Rushing to untie the knot to save the 700 billion VND project from a prolonged deadlock

Khánh Linh |

Lang Son - With a total investment of nearly 700 billion VND, the Ly Thai To extended road project has only received handover of only 1.52% of the site.

30 years of anxiously waiting for legitimate rights

The Ly Thai To extended road and residential and resettlement area project of Lang Son City (now belonging to Dong Kinh ward) is invested by the Lang Son Provincial Construction Investment Project Management Board.

The project has a total area of 24.51 ha, affecting 543 households, individuals and organizations and residential communities.

However, behind the project expected to change the urban face are the long-standing compensation mysteries from the last century.

a
The yellowed counting papers are kept by the family. Photo: Khanh Linh

Located in the area of 250m at the beginning of the route that is currently blocked, Ms. Phan Thi Sinh's family (Dong Kinh ward) is a clear proof of the long wait.

Flipping through each yellowed paper and document left by her late father-in-law, Ms. Sinh recounted: "My family has about more than 1,500m2 of land affected by the project. From 1992, 1993, functional agencies have information that there is currently only compensation for crops, and when there is land compensation, people will be called to take it later.

But waiting for more than 30 years, my father, the household owner of the land that year, passed away more than 20 years ago, and so far the family has not received compensation money.

a
In April 2026, the Ly Thai To extended road project and the residential and resettlement area of Lang Son city (now belonging to Dong Kinh ward) will officially commence construction. Photo: Khanh Linh

Right in the area next to the stream in alley 174 Phai Ve, 32 households completely agreed with the project's policy, and even proactively moved their belongings.

The only bottleneck is that they are still waiting for functional agencies to approve the compensation plan to know how much money they will receive before handing over the land.

Hurriedly removing knots from the past

Explaining the reasons for the "sleeping" files for more than 30 years, Mr. Hoang Van Duc, Head of the Economic, Infrastructure and Urban Department of Dong Kinh ward, said that compensation had not been carried out thoroughly before because the time had passed too long, and related documents were lost.

Along with that, the project has undergone many adjustments with many different names, so verification and compensation payments face countless difficulties.

a
Chu Van An Specialized High School is one of the units affected by the project. Photo: Khanh Linh

However, fortunately, recently, the related documents have been found again. Currently, the Land Fund Development Center is verifying and reviewing the subjects affected, and at the same time comparing with previous documents to proceed with payment to the people" - Mr. Duc informed.

The delay in compensation is pushing the entire project into a "turtle crawling" situation. Accumulated construction value currently only reaches about 1.83% of the contract value. The handed-over land area only reaches 0.37ha/24.51ha (equivalent to 1.52% of the entire project) from 48 households.

The project implementation time is expected to end in 2026, meaning there are only 5 months left for implementation.

According to the representative of the Investor, if the site clearance progress continues to be delayed, the project may have to be prolonged, and the central budget capital of up to 246.165 billion VND cannot be fully disbursed.

The immediate consequence is that this situation will greatly affect the overall disbursement value of the whole province and directly threaten the double-digit economic growth target for the last 6 months of 2026 that Lang Son Provincial People's Committee is drastically directing.

Under too much pressure, in just 1 month, the Project Management Board had to send 4 consecutive documents requesting Dong Kinh Ward People's Committee and related units to focus maximum manpower and definitively resolve the rights of the people to have construction ground and save project progress.

Khánh Linh
RELATED NEWS

2,045 billion VND project in Phu Tho to build university village infrastructure road

|

Phu Tho - Project of the Program for Development of Grade II Cities - Component Project of Vinh Phuc province (old) implementing Component 6: University village infrastructure framework.

Lao Cai dialogue to remove obstacles for 119 billion VND rare earth project

|

Lao Cai - The Ben Den rare earth exploitation project with an investment of about 119 billion VND is being accelerated by local authorities to clear ground.

Project of 5 intersections in Can Tho at risk of being missed due to site clearance problems

|

Can Tho - The project to renovate and expand 5 key traffic intersections in the city is difficult to complete in 2026 when site clearance is less than 10%.

Egypt investigates the origin of UAV attacking 2 gas tankers at Damietta port

|

Egypt is analyzing debris of unmanned aerial vehicles (UAVs) from an unprecedented attack on a Mediterranean port in the country.

Expected sharp reduction in the number of principals when arranging and merging schools

|

More than 20 provinces and cities across the country have announced plans to arrange and merge schools, as well as personnel arrangement plans, including the position of principal.

Super typhoon Dolphin fiercely gusting above level 17, will strengthen and change direction

|

Super typhoon Dolphin continues to strengthen, likely to exceed level 17, moving towards China

Singapore team has big ambitions in the away match at My Dinh Stadium

|

Despite having to play away at My Dinh Stadium and being inferior in head-to-head record, Singapore is still confident in aiming for a positive performance against Vietnam.

2,045 billion VND project in Phu Tho to build university village infrastructure road

Tô Công |

Phu Tho - Project of the Program for Development of Grade II Cities - Component Project of Vinh Phuc province (old) implementing Component 6: University village infrastructure framework.

Lao Cai dialogue to remove obstacles for 119 billion VND rare earth project

Đinh Đại |

Lao Cai - The Ben Den rare earth exploitation project with an investment of about 119 billion VND is being accelerated by local authorities to clear ground.

Project of 5 intersections in Can Tho at risk of being missed due to site clearance problems

Tạ Quang |

Can Tho - The project to renovate and expand 5 key traffic intersections in the city is difficult to complete in 2026 when site clearance is less than 10%.