Hanoi is about to start construction of the 35,600 billion VND metro railway line

Anh Tuấn |

Hanoi - Hanoi urban railway project line 2, Nam Thang Long - Tran Hung Dao section is expected to start construction in 2025 and be completed in 2029.

Representatives of the Hanoi Urban Railway Management Board have just informed about the project to build the Nam Thang Long - Tran Hung Dao metro line.

According to the Hanoi Urban Railway Management Board, Deputy Prime Minister Bui Thanh Son signed a decision approving the adjustment of the investment policy for the Hanoi Urban Railway Construction Project, Line 2, Nam Thang Long - Tran Hung Dao section. This is an important traffic route, contributing to the development of a modern and sustainable public transport system for the capital city of Hanoi.

The project has a total length of 11.5km, including 8.9km underground and 2.6km elevated; there are 7 underground stations and 3 elevated stations. This railway line has 10 trains.

This project is expected to be completed and put into operation in 2029 and have 2 years of operation and maintenance training.

The total investment of the project is nearly 35,600 billion VND, equivalent to more than 1,500 million USD. Of which, ODA capital borrowed from the Japan International Cooperation Agency (JICA) is more than 29,000 billion VND; the counterpart capital of Hanoi city budget is nearly 6,000 billion VND.

Hanoi Urban Railway Management Board (MRB) said that the units will implement the project from 2025.

According to MRB, railway line No. 2 forms an important backbone, connecting the inner city area, Noi Bai International Airport and the northern urban area of ​​Hanoi.

"This is an important step to build a modern, synchronous and sustainable transport network for the capital, meeting the requirements of socio-economic development and improving the quality of life of the people," said an MRB representative.

This project was approved by Hanoi in 2008. The initial total investment was 19,555 billion VND.

The starting point is Nam Thang Long along Nguyen Van Huyen extended street - Hoang Quoc Viet - Hoang Hoa Tham - Thuy Khue - Phan Dinh Phung - Hang Giay - Hang Duong - Hang Ngang - Hang Dao - Dinh Tien Hoang - Hang Bai; the end point intersects with Tran Hung Dao street.

Anh Tuấn
TIN LIÊN QUAN

Chairman of Railway Trade Union receives Labor Medal

|

Chairman of Vietnam Railway Trade Union Mai Thanh Phuong was honored to receive the Second Class Labor Medal.

Modern railway connecting Ho Chi Minh City, Binh Duong, Dong Nai

|

Ho Chi Minh City is promoting regional connectivity with Binh Duong and Dong Nai, notably extending Metro Line 1 and building the Thu Thiem - Long Thanh railway line.

Khanh Le Pass landslide is still complicated, opening date unknown

|

Khanh Hoa - The risk of landslides on Khanh Le Pass is still complicated, and the locality is considering a plan to ban traffic.

People can ride free electric buses connecting to Metro Line 1

|

HCMC - On the morning of December 20, 17 electric bus routes connecting Metro Line 1 officially started running, serving people to experience the city's first tram line.

Coach Kim Sang-sik: Vietnam team is lucky to have Xuan Son in the squad

|

At noon on December 20, coach Kim Sang-sik of the Vietnam team and Myo Hlanging Win of Myanmar attended a press conference before the match.

100 cán bộ quận Hoàng Mai cưỡng chế 4.000m2 đất vàng bị lấn chiếm

Anh Tuấn |

Hà Nội - Các lực lượng chức năng quận Hoàng Mai (TP Hà Nội) đã tiến hành di dời tài sản, quây tôn khu vực đất dự án bị lấn chiếm với diện tích hơn 4.000m2.

Chairman of Railway Trade Union receives Labor Medal

Minh Phương - Hải Nguyễn |

Chairman of Vietnam Railway Trade Union Mai Thanh Phuong was honored to receive the Second Class Labor Medal.

Cưỡng chế 4.000m² đất lấn chiếm ở khu Đền Lừ III, Hoàng Mai

Anh Tuấn |

Hà Nội - Ngày mai (17.12), quận Hoàng Mai sẽ tổ chức cưỡng chế 4.000m2 đất lấn chiếm tại Khu di dân Đền Lừ III (phường Hoàng Văn Thụ).

Modern railway connecting Ho Chi Minh City, Binh Duong, Dong Nai

MINH QUÂN |

Ho Chi Minh City is promoting regional connectivity with Binh Duong and Dong Nai, notably extending Metro Line 1 and building the Thu Thiem - Long Thanh railway line.