The Eastern arterial road of Ho Chi Minh City has not been expanded for 14 years and is not yet completed

MINH QUÂN |

HCMC - After 14 years of implementation, the project to expand Hanoi Highway and National Highway 1 - the main road of the eastern gateway of HCMC - is still not completed.

The project to expand Hanoi Highway and National Highway 1, extending from Saigon Bridge to Tan Van Intersection (15.7 km long), started on April 2, 2010 under the BOT (build - operate - transfer) model.

According to plan, the project will be completed within 36 months from the handover of the site.

However, by the end of November 2024, although the entire main axis from Saigon Bridge to the intersection of Ho Chi Minh City National University, more than 13km long, has been completed, many other sections are still unfinished due to land clearance problems.

In particular, the section of National Highway 1 from the new Eastern Bus Station to Tan Van intersection (about 2km long) has been stalled for many years, creating a "bottleneck" affecting people's travel.

Quoc lo 1 doan qua ben xe Mien Dong moi van chua mo rong xong vi vuong mat bang.  Anh: Minh Quan
National Highway 1 section through the new Eastern Bus Station has not yet been expanded due to land acquisition issues. Photo: Minh Quan

Notably, the East-West main road in Di An City (Binh Duong) - the route connecting to the new Eastern bus station - although completed, still cannot connect to National Highway 1 due to land clearance problems.

Vuong mat bang cung khien duong truc chinh Dong Tay o Binh Duong chua the noi thong ra Quoc lo 1.  Anh: Dinh Trong.
Land acquisition problems also prevent the main East-West axis in Binh Duong from connecting to National Highway 1. Photo: Dinh Trong.

Furthermore, the underpass at the Station 2 intersection on the parallel road on Hanoi Highway (from Ho Chi Minh City to Dong Nai) is also currently under temporary suspension because nearly 30 households have not been relocated.

Ham chui nut giao Tram 2 tren Xa lo Ha Noi dang do vi vuong mat bang. Anh: Minh Quan
The underpass at the Station 2 intersection on Hanoi Highway (HCMC) is unfinished due to land acquisition problems. Photo: Minh Quan

According to Mr. Hoang Phuc Dung - Deputy Head of the Department of Road Traffic Infrastructure Management and Exploitation (Ho Chi Minh City Department of Transport), the entire 15.7km Hanoi Highway and National Highway 1 will be expanded to 12 - 16 lanes, divided into 3 sections.

Section 1 from Saigon Bridge to Binh Thai Intersection is 6.2km long (153m wide); Section 2 from Binh Thai to Tram 2 Intersection is 5.3km long (113m wide); Section 3 from Tram 2 Intersection to Tan Van Intersection is 4.2km long (111m wide).

Mr. Hoang Phuc Dung said that the "bottleneck" situation at unfinished sections not only reduces the efficiency of the project but also causes serious congestion.

On average, each month, the Hanoi Highway toll station records nearly 1 million vehicles passing through, putting great pressure on the area's traffic infrastructure.

Doan mo rong Quoc lo 1 vuong mat bang phia tinh Binh Duong.  Anh: Minh Quan
The expansion section of National Highway 1 is stuck in the land acquisition process on the Binh Duong side. Photo: Minh Quan

A representative of the Ho Chi Minh City Department of Transport said that the section of National Highway 1 in Binh Duong province, from the new Mien Dong bus station to Tan Van intersection, has completed upgrading the existing main road surface since 2018 and building a parallel road in front of the gate of the new Mien Dong bus station.

However, the main road expansion and parallel roads on both sides (except for the 500m range in front of the new Eastern bus station) have not yet been cleared.

To date, Binh Duong province has paid and handed over the land to 152 out of 298 cases, but 146 cases have not been resolved. The prolonged situation increases compensation costs.

Currently, the investor of the BOT project to expand Hanoi Highway and National Highway 1 is adjusting the plan and balancing capital sources to continue completing compensation and site clearance work, in order to soon put the project into synchronous operation.

