Infrastructure accelerates but site clearance is still congested at VSIP Can Tho industrial park

Tạ Quang |

Can Tho - Vinh Thanh Industrial Park Project (phase 1) achieved many results in infrastructure construction, but still faced difficulties in site clearance and procedures.

The project to invest in construction and business of Vinh Thanh Industrial Park infrastructure (phase 1) invested by VSIP Can Tho Joint Stock Company has disbursed more than 2,118 billion VND, reaching 56.97% of the total investment.

To date, many important legal procedures have been completed, but the project is still facing difficulties due to site clearance and some procedures are still being carried out.

Công nhân thi công tại Dự án đầu tư xây dựng và kinh doanh kết cấu hạ tầng  Khu công nghiệp Vĩnh Thạnh (giai đoạn 1). Ảnh: Tạ Quang
Construction workers at the Vinh Thanh Industrial Park Infrastructure Investment and Business Project (phase 1). Photo: Ta Quang

Mr. Tran Ngoc Hung - Acting Head of the Management Board of Can Tho Export Processing and Industrial Zones - said that for ground leveling, roads, rainwater drainage, wastewater drainage, water supply, lighting, communication, and power supply items are being implemented. The total progress is estimated at about 40%.

The investor has completed leveling about 50 hectares, including land for the Bestway Can Tho Sports Technology Factory project and many technical functional areas. Internal technical infrastructure system reaches about 30%.

The centralized wastewater treatment plant (Module 1) with a capacity of 6,000 m3/day and night currently meets about 90% of the volume, is installing technology equipment and is expected to be completed in June 2026. The fire prevention and fighting station also meets about 90% of the progress, while the 22kV power supply system has been completed to serve temporary power supply for secondary investors.

In parallel, the water supply line from National Highway 80 to the industrial park has been completed, the turbocharged pumping station is under construction and is expected to be put into operation in September 2026. The 110kV substation is completing investment procedures, expected to be completed in mid-2027.

Lãnh đạo Thành ủy Cần Thơ và UBND TP kiểm tra dự án (ảnh chụp tháng 3.2026). Ảnh: Tạ Quang
Leaders of Can Tho City Party Committee and City People's Committee inspect the project (photo taken in March 2026). Photo: Ta Quang

Regarding investment attraction, Mr. Tran Ngoc Hung said that Vinh Thanh Industrial Park has welcomed the first secondary investor, the Bestway Can Tho Sports Technology Factory Project with a total investment of about 100 million USD.

For connecting infrastructure projects, the road from National Highway 80 to the industrial park has been completed and put into use from October 2025. The road connecting from the access road to Vam Cong bridge to the industrial park currently reaches about 63% of the construction volume. Meanwhile, the resettlement area serving the project has completed construction, handed over 257 out of a total of 547 plots to people and is continuing to complete procedures to hand over the remaining plots.

Although many positive results have been achieved, the project still has some difficulties that need to be removed. According to Mr. Tran Ngoc Hung, there are currently about 21.5 billion VND of compensation and support that have not been paid. Notably, there are still 50 houses and electricity, water and telecommunications systems that have not been relocated, directly affecting the construction progress of technical infrastructure items.

Đến nay, dự án vẫn còn gặp khó khăn do công tác giải phóng mặt bằng và một số thủ tục đang tiếp tục được thực hiện. Ảnh: Tạ Quang
To date, the project is still facing difficulties due to site clearance and some procedures are still being carried out. Photo: Ta Quang

In addition, the clean water price plan for industrial parks has not yet been approved by competent authorities, affecting the completion of infrastructure conditions to serve the operations of investors.

To speed up the project progress, the Can Tho Export Processing and Industrial Zones Authority proposed that the City People's Committee direct relevant units to soon issue clean water prices for industrial parks; accelerate compensation, support and resettlement; mobilize the remaining households to hand over land, and coordinate the relocation of electricity, water, and telecommunications infrastructure according to regulations.

For the investor, the Management Board requested VSIP Can Tho Joint Stock Company to continue to complete legal procedures, accelerate the progress of synchronous technical infrastructure construction to meet the conditions for secondary investors to implement projects, contributing to promoting industrial development and attracting investment into Can Tho city.

Vinh Thanh Industrial Park (phase 1) was approved for investment policy by the Prime Minister from October 2022 with a scale of 293.7 ha and a total investment capital of more than 3,717 billion VND (equivalent to nearly 160 million USD).

Tạ Quang
RELATED NEWS

Businesses reduce logistics costs by infrastructure and digital transformation

|

Ho Chi Minh City - Rising logistics costs are becoming a bottleneck of the economy. To remove obstacles, it is necessary to invest in infrastructure and promote business transformation.

670 biological samples in Can Tho set off for Hanoi to find the names of the martyrs

|

Can Tho - 670 biological samples of martyrs' remains in the city were transferred to Hanoi for DNA testing, opening up more hope for identifying identities.

Project of over 7,200 billion VND in Can Tho still has 369 cases of land not yet handed over

|

Can Tho - The National Highway 91 Upgrade and Expansion Project has had 691/1,060 cases of site handover, and the remaining 369 cases have not yet handed over the site.

Older brother overcomes a thousand thorns shining until 2 am, the results are controversial

|

Episode 2 of "Anh Trai Vuot Ngan Chong Gai" season 2 created a lively debate after 10 groups performed the first performances.

Infrastructure accelerates but site clearance is still congested at VSIP Can Tho industrial park

|

Can Tho - Vinh Thanh Industrial Park Project (phase 1) achieved many results in infrastructure construction, but still faced difficulties in site clearance and procedures.

Hero Ngo Thi Tuyen passed away at the age of 80

|

Thanh Hoa - Hero Ngo Thi Tuyen, who carried 2 boxes of ammunition heavier than twice her body weight during the anti-American resistance war, has passed away.

Businesses reduce logistics costs by infrastructure and digital transformation

NGỌC LÊ |

Ho Chi Minh City - Rising logistics costs are becoming a bottleneck of the economy. To remove obstacles, it is necessary to invest in infrastructure and promote business transformation.

670 biological samples in Can Tho set off for Hanoi to find the names of the martyrs

Tạ Quang |

Can Tho - 670 biological samples of martyrs' remains in the city were transferred to Hanoi for DNA testing, opening up more hope for identifying identities.

Project of over 7,200 billion VND in Can Tho still has 369 cases of land not yet handed over

Tạ Quang |

Can Tho - The National Highway 91 Upgrade and Expansion Project has had 691/1,060 cases of site handover, and the remaining 369 cases have not yet handed over the site.