Urgently remove obstacles at Ring Road 2.5 project with a capital of over 1,300 billion VND

SÓNG HỮU |

Hanoi - Relevant units are coordinating site clearance for investors to complete the Ring Road 2.5 project, Dam Hong - National Highway 1A section.

The Ring Road 2.5 project, Dam Hong - National Highway 1A section, technically opened to traffic on February 10, 2026, but there are still obstacles in site clearance (GPMB) that have not been completely resolved.

Accordingly, in Phuong Liet ward, there are still 2 households with an area of 59.3m2 (1 household recovered 6.1m2/129.8m2 and 1 household recovered 53.2m2/110.9m2) belonging to the Dinh Cong Central Construction Area project (now Dinh Cong New Urban Area) of Housing and Urban Development Investment Corporation (HUD Corporation) located in the sidewalk area of Ring Road 2.5 project that have not carried out site clearance work.

The Hanoi Traffic Construction Investment Project Management Board has proposed to the City People's Committee to consider and give opinions directing HUD Corporation to sign a land clearance contract with Phuong Liet Ward People's Committee for 2 households with an area of 59.3m2 located within the boundary of Ring Road 2.5.

d
d
59.3m2 of land in Phuong Liet ward (Hanoi) has not been handed over to the Ring Road 2.5 project, Dam Hong - National Highway 1A section. Photo: Song Huu

Phuong Liet Ward People's Committee said that it has assigned the Economic, Infrastructure and Urban Department to contact Dinh Cong Ward People's Committee to study land management records in the GPMB area related to the above 2 households (before July 1, 2025, this GPMB location belonged to Dinh Cong Ward).

The Investment - Infrastructure Project Management Board summarizes legal documents to serve the site clearance work of the project; continues to advise the Ward People's Committee to send documents to the Hanoi Institute of Construction Planning to collect documents and drawings; based on the legal documents provided and supplemented by HUD Corporation, assign the Investment - Infrastructure Project Management Board to sign a contract with HUD Corporation to deploy some contents related to site clearance work in advance.

Ward police grasp the security and order situation in the area, classify subjects whose land is recovered to grasp the thoughts and aspirations of households to have a basis for propaganda and mobilization from the first day of deploying site clearance work.

d
d
The slow handover of land has caused the sidewalk construction item at the intersection of Ring Road 2.5 with Tran Nguyen Dan street not to be completed. Photo: Song Huu

On April 13, 2026, the Phuong Liet Ward Investment - Infrastructure Project Management Board signed Contract No. 92/HDKT-BQLDA-HUD with HUD Corporation on the implementation of compensation, support, and resettlement work to serve the site clearance of the Dinh Cong Concentrated Construction Area project (now Dinh Cong New Urban Area), Phuong Liet ward.

Phuong Liet Ward proposed that HUD Corporation deduct 80% of the amount of 134,389,000 VND (equivalent to 107,511,000 VND) to the account of the Phuong Liet Ward Investment - Infrastructure Project Management Board to implement the land clearance and land acquisition steps according to regulations and hand over to the construction contractor for the Ring Road 2.5 Dam Hong - National Highway 1A project.

The investment project to build Ring Road 2.5, Dam Hong - National Highway 1A section was started in 2014 with a length of 1.6km, total investment of about 1,317 billion VND under the BT (build - transfer) contract form, expected to be completed in 2017.

However, the project progress was delayed due to problems in site clearance and waiting for BT contract extension.

By 2020, when only about 40% of the workload was completed, the project had to be temporarily suspended.

d
1. 2/1. 6km of Ring Road 2. 5, Dam Hong - National Highway 1A section technically opened to traffic on February 10. 2. Photo: Song Huu

After 5 years of suspension, by the end of May 2025, Hoang Mai - Hanoi Construction Investment Co., Ltd. (project enterprise) will organize the Groundbreaking Ceremony for the 2.5 Ring Road project, Dam Hong - National Highway 1A section.

For the section from Km0+320 (lane 192 Le Trong Tan) to Km1+600 (location adjacent to the underpass of Ring Road 2.5 and Giai Phong road) with a length of 1,280m, technical traffic has been opened from February 10, 2026.

SÓNG HỮU
RELATED NEWS

Bridge and road project worth nearly 10,200 billion VND in Hanoi is under construction and waiting for site clearance

|

Hanoi - The site has not been completely handed over, affecting the progress of the Ngoc Hoi bridge and approach roads at both ends of the bridge, with a total capital of nearly 10,200 billion VND.

Trillion-VND road in Hanoi has been technically opened to traffic but still has site clearance problems

|

Hanoi - Ring Road 2.5, Dam Hong section - National Highway 1A, technically opened to traffic 2 months ago, but so far site clearance has not been completed.

Hanoi removes site clearance, accelerates construction of Ring Road 2.5 - Linh Nam

|

Hanoi accelerates site clearance for Ring Road 2.5 - Linh Nam project, but many obstacles put the progress at risk of slowing down.

Prime Minister Le Minh Hung approves personnel for Dong Nai province

|

Prime Minister Le Minh Hung approved the election results for the position of Vice Chairman of Dong Nai Provincial People's Committee with Mr. Nguyen Tuan Anh - Director of the Department of Agriculture and Environment.

Innovation 1-1 for students on grade 3 textbooks with "black" links

|

HUE - ESVN recalls books with unsafe links, innovates 1-1, supports at schools and nationwide, and coordinates to block malicious links.

The world's strongest super typhoon Sinlaku is about to make landfall, high risk of disaster

|

Super typhoon Sinlaku - the strongest storm on the planet this year - is approaching US islands in the Western Pacific.

HCMC leaders meet with Lao and Cambodian students studying in the city

|

Ho Chi Minh City - The program of Ho Chi Minh City leaders meeting with Lao and Cambodian students studying in Ho Chi Minh City took place on the evening of April 13.

Bridge and road project worth nearly 10,200 billion VND in Hanoi is under construction and waiting for site clearance

SÓNG HỮU |

Hanoi - The site has not been completely handed over, affecting the progress of the Ngoc Hoi bridge and approach roads at both ends of the bridge, with a total capital of nearly 10,200 billion VND.

Trillion-VND road in Hanoi has been technically opened to traffic but still has site clearance problems

SÓNG HỮU |

Hanoi - Ring Road 2.5, Dam Hong section - National Highway 1A, technically opened to traffic 2 months ago, but so far site clearance has not been completed.

Hanoi removes site clearance, accelerates construction of Ring Road 2.5 - Linh Nam

Minh Hạnh |

Hanoi accelerates site clearance for Ring Road 2.5 - Linh Nam project, but many obstacles put the progress at risk of slowing down.