Two contractors constructing the Bien Hoa - Vung Tau expressway in Dong Nai province are behind schedule

HÀ ANH CHIẾN |

Dong Nai - The two contractors behind schedule for the Bien Hoa - Vung Tau expressway project are Hai Dang Joint Stock Company and Truong Son Construction Corporation.

On July 17, the Dong Nai Provincial Construction Investment Project Management Board (abbreviated as the Project Management Board) has just reported to the Chairman of the Provincial People's Committee to support and urge the progress, requesting the two contractors, Truong Son Construction Corporation and Hai Dang Joint Stock Company, to urgently mobilize all resources to compensate for the delayed progress (technical traffic progress before December 19, 2025).

According to the Project Management Board, Component Project 1 of the Bien Hoa - Vung Tau Expressway Construction Investment Project Phase 1 - is implementing the construction of 2 main construction packages, with 9 contractors participating in the construction. The Project Management Board assessed that the two contractors were ahead of schedule, Lizen Joint Stock Company and 368 Joint Stock Company, with 5 contractors basically meeting the schedule and 2 contractors not ensuring the schedule.

Accordingly, for Hai Dang Joint Stock Company - a member of the consortium of construction packages No. 21, it is 11% behind schedule.

For Truong Son Construction Corporation - the leader of the consortium of construction packages No. 18, through inspection and progress monitoring (from April 23 to July 12), construction progress is slow and not guaranteed, especially for the item of weak soil treatment using cement reinforced soil piles, construction is very slow, only 2/6 lines are operating at the construction site; the accumulated volume reaches 27% of the contract value, 13% behind schedule.

According to the Project Management Board, the construction volume is still very large, with the current construction progress, the two contractors will not be able to complete the technical traffic opening on December 19, 2025 according to the direction of the Prime Minister.

The Project Management Board recommends that the Chairman of the Provincial People's Committee support and urge the progress, requiring the two contractors, Truong Son Construction Corporation and Hai Dang Joint Stock Company, to urgently mobilize all resources in terms of financial resources, human resources, machinery and equipment, proactively source filling land, increase construction shifts with the spirit of "3 shifts, 4 teams" to compensate for the delayed progress.

In case by August 15, 2025, the two contractors do not have a positive change in actual progress at the site, the Project Management Board will carry out procedures to reduce the remaining volume to transfer to qualified contractors in the package consortium or in the project to continue implementing to complete the items synchronously, ensuring the technical traffic of the entire project before December 19, 2025.

HÀ ANH CHIẾN
TIN LIÊN QUAN

The two contractors constructing the Bien Hoa - Vung Tau expressway in Dong Nai province are ahead of schedule

|

Dong Nai - 2 contractors participating in the construction of package 21 - component project 1 - Bien Hoa - Vung Tau Expressway Project are ahead of schedule.

Technical traffic opening of Bien Hoa - Vung Tau Expressway Component 3 Project

|

Ba Ria - Vung Tau has 4 projects that were started and inaugurated on April 19 to celebrate the 50th anniversary of the country's reunification.

Celebrating New Year's Eve with workers of Bien Hoa - Vung Tau Expressway project

|

Dong Nai - Lao Dong newspaper reporters welcomed New Year's Eve with officers and workers working through Tet at package 18 of component project 1 of Bien Hoa - Vung Tau expressway.

Professor Nguyen Buu Trieu - "The Great Trees" of the Vietnamese Surgery industry passed away

|

Professor Nguyen Buu Trieu - "The Great Trees" of the Vietnamese Surgery industry, passed away last night, July 16 in Hanoi.

Ukraine has a female Prime Minister for the second time in history

|

On July 17, the Ukrainian parliament voted to appoint Yulia Svyrydenko as the country's new prime minister.

Live volleyball Vietnam men's team 1-2 Indonesia: Set 4

|

Live match between the Vietnamese men's volleyball team and Indonesia in the second phase of SEA V.League 2025, taking place at 19:00 on July 17.

Discussion: Green transportation transformation - an irreversible trend

|

In order to protect the environment and improve people's health, Lao Dong Newspaper organized a seminar: Green transportation transformation - an irreversible trend.

Support rate for Ms. Paetongtarn to be reappointed as Prime Minister of Thailand

|

With Prime Minister Paetongtarn Shinawatra suspended from office, Thailand is facing a major turning point with 3 potential scenarios.

The two contractors constructing the Bien Hoa - Vung Tau expressway in Dong Nai province are ahead of schedule

HÀ ANH CHIẾN |

Dong Nai - 2 contractors participating in the construction of package 21 - component project 1 - Bien Hoa - Vung Tau Expressway Project are ahead of schedule.

Technical traffic opening of Bien Hoa - Vung Tau Expressway Component 3 Project

Thành An |

Ba Ria - Vung Tau has 4 projects that were started and inaugurated on April 19 to celebrate the 50th anniversary of the country's reunification.

Celebrating New Year's Eve with workers of Bien Hoa - Vung Tau Expressway project

NHƯ QUỲNH - HÀ ANH CHIẾN |

Dong Nai - Lao Dong newspaper reporters welcomed New Year's Eve with officers and workers working through Tet at package 18 of component project 1 of Bien Hoa - Vung Tau expressway.