Thousands of workers construct 2 expressways through Quang Binh

CÔNG SÁNG |

Quang Binh - The North-South expressway projects through the province are being accelerated, 1 project has come into operation, the remaining 2 projects have reached 85 to 90%.

Van Ninh - Cam Lo accelerates

Speaking to Lao Dong Newspaper reporters on May 11, Mr. Mai Quy Khanh - Deputy Head of Project Management Department 4, Ho Chi Minh Road Project Management Board said that the North - South expressway project, Van Ninh - Cam Lo section, has now achieved important progress, in which the section through Quang Binh alone has completed 100% of site clearance, and the packages have been constructed simultaneously.

According to the Ho Chi Minh Road Project Management Board, the Van Ninh - Cam Lo project has a total length of 65.54km, passing through Quang Binh 33.017km and Quang Tri 32.53km, invested by the Ho Chi Minh Road Project Management Board. Currently, the entire site has been handed over, of which Quang Binh has handed over 100% (33.017km). However, the items of the residential access road still have 8.5km that have not been handed over due to arising after the start of construction.

Cong nhan thi cong tren cao toc Van Ninh - Cam Lo. Anh: Nguyen Luan
Workers constructing on the Van Ninh - Cam Lo expressway. Photo: Nguyen Luan

Mr. Khanh informed that the XL1 and XL2 construction packages are being implemented simultaneously with a total of 53 teams, mobilizing nearly 1,500 workers, engineers, and hundreds of equipment and machinery. The output to date has reached more than 85.5% of the contract value. Labor safety, quality, and environmental sanitation are assessed to be guaranteed.

On the entire route, we have been constructing 30 bridges, and many items such as culverts, underpasses for people, road foundations, and roadbed excavation have also been accelerated. For Quang Binh province, all 13 bridges, 17 underpasses and hundreds of culverts of all kinds are being urgently completed," said Mr. Khanh.

In addition, the construction of a resettlement area in Quang Binh, including 4 areas, with a total area of nearly 9 hectares serving 95 households, has also been completed, contributing to stabilizing the lives of people affected by the project. The related technical infrastructure has also been relocated to 44/44 locations.

Hurry to finish on time

Meanwhile, the Bung - Van Ninh Expressway Project (more than 48km long, total investment of more than VND 9,300 billion) was basically completed after more than 2 years of construction and put into operation at the end of April 2025.

As for the Vung Ang - Bung Project (more than 55km long), informing Lao Dong Newspaper, Project Management Board 6 said that more than 90% of the construction value has been completed. The route passes through Ha Tinh and Quang Binh provinces, of which Quang Binh accounts for more than 42km. The project has 2 main packages, including 33 bridges, 1 tunnel through Deo But mountain, over 1.5km long, 406 culverts and 37 underpasses for people.

Currently, 40 construction teams with more than 1,200 workers and 620 equipment are being mobilized. The bridge, culvert, roadbed, and underpass items are basically completed. Deo But tunnel alone has opened both branches, reaching more than 99% of the tunnel excavation volume. Some remaining items such as road surfaces, railings, and safety fences are being accelerated to ensure progress.

Cao toc Vung Anh - Bung dat tren 90% tong khoi luong. Anh: Cong Hung
The Vung Anh - Bung Expressway has reached over 90% of the total volume. Photo: Cong Xuan

Regarding difficulties, Project Management Board 6 said that there are still some households that have not handed over the site, affecting the construction of fences, service roads, and against- Pressure platforms. Specifically, in Quang Trach district, there are still 12 households and in Ba Don town, there are still 29 households that have not been relocated, causing delays in the construction of auxiliary items.

As of early May 2025, the project has disbursed all capital for the years 2022-2024, reaching nearly VND 8,200 billion. The project management board requested the locality to urgently complete site clearance, ensuring the route is open to traffic by mid-2025 as planned.

The Van Ninh - Cam Lo and Vung Ang - Bung expressways are expected to be completed by the end of June 2025.

It is expected that when completed, the 3 North - South expressway projects through Quang Binh will create a great driving force to promote regional connectivity, expand space for economic, social, defense and security development for the locality and the North Central region.

CÔNG SÁNG
RELATED NEWS

VEC speaks out about the Noi Bai - Lao Cai expressway asphalt paving contractor in the rain

|

Vietnam Expressway Corporation (VEC) said that the contractor will remove the asphalt section of the Noi Bai - Lao Cai Expressway.

Vice Chairman of the province visits people's houses to mobilize and resolutely remove obstacles to the highway's land

|

Localities with expressway projects are urgently taking action, determined to hand over the site for construction soon, in order to complete 3,000km of expressway in 2025 according to the direction of the Prime Minister.

Removing obstacles at the trillion-dong expressway project in Bac Kan

|

Bac Kan - The expressway project worth more than VND5,700 billion is facing difficulties in site clearance due to land clearance problems, houses on agricultural land...

Argentine newspaper continues to publish evidence of Malaysian player naturalization

|

On the night of November 5, the Argentine media published a series of documents proving that the Football Association of Malaysia (FAM) had committed fraud in the process of naturalizing player Imanol Machuca.

A Lam Dong resident forgot to jump into the rushing water to save a woman who was struggling

|

Lam Dong - Seeing a woman roaming the Dinh River, people rushed down to rescue her in time.

Forecast of the most affected area of super typhoon Fung-wong, the predecessor of typhoon No. 14

|

Super typhoon Fung-wong, the predecessor of typhoon No. 14, is forecast to reach its strongest level before making landfall, causing the risk of flooding, high waves and widespread heavy rain.

People reported to the head of the department's phone that a passenger bus traveling in the wrong lane in Hung Yen was being handled

|

Hung Yen - Receiving feedback via the hotline, Hung Yen Traffic Police verified and handled the passenger bus going in the wrong lane, going in the wrong direction on National Highway 39.

Truck crashed into many vehicles and fled in Hanoi

|

Hanoi - A series of accidents occurred on the evening of November 5 on Hoang Mai Street (Hoang Mai Ward).

VEC speaks out about the Noi Bai - Lao Cai expressway asphalt paving contractor in the rain

Nhóm PV |

Vietnam Expressway Corporation (VEC) said that the contractor will remove the asphalt section of the Noi Bai - Lao Cai Expressway.

Vice Chairman of the province visits people's houses to mobilize and resolutely remove obstacles to the highway's land

Hà Anh Chiến |

Localities with expressway projects are urgently taking action, determined to hand over the site for construction soon, in order to complete 3,000km of expressway in 2025 according to the direction of the Prime Minister.

Removing obstacles at the trillion-dong expressway project in Bac Kan

Nguyễn Hoàn |

Bac Kan - The expressway project worth more than VND5,700 billion is facing difficulties in site clearance due to land clearance problems, houses on agricultural land...