Hanoi has just supplemented the list of 873 land acquisition projects to implement socio-economic development projects for national and public interests with a total land area of 11,563.83ha.
In Dai Mo ward, it is expected to recover more than 11ha of land to implement 2 projects.
Accordingly, the city will recover 6.57ha of land to invest in building technical infrastructure for the ĐM2 resettlement area and recover 4.5ha of land for the purpose of building road sections connecting ĐM1 areas, ĐM2 resettlement area, Dai Mo urban functional area and B32.
| STT | List of works, projects | Land use purpose (Land type code) | Registered unit, organization | Project area (ha) | Land area recovered (ha) |
|---|---|---|---|---|---|
| 1 | Investing in building technical infrastructure for resettlement area DM2, Dai Mo ward | ODT, other types of soil | Dai Mo Ward DTHT Project Management Board | 6.57 | 6.57 |
| 2 | Construction of road sections connecting NM1 areas, NM2 resettlement area, Dai Mo urban functional area and B32, Dai Mo ward | DGT | Dai Mo Ward DTHT Project Management Board | 4.5 | 4.5 |