Hanoi proposes to soon construct 3 bridges across the Red River on Ring Road 4

HỮU CHÁNH |

Hanoi recommends that investors and project enterprises focus on mobilizing capital and soon select contractors to construct the entire route, especially the 3 large bridges on Ring Road 4.

On September 3, the Hanoi Traffic Construction Investment Project Management Board (Project Management Board) signed a BOT contract for component project 3: investment in the construction of the expressway under the PPP method under the Ring Road 4 - Capital Region project.

To ensure the construction progress according to the instructions, Mr. Ngo Ngoc Van, Director of the Project Management Board, requested investors and project enterprises to urgently carry out preparations to comply with the provisions of law.

In the coming time, investors and project enterprises are requested to focus on mobilizing capital, speeding up the selection of construction contractors for construction on the entire route. Especially for large bridges across the Red River and Duong River such as the Hong Ha, Me So, Hoai Thuong bridges and interconnecting intersections to connect the entire parallel road.

Along with that, the leaders of the Project Management Board also requested relevant departments and branches to continue to support the management and implementation of BOT contracts and have instructions and reports to competent authorities to promptly handle difficulties and problems in the implementation process.

The Component project 3 of the central expressway, the backbone of the Ring Road 4 Project, is about 113.5km long, 17m wide, large bridges across the river are 24.5m wide, phase 1 has 4 lanes across.

The entire route has 13 elevated sections with a total length of about 82km; arranged 3 large bridges across the river including Hong Ha, Me So, Hoai Thuong, 8 intersections and completed 1 intersection.

The total investment of component project 3 is nearly VND 56,300 billion, of which the State budget capital accounts for 47.5%, the rest is the capital of the investor consortium. The construction period according to the signed contract is 30 months.

Previously, in June 2025, the Hanoi People's Committee issued a decision approving the results of selecting investors to implement component project 3 - investment in the construction of expressways under the public-private partnership method under the Ring Road 4 project - Hanoi Capital Region.

The winning investor is the joint venture City Land - Sunflower - VEC - Horizon (City Real Estate Investment Company Limited - Saigon Huong Duong Flowers Company Limited - Vietnam Expressway Development Investment Corporation - Horizon Investment Joint Stock Company Limited); BOT contract type.

HỮU CHÁNH
RELATED NEWS

Starting construction of the road connecting to Ho Chi Minh City Ring Road 4 with an investment capital of VND 3,143 billion

|

Ho Chi Minh City invested VND3,143 billion to build 5km of road connecting to the former Ho Chi Minh City Ring Road 4 in Ben Cat and Binh Duong areas.

Hanoi is about to start construction of Ring Road 4 expressway, many bridges across the Red River

|

During major holidays from now until the end of the year, Hanoi will start many important transport projects, including the Ring Road 4 and 4 expressways across the Red River.

Hanoi Ring Road 4 project faces obstacles, risk of missing the completion date by the end of this year

|

Hanoi - 11/17 wards and communes have not yet handed over enough land to the contractor, causing the project to build the Ring Road 4 parallel road to risk missing the completion date by the end of 2025.

Struggling in the hot sun to construct the Ring Road 4 parallel road

|

Under the scorching sun, workers and laborers at the Ring Road 4 construction site are still working hard, determined to complete the project on schedule, with the highest quality and efficiency.

Special features of Vietnam Night in Ho Chi Minh City

|

Ho Chi Minh City - The Vietnam Night Art Program is a welcome from Ho Chi Minh City to friends from 5 continents, a city with a new look, new space, new potential.

The success of the parade and march reflects the endless growth of the Army

|

According to General Phan Van Giang, the success of the parade and march reflects the maturity and constant growth of the heroic Vietnam People's Army.

The Ministry of Construction requests to tighten management after the fire at the Vinh Tuy bridge underpass

|

The Ministry of Construction has just requested a review of the management and use of road safety corridors after the fire at the parking lot under Vinh Tuy Bridge.

The brilliant A80 roses return to Ho Chi Minh City after completing their mission

|

HCMC - On the afternoon of September 3, the female pilots performing the A80 mission boarded a flight from Hanoi back to HCMC in the arms of the people and the joy and pride of the people.

Starting construction of the road connecting to Ho Chi Minh City Ring Road 4 with an investment capital of VND 3,143 billion

ĐÌNH TRỌNG |

Ho Chi Minh City invested VND3,143 billion to build 5km of road connecting to the former Ho Chi Minh City Ring Road 4 in Ben Cat and Binh Duong areas.

Hanoi is about to start construction of Ring Road 4 expressway, many bridges across the Red River

SÓNG HỮU |

During major holidays from now until the end of the year, Hanoi will start many important transport projects, including the Ring Road 4 and 4 expressways across the Red River.

Hanoi Ring Road 4 project faces obstacles, risk of missing the completion date by the end of this year

SÓNG HỮU |

Hanoi - 11/17 wards and communes have not yet handed over enough land to the contractor, causing the project to build the Ring Road 4 parallel road to risk missing the completion date by the end of 2025.

Struggling in the hot sun to construct the Ring Road 4 parallel road

Hữu Chánh |

Under the scorching sun, workers and laborers at the Ring Road 4 construction site are still working hard, determined to complete the project on schedule, with the highest quality and efficiency.