Road worth over 1,300 billion VND in Hanoi untangled after 12 years of construction

SÓNG HỮU |

Hanoi - After receiving the final land area, the investor will focus on completing the Ring Road 2.5 project, with a total capital of more than 1,300 billion VND.

According to Lao Dong's records on May 5, at the Ring Road 2.5 project, Dam Hong - National Highway 1A section, the contractor has basically completed the section from Dam Hong to alley 192 Le Trong Tan street with a length of more than 300m.

Previously, on February 10, the section from alley 192 Le Trong Tan to the connecting point with Kim Dong - Giai Phong underpass with a length of about 1,280m was technically opened to traffic, serving the travel needs of people.

Currently, the starting point of the project at Dam Hong is still a dead end, waiting for the Ring Road 2.5 project, Nguyen Trai - Dam Hong section to be completed to maximize investment efficiency.

a
The starting point of the Ring Road 2.5 project, Dam Hong - National Highway 1A section (Hanoi) has been basically completed. Photo: Song Huu
a
Traffic sign system installed on the route. Photo: Song Huu
a
The road surface is paved with asphalt, painted with road markings, people can travel conveniently. Photo: Song Huu
a
Workers complete the sidewalk item at the beginning of the route. Photo: Song Huu

Talking to Lao Dong Newspaper, a representative of Hoang Mai Construction Investment Co., Ltd. - Hanoi (the project enterprise) said that by the end of April 2026, obstacles in site clearance related to 2 households (belonging to Phuong Liet ward) with a recovered land area of about 60m2 had been resolved.

Up to now, the work of collecting assets and belongings to serve the demolition of the project is being implemented by the relevant parties.

After receiving the handover of the final site, the contractor will immediately deploy the construction to complete the sidewalk item at the intersection with Tran Nguyen Dan street, ensuring progress and quality of the project.

a
Ring Road 2.5, Dam Hong - National Highway 1A section has a length of 1.6km, cross-section 40m. Photo: Song Huu
a
L3 bridge across the Lu River belongs to Ring Road 2.5. Photo: Song Huu
a
Sidewalk, lighting, green trees,... items have been completed. Photo: Song Huu
a
The end point of the route connects to the Kim Dong - Giai Phong intersection underpass. Photo: Song Huu

The investment project to build Ring Road 2.5, Dam Hong - National Highway 1A section was started in 2014 with a length of 1.6km, total investment of about 1,317 billion VND under the BT (build - transfer) contract form, expected to be completed in 2017.

However, the project progress was delayed due to problems in site clearance and waiting for BT contract extension.

By 2020, when only about 40% of the workload was completed, the project had to be temporarily suspended.

After 5 years of suspension, by the end of May 2025, Hoang Mai - Hanoi Co., Ltd. will organize a restarting ceremony for the 2.5 Ring Road project, Dam Hong - National Highway 1A section.

The completed and put into use route will help reduce congestion, change the urban appearance, and contribute to socio-economic development in the southern area of the Capital.

SÓNG HỮU
RELATED NEWS

2 last households dismantle houses, hand over land for Ring Road 2.5 project in Hanoi

|

Hanoi - The investor of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, has been handed over 100% of the clean site, and is deploying construction to complete the road.

US - Iran: Ceasefire agreement increasingly fragile

|

The ceasefire agreement in the Middle East is facing the risk of collapse as the US and Iran continue military actions to control the Strait of Hormuz.

Fearing communication disruption, users urgently verify subscribers

|

Hanoi - Network operators are always crowded with customers when deploying subscriber authentication, many people are worried about interrupting communication if they do not standardize information in time.

2 low pressure systems move towards the Philippines, possibly strengthening into Typhoon Caloy

|

Two low pressure systems are moving towards the Philippines, one of which enters the forecast area on May 5, while the other low pressure system is strengthening.

Scene of the chain collision at the beginning of Thang Long bridge, the car was crushed

|

Hanoi - A series of accidents at the beginning of Thang Long bridge (direction to Dong Anh) caused many vehicles to be heavily damaged.

Lãnh đạo phường xuyên lễ bám thực địa, thúc tiến độ GPMB dự án Vành đai 2,5

HỮU CHÁNH |

Hà Nội - Sự hiện diện thường xuyên của lãnh đạo phường Khương Đình ở hiện trường trong dịp lễ thể hiện tinh thần trách nhiệm trong GPMB dự án Vành đai 2,5.

Phường Thanh Xuân duyệt chi trả tiền bồi thường Vành đai 2,5 đạt gần 50%

HOÀI ANH |

Hà Nội - Công tác duyệt chi trả tiền bồi thường, tái định cư dự án Vành đai 2,5 tại phường Thanh Xuân đạt xấp xỉ 50%.

2 last households dismantle houses, hand over land for Ring Road 2.5 project in Hanoi

SÓNG HỮU |

Hanoi - The investor of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, has been handed over 100% of the clean site, and is deploying construction to complete the road.