Ho Chi Minh City Ring Road 3 through Dong Nai clears 90% of land

HÀ ANH CHIẾN |

Dong Nai - Component 3 project of Ho Chi Minh City Ring Road 3, section through Nhon Trach district, has cleared more than 90% of the land.

On October 18, according to information from the Nhon Trach District Land Fund Development Center, the district has so far handed over 100% of the site for component project 1A of Ho Chi Minh City Ring Road 3. As for component project 3 of Ho Chi Minh City Ring Road 3, over 90% of the site has been cleared.

The Ho Chi Minh City Ring Road 3 Project, through Dong Nai Province, has 3 component projects including: Component Project 1A invested by My Thuan Project Management Board; Component Project 3 invested by Dong Nai Province Traffic Construction Investment Project Management Board and Component Project 4 - Compensation and resettlement support for Ho Chi Minh City Ring Road 3 through Dong Nai Province, with Nhon Trach District People's Committee as the investor for site clearance.

Regarding construction, the component project 3 of Ho Chi Minh City Ring Road 3, section through Dong Nai province, is more than 11 km long and has 3 main construction packages.

According to the Dong Nai Province Traffic Construction Project Management Board, the construction sites of packages 32 and 29 are basically ready for construction. In particular, many sections of package 26 are still unpaved and not connected from start to finish, making it difficult to organize construction.

The Component 3 Project of Ho Chi Minh City Ring Road 3, section through Dong Nai, was started on June 18, 2023 with a total investment of nearly VND 2,600 billion. It is expected to be completed in 2025 and put into operation from 2026.

The project starts at Km 0+000 in Vinh Thanh commune, Nhon Trach district, Dong Nai province. The end point is at Nhon Trach bridge in Long Tan commune, Nhon Trach district (continuing with component project 1A of Ho Chi Minh City Ring Road 3).

On the route, a 5 km expressway will be built connecting component project 1A, Tan Van - Nhon Trach section at the intersection of provincial road 25B, with a scale of 4 lanes and a speed of 100 km/h.

HÀ ANH CHIẾN
RELATED NEWS

Viewing Ho Chi Minh City Ring Road 3 after more than 1 year of construction

|

HCMC - The Ho Chi Minh City Ring Road 3 project through Hoc Mon district has reached 15% progress after more than 1 year of construction.

US and Iran show signs conflict will continue

|

US-Iran war escalates, threatening global energy security and maritime transport.

Officially eliminate typhoon Yagi and 8 other names, finalize replacement names

|

The Asia-Pacific Regional Typhoon Committee has officially finalized the use of Typhoon Tomo instead of Yagi after the heavy damage caused by this storm.

Lang Son Hotel "out of rooms" during the festival season, people open doors to invite guests to stay

|

Lang Son - While many tourists are struggling to find accommodation during the Ky Cung - Ta Phu festival, many local people have opened their houses to guests for free.

Reasons why the 2026 World Cup budget is cut by 100 million USD

|

3 months before the start of the 2026 World Cup, FIFA issued a surprise announcement that worried fans about the grandeur of this final round.

Important notes for candidates when registering for a maximum of 15 university aspirations in 2026

|

Arranging and selecting aspirations reasonably is considered an important factor to increase the chances of admission.

How to help children overcome shock when parents divorce

|

Divorce not only changes families but can also cause psychological harm to children if there is no care and sharing from parents.

Gasoline and oil prices simultaneously sharply decreased from 10 PM on March 11

|

After the Ministry of Industry and Trade and the Ministry of Finance disbursed the price stabilization fund, gasoline and oil prices simultaneously decreased sharply from 10:00 PM on March 11.

Viewing Ho Chi Minh City Ring Road 3 after more than 1 year of construction

Minh Tâm - Anh Tú |

HCMC - The Ho Chi Minh City Ring Road 3 project through Hoc Mon district has reached 15% progress after more than 1 year of construction.

Cận cảnh tiến độ thi công dự án đường Vành đai 3 TPHCM

Minh Tâm - Anh Tú |

TPHCM - Hiện trên công trường, công nhân đang gấp rút thi công ngày đêm để sớm đưa dự án đường Vành đai 3 TPHCM sớm về đích như dự kiến.

Cầu vượt sông lớn nhất Vành đai 3 TPHCM tăng tốc về đích sớm

Anh Tú - Như Quỳnh |

TPHCM - Sau gần 2 năm khởi công, cầu Nhơn Trạch thuộc dự án thành phần 1A (nối TPHCM - Đồng Nai) đường Vành đai 3 TPHCM đạt 80%, vượt tiến độ 4 tháng.