peak, racing to progress the Ring Road 4 project in the Capital region

HỮU CHÁNH |

Hanoi - Under the harsh heat, workers are still actively constructing the Ring Road 4 parallel road project, completing the project as soon as possible, ensuring quality.

Ring Road 4 still has many households, Hanoi delays site clearance completion

SÓNG HỮU |

Hanoi - The site clearance for the Ring Road 4 construction project has been postponed to the third quarter to resolve some remaining difficulties and problems.