Road through 5 wards in Hanoi under construction, expected to be completed in 2026

SÓNG HỮU |

The investor and construction unit set a target to complete the Linh Nam road expansion project in 2026. The project is 3.4km long, passing through 5 wards of Hanoi.

The project to upgrade and expand Linh Nam road was approved for investment policy by the Hanoi People's Committee in 2013.

By August 2024, Hanoi City People's Committee has approved the adjustment of the implementation time of the Linh Nam road upgrade and expansion project according to the plan, to be completed in 2027.

The reason for the adjustment is due to difficulties and obstacles in site clearance, leading to the project not ensuring progress.

The project is about 3.4km long, starting point at Tam Trinh intersection, ending point at Nguyen Khoai dike intersection.

After the operation of the 2-level local government model (July 1, 2025), Hanoi City People's Committee assigned Vinh Hung Ward People's Committee to be the investor to implement the Linh Nam road upgrade and expansion project.

Up to now, the project has achieved many remarkable results. At package No. 01 - Construction and traffic assurance, the section from Nguyen Khoai dyke to Do Muoi road (Belt Road 3), about 200m long, has completed the roadbed, stone embankment, drainage system, crushed stone paving, adhesive asphalt irrigation, lower layer of road surface concrete paving, sidewalk paving, installing lighting poles, planting trees. Installing median strips of about 150/200m.

For package No. 07 (moving, undergrounding electrical and telecommunications systems), the contractor has fully prepared the main materials and equipment.

Section from Nguyen Khoai dyke to Do Muoi street (200m): Completion of temporary line connection laying, recovery of low-voltage power lines after Linh Nam 2 substation.

Long Thuyen market section (140m): Digging and casting foundations to temporarily move low tension at pile 144 Linh Nam 3 substation.

However, in Vinh Hung ward and 4 wards under the project, there are still many challenges, especially site clearance work when some households have not agreed on compensation and support plans.

At the same time, the prolonged cold and rainy days before Tet have interrupted construction. The project's workload is large, the road is long, and many technical items are complex, requiring synchronous coordination...

On February 23, the Standing Committee of Vinh Hung Ward Party Committee came to the project construction site to check the number of personnel, equipment, construction measures, and measures to ensure safety for workers and traffic participants.

At the construction site, the commanders of the construction units all committed to the progress and goal of completing on schedule and putting the road into use this year.

SÓNG HỮU
RELATED NEWS

Nguyen Tuan road construction is messy, contractors are slow to rectify violations

|

Hanoi - Although the ward has directed inspections, the contractor of the Nguyen Tuan road expansion project has not fully remedied safety conditions during construction.

Car crashes into median strip, overturns on the road in Hanoi

|

Hanoi - After climbing the median strip, the car overturned and lay in the middle of Hoang Dieu Street.

Quang Tri tourism marks the occasion of Binh Ngo Tet 2026

|

Quang Tri - Welcoming more than 409,000 visitors during Tet, Quang Tri tourism left many impressions thanks to attractive products, vibrant festivals and safe and friendly destinations.

Overview of Mr. Trump's tax process

|

US President Donald Trump's decision to impose tariffs since taking office in January 2025 has shocked the global financial market.

Benjamin Sesko shines, Man United close to top 3 Premier League

|

In the early morning of February 24 (Vietnam time), Benjamin Sesko's only goal helped Man United defeat Everton in the 27th round of the Premier League.

Can Tho workers enthusiastically enter shifts, expecting breakthrough orders

|

Can Tho - Excited to return to the factory after the Tet holiday, thousands of workers are enthusiastically producing with the expectation of abundant orders and prosperous income in the new year.

Gold price update morning of February 24th: Domestic gold prices increase

|

Gold price update morning of February 24th: Simultaneously increasing. Domestic gold approaches the threshold of 185 million VND/tael.

Chain collision of 5 cars on Phan Thiet - Dau Giay expressway

|

Lam Dong - A chain collision between 5 cars on the Phan Thiet - Dau Giay highway caused prolonged traffic congestion.

Hiện trạng dự án đường Nguyễn Tuân sau dịp nghỉ Tết Nguyên đán

NHÓM PV |

Hà Nội - Dự án mở rộng đường Nguyễn Tuân vẫn dang dở, không có hoạt động thi công, chiều 22.2.

Dự án đường Nguyễn Tuân: Phường nói xong trước Tết, người dân hoài nghi

SÓNG HỮU |

Hà Nội - Trước Tết Nguyên đán 3 ngày, dự án mở rộng đường Nguyễn Tuân vẫn nhầy nhụa bùn đất, ảnh hưởng đến cuộc sống, việc đi lại của người dân.

Nguyen Tuan road construction is messy, contractors are slow to rectify violations

SÓNG HỮU |

Hanoi - Although the ward has directed inspections, the contractor of the Nguyen Tuan road expansion project has not fully remedied safety conditions during construction.

Car crashes into median strip, overturns on the road in Hanoi

Tô Thế |

Hanoi - After climbing the median strip, the car overturned and lay in the middle of Hoang Dieu Street.