Unfinished rural roads, people petition to clarify project implementation

Đinh Đại |

Lao Cai - The Na Sam - Ban No rural road project in Van Ban commune has been delayed for nearly 3 years, causing people to be upset and continuously petition.

For many years, the Na Sam - Ban No road in Giang village (old Lang Giang commune, now Van Ban commune) has been a road for dozens of households to travel and transport agricultural products.

Due to serious degradation, muddy in the rainy season, dusty in the dry season, people's travel is very difficult.

In 2023, the road was approved, invested by the People's Committee of Lang Giang commune (old), with a length of about 1.67km, total cost of nearly 2 billion VND.

Phần lớn tuyến đường Nà Sầm - Bản Nơ vẫn là đường đất, đá gồ ghề, gây nhiều khó khăn cho người dân mỗi khi mưa xuống. Ảnh: Đinh Đại
Most of the Na Sam - Ban No road is still dirt and rocky roads, causing many difficulties for people every time it rains. Photo: Dinh Dai

When there was a policy to build roads, people agreed to donate land, clear ground and contribute socialized funds with the desire to soon have a solid road.

However, according to feedback sent to Lao Dong Newspaper, after nearly 3 years, the project has only been constructed about 200m and then stopped.

Notably, people believe that the project has been paid about 700 million VND, while the actual completed volume is very small.

Người dân cho rằng vật liệu làm đường không phù hợp. Ảnh: Đinh Đại
People believe that road materials are not suitable and not guaranteed. Photo: Dinh Dai

Mr. Nguyen Van Toan (Giang village, Van Ban commune) reflected: "The commune's report at the recent working session also shows a very large payment value. Meanwhile, the project has only been built about 200m, so I don't know how they are constructing".

According to people, in addition to budget capital, people also contribute hundreds of millions of VND in socialization funds, averaging more than 1.3 million VND per household. Some poor households still have to borrow to pay with the hope of soon having a new road.

Up to now, the road is still not finished, traveling is very difficult, affecting production and economic development of the whole village," Mr. Toan complained.

Hiện trạng tuyến đường sau nhiều năm triển khai. Ảnh: Đinh Đại
Current status of the road after many years of implementation. Photo: Dinh Dai

In addition to the slow progress, people also believe that the road section has been constructed using stream stone instead of materials according to the approved dossier, so they request functional agencies to inspect and clarify.

Talking to Lao Dong Newspaper, Mr. Trieu Van Hiep - Head of Giang village confirmed that the road has only been constructed for about 200m and then stopped.

According to Mr. Hiep, the entire site has been donated and handed over by people for a long time. People have also contributed socialization funds, each household over 1 million VND.

This road is not too long and not of great value, but it is the aspiration of the people. When there is an investment decision, people are extremely excited because they think there will be a new road soon.

But until now, the project is still unfinished, the road is bad, and traveling is very difficult, so people are very upset and disappointed," Mr. Hiep added.

Dự án thực hiện trong giai đoạn 2023-2025, tuy nhiên đến nay người dân vẫn phải đi lại trên con đường đất cũ. Ảnh: Đinh Đại
The project is implemented in the 2023-2025 period, but so far people still have to travel on the old dirt road. Photo: Dinh Dai

Mr. Hiep said that, according to the information he has grasped, the project has been disbursed about 700 million VND, but the construction is still stopped. People in the village have also repeatedly wondered about the quality of materials used in the road section that has been built.

If it is not resolved in the near future, people will continue to have petitions to higher levels," the village head said.

Khối lượng và số tiền đã thanh toán. Ảnh: Đinh Đại
Quantity and amount of money paid. Photo: Dinh Dai

Regarding people's reflections, Mr. Vu Xuan Thuy - Chairman of Van Ban Commune People's Committee said that the project dossier invested by Lang Giang Commune People's Committee (old) is currently being handed over to the new commune after arranging administrative units.

I have assigned the Economic Department to go down to inspect the actual site, accurately determine the volume of construction, compare documents, and clarify the contents reflected by the people. After having the results, the commune will inform the press," Mr. Thuy said.

Đinh Đại
RELATED NEWS

The trillion-dong road gradually takes shape at the gateway to the border region of Lao Cai

|

Lao Cai - After many years of construction, the road along the Red River is gradually being completed, opening up a new face for traffic infrastructure in the border area.

Removing the bottleneck of the billion-dong road project in Thai Nguyen

|

The Ring Road I project - an important urban infrastructure project of Thai Nguyen province - has untangled the bottleneck of site clearance, accelerating progress.

Explaining the reasons why Provincial Road 160 in Lao Cai is under construction slowly and behind schedule

|

Lao Cai - Provincial road 160 construction is slow, explained by the contractor's poor construction capacity, fluctuating fuel and material prices, directly affecting the project.

Hanoi adjusts traffic at Lang Ha - Giang Vo intersection from September 11th

|

Hanoi adjusts traffic at the Lang Ha - Giang Vo - La Thanh intersection from 11:00 PM on September 11th to serve the construction of the overpass under the Ring Road 1 project.

Forecast of thunderstorms and temperature drop from tomorrow, September 10th due to cold air

|

Forecast due to the impact of cold air, the North and North Central regions will have rain; the lowest temperature is commonly 21-24 degrees C, high mountainous areas have places below 19 degrees C.

Close-up of US airstrike sinking 5 Iranian oil tankers

|

US Secretary of State Marco Rubio on September 8 (local time) announced that Washington will continue to target Iranian oil tankers in retaliatory strikes.

Frozen chicken imported massively into Vietnam, priced half as cheap as domestic goods

|

Imported chicken meat to Vietnam, including chicken thighs, frozen chicken wings and other by-products such as chicken feet, chicken hearts... with an average price of only 26,500 VND/kg.

Ministry of Health tightens private clinics: Drawing diseases, extorting money may result in revocation of licenses

|

The Ministry of Health requests localities to conduct surprise inspections of private clinics, strictly handle acts of drawing diseases, extorting money, and even revoke licenses.

The trillion-dong road gradually takes shape at the gateway to the border region of Lao Cai

Đinh Đại |

Lao Cai - After many years of construction, the road along the Red River is gradually being completed, opening up a new face for traffic infrastructure in the border area.

Removing the bottleneck of the billion-dong road project in Thai Nguyen

Việt Bắc |

The Ring Road I project - an important urban infrastructure project of Thai Nguyen province - has untangled the bottleneck of site clearance, accelerating progress.

Explaining the reasons why Provincial Road 160 in Lao Cai is under construction slowly and behind schedule

Đinh Đại |

Lao Cai - Provincial road 160 construction is slow, explained by the contractor's poor construction capacity, fluctuating fuel and material prices, directly affecting the project.