Minh Tâm - Anh Tú |

HCMC - The Ho Chi Minh City Ring Road 3 project through Hoc Mon district has reached 15% progress after more than 1 year of construction.

The Beltway 3 project, section through Ho Chi Minh City, has a total length of more than 47km, including 10 main construction packages and 4 operation packages. This is one of the city's key traffic projects.

According to Lao Dong on October 14, at the XL8 package passing through Hoc Mon district, workers and engineers are focusing on implementing construction items. Items of the XL8 package include an overpass over Nguyen Van Bua street, 2 overpasses over the canal and a highway section over 7km long, with a total package value of 1,417 billion VND.

Toan canh du an duong Vanh dai 3 TPHCM doan qua huyen Hoc Mon nhin tu tren cao. Anh: Anh Tu
Panoramic view of the Ring Road 3 project in Ho Chi Minh City through Hoc Mon district from above. Photo: Anh Tu

Although construction began in July 2023, the Ring Road 3 project through Hoc Mon district has only reached 15% progress. The main reason is identified as difficulties in supplying sand materials.

The contractor representative said that the entire package needs about 1.4 million cubic meters of sand to fill the main road and the secondary roads, service roads, bypass roads, etc. "At the beginning of the period, sand was scarce, so the overall progress was slowed down. More than 120,000 cubic meters of sand have started arriving since September, the contractor is speeding up construction to make up for the past progress," the contractor representative shared.

Tien do du an bi cham nguyen nhan duoc cho la gap kho khan ve nguon cung cap vat lieu cat dap. Anh: Anh Tu
The project's progress is delayed due to difficulties in supplying sand materials. Photo: Anh Tu

At the construction site, workers are reinforcing the weak ground by using wicking. Some sections have no sand and are overgrown with weeds despite having been previously excavated.

According to the contractor, the main source of sand is currently in Vinh Long, Ben Tre and Tien Giang sand mines. These are existing mines, while new mines have not been provided. Domestic supply is still scarce, although there is a mechanism to buy Cambodian sand, but because of the high cost and difficult transportation, it is still a barrier for this unit.

Tu thang 9 nguon cat bat dau ve, nha thau dang cho day nhanh thi cong, bu dap tien do vua qua. Anh: Anh Tu
Since September, sand supplies have started to arrive, and contractors are speeding up construction to make up for the past delay. Photo: Anh Tu
Nguon cat chinh chu yeu o mo cat Vinh Long, Ben Tre va Tien Giang. Anh: Anh Tu
The main source of sand is from the sand mines of Vinh Long, Ben Tre and Tien Giang. Photo: Anh Tu

In addition, contractors are focusing on speeding up the bridge sections at the TL9 overpass and the N8 bridge, and the bridge progress is exceeding the set plan. The TL9 overpass through Hoc Mon has a total of 14 piers and 2 abutments. Many piers have basically completed the body and base.

Ben canh do, cac nha thau dang tap trung day nhanh cac hang muc phan cau tai cau vuot TL9 va cau N8, tien do phan cau dang vuot ke hoach de ra. Anh: Anh Tu
In addition, contractors are focusing on speeding up the bridge sections at the TL9 overpass and N8 bridge, the bridge progress is exceeding the set plan. Photo: Anh Tu

The Ho Chi Minh City Ring Road 3 project is very important for the city's transport development. When completed, this route will help reduce traffic congestion, connect areas and promote socio-economic development.

The total construction project of Ring Road 3 is 76km long, passing through 4 localities, including: Ho Chi Minh City, Binh Duong, Dong Nai, Long An with a total investment of nearly 75,400 billion VND.

The project is divided into 8 component projects, each locality implements 2 projects, including site clearance and construction.

In Ho Chi Minh City, the Ring Road 3 - Ho Chi Minh City project has 14 bid packages, including 10 main construction bid packages and 4 bid packages for exploitation and operation.

The Traffic Department and units are making efforts to keep up with the schedule, basically completing the project by 2025 and opening the entire route to traffic by 2026.

Minh Tâm - Anh Tú
TIN LIÊN QUAN

The journey to turn Ponagar Tower into a special national monument

|

Khanh Hoa - The Government has recognized Ponagar Tower as a special national monument.

Research on Vietnamese people playing casino after the pilot period

|

The Deputy Prime Minister requested to study special policies for the development of Phu Quoc Special Zone, allowing Vietnamese people to play casino after the pilot period.

Raising growth forecast for 2025, stocks welcome large cash flow

|

Many securities organizations and companies have increased their forecasts for Vietnam's GDP growth in 2025. The stock market flourished, large-cap stocks led the increase.

Continue to reorganize mass organizations assigned by the Party and the State

|

The Party Committee of the Vietnam Fatherland Front and Central organizations will lead and direct the continued reorganization of mass associations assigned by the Party and State to operate under the Vietnam Fatherland Front, in the direction of reducing the number, streamlining the internal apparatus, and operating practically and effectively.

Buying Vietlott lottery on the day of giving birth, a worker won more than 16 billion VND

|

A man has just received the Vietlott Jackpot 2 lottery draw Power 6/55 QSMT No. 01210 with a value of more than 16 billion VND.

There have been conclusions about the person who shot down the MH17 passenger plane

|

The Malaysia MH17 plane crash due to shelling in 2014, with 298 passengers on board, has been determined.

Female judge tries to choose Phuong My Chi to avoid controversy in China

|

The change in performance style of Truong Luong Dinh - a judge who did not vote for Phuong My Chi 3 times - caused a wave of controversy in China.

Cận cảnh tiến độ thi công dự án đường Vành đai 3 TPHCM

Minh Tâm - Anh Tú |

TPHCM - Hiện trên công trường, công nhân đang gấp rút thi công ngày đêm để sớm đưa dự án đường Vành đai 3 TPHCM sớm về đích như dự kiến.

Nóng Sài Gòn: Thời điểm thông xe Vành đai 3 dài hơn 76km

Thanh Chân - Ngọc Lê |

Tin tức Nóng Sài Gòn ngày 22.8: Thời điểm thông xe tuyến đường 76km qua TPHCM và 3 tỉnh; Tuyến đường 76km đi qua TPHCM và 3 tỉnh thông xe năm 2026...

Cầu vượt sông lớn nhất Vành đai 3 TPHCM tăng tốc về đích sớm

Anh Tú - Như Quỳnh |

TPHCM - Sau gần 2 năm khởi công, cầu Nhơn Trạch thuộc dự án thành phần 1A (nối TPHCM - Đồng Nai) đường Vành đai 3 TPHCM đạt 80%, vượt tiến độ 4 tháng.