Complete construction of 30km of Long Thanh airport boundary fence before December 19

HÀ ANH CHIẾN |

Dong Nai - Package 2.10 for the construction of the Long Thanh airport boundary fence has an adjusted completion schedule before December 19, 2025.

On October 14, according to information from Vietnam Airports Corporation (ACV), the consortium of contractors has mobilized 102 personnel and 12 equipment and machinery to simultaneously deploy 8 construction teams of package 2.10 - Border Guard of Long Thanh International Airport (abbreviated as Long Thanh Airport) outside the 1,810 hectare area.

Currently, the contractor consortium is implementing the excavation of the project foundation, the construction of concrete for the M200 foundation, the construction of reinforced concrete for the foundation, and the construction of brick walls.

This package has a contractor, the Chau Viet - Dai Viet joint venture, which started construction on October 25, 2024, with a construction period of 12 months.

However, the adjustment schedule will be completed synchronously along with other packages before December 19, 2025.

Thi cong du an san bay Long Thanh. Anh: HAC
Construction of Long Thanh airport project. Photo: HAC

Previously, the fence within 1,810 hectares of phase 1 of Long Thanh airport (package 2.4) was 100% completed with a length of 7,856 m.

The People's Committee of Dong Nai province has proposed to soon complete the construction of a protective fence for the entire 5,000 ha area of the Long Thanh airport project, with a length of about 30 km.

The solution is to build fences around the Long Thanh airport project to prevent re-encroachment after clearing the land.

HÀ ANH CHIẾN
RELATED NEWS

Overcoming the sun and rain, mobilizing nearly 14,000 human resources to construct Long Thanh airport

|

Dong Nai - Long Thanh airport project is under construction in unfavorable weather due to continuous heavy rain in September.

Gold price increases, buyers earn nearly 10 million VND/tael after two weeks

|

Gold prices are recording a strong increase in both domestic and international markets. Investors made a profit of up to 9.9 million VND/tael after a week of paying.

The risk of a severe winter covering Ukraine

|

Ukraine faces a serious gas shortage winter, having to cut the heating season as Russia continues to attack energy infrastructure.

German intelligence director warns of the risk of European attacks

|

A new warning from Germany said that Europe is facing the risk of conflict with Russia in the context of fragile peace.

November completes reviewing bank accounts on VNeID to make social security payments

|

The bank will review people's bank accounts on VNeID to clean up data, serve social security payments, avoid fraud, and complete in November 2025.

Forecast of the time to end thunderstorms in the North due to cold air

|

According to the meteorological agency, cold air will continue to cause rain in the North until October 15, with some places having heavy rain over 120mm.

Sân bay Long Thành đưa vào khai thác nhưng đừng để hành khách kẹt xe trên cao tốc

Lê Thanh Phong |

Mưa lớn ảnh hưởng nghiêm trọng đến thi công sân bay Long Thành, làm gián đoạn nhiều hạng mục, các công trình ngầm như hệ thống thoát nước, nền đường…

Báo cáo Chính phủ và 2 Bộ triển khai đường cất hạ cánh thứ 3 dự án sân bay Long Thành

HÀ ANH CHIẾN |

Đồng Nai - ACV đã có tờ trình báo cáo Chính phủ, Bộ Tài chính, Bộ Xây dựng triển khai đường cất hạ cánh thứ 3 và giai đoạn 2 sân bay Long Thành.

Overcoming the sun and rain, mobilizing nearly 14,000 human resources to construct Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport project is under construction in unfavorable weather due to continuous heavy rain in September.