Nearly 10km road connecting Cai Mep port with National Highway 51 and expressway reaches 95% progress

THÀNH AN |

Ho Chi Minh City - Road 991B connecting Cai Mep port area with National Highway 51 and Bien Hoa - Vung Tau expressway has reached about 95% progress, expected to be operational by the end of 2026.

On September 6, the Ho Chi Minh City Traffic Construction Investment Project Management Board (abbreviated as the Traffic Board) said that road 991B, which is more than 9.7km long, connecting the downstream area of Cai Mep port to National Highway 51, has gradually been completed; it is expected to be completed and put into operation at the end of 2026.

Previously, the project started in 2018 and was expected to be completed in 2024. However, due to many difficulties and obstacles in the implementation process, it has been adjusted the construction progress by competent authorities many times.

According to the Traffic Board, the progress and quality of work are being implemented to ensure compliance with the signed contract, and the total construction value of the bidding packages is estimated to reach about 95%.

In which, package No. 36 (from downstream Cai Mep to Mo Nhat bridge) has completed more than 97% of the construction output, with Rach Ong and Mo Nhat bridges completed. Package No. 37 (from National Highway 51 to Mo Nhat bridge) has been completed about 85%, of which the overpass section of National Highway 51 reached 99%; Rach Tre bridge reached 85%.

Recorded at the construction site, the project has been asphalted over a length of more than 7km from the downstream area of Cai Mep, along with sections on Rach Ong bridge, Mo Nhat, National Highway 51 overpass. Construction teams are quickly deploying to complete the remaining sections.

Đơn vị thi công đang nhanh chóng triển khai hoàn tất các phần còn lại của dự án. Ảnh: Thành An
The construction unit is quickly deploying to complete the remaining parts of the project. Photo: Thanh An

After completion and commissioning at the end of 2026, the project will contribute to completing and synchronizing the freight transport route for the Cai Mep - Thi Vai international gateway seaport complex. At the same time, it will support connecting Long Son industrial park to National Highway 51 and to Bien Hoa - Vung Tau expressway. Thereby, creating convenience in freight transport and serving the travel needs of people, contributing to promoting socio-economic development in the region in particular and the whole country in general.

Road 991B from National Highway 51 to the downstream Cai Mep port is about 9.73km long, started in 2018, expected to be completed in 2024, with a total initial investment of more than 3,951 billion VND. Among them, there are 4 bridges including: National Highway 51 overpass, Rach Tre bridge, Mo Nhat bridge, Rach Ong bridge.

After many adjustments and extensions of the progress, the 991B road project is expected to be completed and put into use by the end of 2026, with a total investment of more than 3,043 billion VND.

Sơ đồ tuyến đường 991B kết nối khu vực cảng Cái Mép - Thị Vải với Quốc lộ 51 và cao tốc Biên Hòa - Vũng Tàu. Ảnh: Google maps
Map of route 991B connecting Cai Mep - Thi Vai port area with National Highway 51 and Bien Hoa - Vung Tau expressway. Photo: Google maps
THÀNH AN
RELATED NEWS

3 projects connecting Long Thanh airport are slow to cut down rubber trees

|

Dong Nai - 3 transport projects connecting Long Thanh airport, about 110km long, are slow to cut down rubber trees, making the construction site look like leopards, making it difficult to access the construction site.

After National Highway 13, Ho Chi Minh City will soon build 5 more projects connecting the old Binh Duong area

|

Ho Chi Minh City - After starting the expansion of National Highway 13, Ho Chi Minh City is preparing to deploy 5 more projects with a total capital of nearly 90,000 billion VND connecting the Binh Duong area before.

Dong Nai publicly announces compensation plan for 6-lane road project connecting airport

|

Dong Nai - Phuoc Thai Commune People's Committee publicly announced the compensation and support plan for the 770B road project (phase 7) with 41 cases.

Forecast for the North to welcome early-season cold air causing thunderstorms

|

It is forecasted that around September 9-10, the North will welcome a wave of weak-intensity early-season cold air, the temperature will not fluctuate much.

Iran attacks US unmanned ship in the Strait of Hormuz

|

Iran on September 6 announced that its forces had attacked a US Navy unmanned ship.

3 projects connecting Long Thanh airport are slow to cut down rubber trees

HÀ ANH CHIẾN |

Dong Nai - 3 transport projects connecting Long Thanh airport, about 110km long, are slow to cut down rubber trees, making the construction site look like leopards, making it difficult to access the construction site.

After National Highway 13, Ho Chi Minh City will soon build 5 more projects connecting the old Binh Duong area

MINH QUÂN |

Ho Chi Minh City - After starting the expansion of National Highway 13, Ho Chi Minh City is preparing to deploy 5 more projects with a total capital of nearly 90,000 billion VND connecting the Binh Duong area before.

Dong Nai publicly announces compensation plan for 6-lane road project connecting airport

HÀ ANH CHIẾN |

Dong Nai - Phuoc Thai Commune People's Committee publicly announced the compensation and support plan for the 770B road project (phase 7) with 41 cases.