Road worth over 1,300 billion VND in Hanoi completed all items in March

SÓNG HỮU |

Hanoi - Ring Road 2.5 project, Dam Hong - National Highway 1A section, 1.6km long, with a total capital of over 1,300 billion VND, will complete all items in March 2026.

The Ring Road 2.5 construction project, Dam Hong - National Highway 1A section, is invested in the form of a BT (build - transfer) contract with a length of 1.6km, a cross-section of 40m, and a total investment of over 1,300 billion VND.

The project started in 2014, was expected to be completed in 2017 but was delayed.

By 2020, the project was temporarily suspended when it had only reached about 40% of the workload. The reason was due to problems in site clearance and extension of the BT contract appendix.

After 5 years of suspension, by the end of May 2025, with the permission of the Hanoi People's Committee, Hoang Mai - Hanoi Construction Investment Co., Ltd. (the project enterprise) organized the Groundbreaking Ceremony for the 2.5 Ring Road Construction Project, Dam Hong - National Highway 1A section.

a
Ring Road 2.5, Dam Hong - National Highway 1A section (Hanoi) has a cross-section of 40m. Photo: Song Huu
a
L3 bridge across the Lu River on Ring Road 2.5. Photo: Song Huu

On February 10, the 2.5 Ring Road project, Dam Hong - National Highway 1A section, was technically opened to traffic, ensuring synchronous connection with the technical opening plan of the 2.5 Ring Road - Giai Phong underpass project, serving people to travel to welcome the Binh Ngo Lunar New Year.

Ms. Nguyen Thi Bich Ngoc (resident of Dinh Cong ward) said that she and many people in the area are very excited that the project has been opened to traffic after many years of waiting.

The completed road not only helps reduce traffic congestion, serve people's travel but also changes the face of the area, contributing to promoting local socio-economic development" - Ms. Ngoc said.

According to the Hanoi Traffic Construction Investment Project Management Board, the project has basically completed site clearance to date.

However, in Dinh Cong ward, there are still 2 cases of encroachment on the red line boundary that have not been cleared (located in the sidewalk construction section). Currently, the investor and project enterprise are coordinating with the Ward People's Committee to implement it.

In Phuong Liet ward, there are still 2 households (area of about 59.3m2) that have not been cleared on the sidewalk of the project.

On January 27, 2026, Phuong Liet Ward People's Committee issued Document No. 216/UBND-BQLDA to the Housing and Urban Development Investment Corporation to coordinate and sign land clearance contracts for the above 2 households.

a
Vehicles circulate smoothly on the route. Photo: Song Huu
a
Some remaining items are being urgently implemented by the contractor. Photo: Song Huu

Representatives of the project enterprise said that by March 31, 2026 at the latest, the project will complete all items (except for some sections still facing site clearance issues), ensuring synchronization and meeting the conditions for handover and commissioning according to regulations.

SÓNG HỮU
RELATED NEWS

A section of Ring Road 2.5 is both under construction and site clearance

|

Hanoi - The Ring Road 2.5 project section passing through Xuan Dinh ward has just organized construction, and has also carried out land acquisition and site clearance.

Hanoi informs progress of site clearance for Ring Road 2.5 project

|

Hanoi - Cau Giay, Yen Hoa and Thanh Xuan wards are implementing land acquisition and site clearance for 3 sections of the Ring Road 2.5 project.

People collect assets, hand over land to build Ring Road 2.5

|

Hanoi - Some households are urgently collecting assets and handing over land for the Ring Road 2.5 project, Cau Giay section - Dich Vong New Urban Area.

Live football U17 Vietnam vs U17 Indonesia: Coach Roland finalizes the lineup

|

Live match between U17 Vietnam vs U17 Indonesia at the 2026 Southeast Asian Championship, taking place at 7:30 PM today (April 19).

Village heads and residential group leaders are proposed to calculate allowances from 1. 7

|

Village heads and residential group leaders are proposed to calculate allowances according to the expected base salary applied from 1. 7.

Billion-dollar bridge completed but no access road due to site clearance problems

|

Quang Tri - Nhat Le 3 bridge has been basically completed but still has to "wait" when many households have not handed over the site to construct the access road to the bridge.

Thousands of people brave the rain to visit Hung Temple festival on Han Thuc Tet

|

Phu Tho - April 19 (ie March 3rd of the lunar calendar - Lunar New Year), despite the rainy weather, thousands of people and tourists pilgrained to Hung Temple.

Pickup truck stuck while trying to overtake a level crossing in Hanoi

|

Hanoi - When the barrier was lowering, the pickup truck driver still drove the vehicle in, then got stuck close to the railway tracks.

A section of Ring Road 2.5 is both under construction and site clearance

VIÊN NGUYỄN - SÓNG HỮU |

Hanoi - The Ring Road 2.5 project section passing through Xuan Dinh ward has just organized construction, and has also carried out land acquisition and site clearance.

Hanoi informs progress of site clearance for Ring Road 2.5 project

SÓNG HỮU |

Hanoi - Cau Giay, Yen Hoa and Thanh Xuan wards are implementing land acquisition and site clearance for 3 sections of the Ring Road 2.5 project.

People collect assets, hand over land to build Ring Road 2.5

SÓNG HỮU |

Hanoi - Some households are urgently collecting assets and handing over land for the Ring Road 2.5 project, Cau Giay section - Dich Vong New Urban Area.