To thoroughly resolve the problem, the Ho Chi Minh City Department of Transport has proposed that the People's Committee of Binh Duong province and the People's Committee of Thu Duc city promptly complete compensation and site clearance procedures to hand over to investors.

Doan Quoc lo 1 qua ben xe Mien Dong moi chua hoan thanh mo rong.  Anh: Anh Tu
The section of National Highway 1 through the new Mien Dong bus station has not yet been expanded. Photo: Anh Tu

In 2009, the Hanoi Highway and National Highway 1 BOT project was approved by the Ho Chi Minh City People's Committee with a total investment of VND 2,516 billion and in 2016 it was adjusted to more than VND 4,900 billion.

From April 2021, Hanoi Highway BOT has started collecting tolls, expected to last 17 years and 9 months.

Currently, this is the main artery at the eastern gateway of Ho Chi Minh City, connecting directly through Binh Duong and Dong Nai, and is also the road axis parallel to Metro Line 1 (Ben Thanh - Suoi Tien) which is about to be put into operation.

MINH QUÂN
TIN LIÊN QUAN

8 years have passed since the construction of the underpass at the eastern gateway of Ho Chi Minh City was completed

|

HCMC - Construction began in 2016 on the underpass at Station 2 intersection on Hanoi Highway, from HCMC to Dong Nai, but has yet to be completed due to land acquisition issues.

The Eastern road of Ho Chi Minh City has been waiting for 9 years but still has not been widened

|

HCMC - The project to expand Luong Dinh Cua Street (Thu Duc City) with an investment capital of 826 billion VND has been implemented for 9 years, but the completion date has not yet been determined.

Hang Ma Street transforms after Christmas, "dressing up" to welcome Lunar New Year

|

Although Christmas has just passed, the shops on Hang Ma Street (Hoan Kiem, Hanoi) have changed their appearance and are bustling with customers buying and selling Lunar New Year 2025 items.

Rest stop on Cam Lo - La Son highway turns into "mud field"

|

HUE - Many drivers are no longer interested in resting at the two temporary rest stops on the Cam Lo - La Son highway because the entrance and parking area are like "mud fields".

Seminar "Diversifying resources to eliminate temporary and dilapidated houses"

|

At 2:00 p.m. on December 27, Lao Dong Newspaper in collaboration with the Vietnam Oil and Gas Group organized a discussion on "Diversifying resources to eliminate temporary and dilapidated houses".

Hoang Sinh Company owes social insurance up to 30 billion VND

|

Binh Duong - Many agencies are involved in handling the case of Hoang Sinh Company owing wages and social insurance to about 1,000 workers.

ASEAN nation accepts BRICS invitation

|

Thailand confirms readiness to become a BRICS partner country.

Admire the special national monument Hai Thuong Lan Ong

|

Ha Tinh - The restoration and beautification of the tomb, monument, and memorial site was completed on the occasion of the 300th anniversary of the birth of famous physician Hai Thuong Lan Ong.

8 years have passed since the construction of the underpass at the eastern gateway of Ho Chi Minh City was completed

MINH QUÂN |

HCMC - Construction began in 2016 on the underpass at Station 2 intersection on Hanoi Highway, from HCMC to Dong Nai, but has yet to be completed due to land acquisition issues.

The Eastern road of Ho Chi Minh City has been waiting for 9 years but still has not been widened

MINH QUÂN |

HCMC - The project to expand Luong Dinh Cua Street (Thu Duc City) with an investment capital of 826 billion VND has been implemented for 9 years, but the completion date has not yet been determined.

Chủ đầu tư BOT Xa lộ Hà Nội nói về việc đóng đường dưới cầu Rạch Chiếc

MINH QUÂN |

TPHCMChủ đầu tư BOT Xa lộ Hà Nội cho biết, việc đóng đường dưới cầu Rạch Chiếc là để trả lại mặt bằng theo quy hoạch chứ không nhằm mục đích tận thu.