Overcoming the sun and rain, mobilizing nearly 14,000 human resources to construct Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport project is under construction in unfavorable weather due to continuous heavy rain in September.

September rain for about 21 days at Long Thanh airport project

According to Vietnam Airports Corporation (ACV), in September 2025, continuous heavy rain (about 21 days of rain) will seriously affect the entire construction work, disrupting many items, especially underground works such as tunnels, drainage systems, roadbeds, etc.

Du an thanh phan 3 - Cac cong trinh thiet yeu trong Cang hang khong thuoc Du an dau tu xay dung san bay Long Thanh giai doan 1 do ACV lam chu dau tu. Anh: HAC
Component project 3 - Essential works in the Airport under the Long Thanh Airport Construction Investment Project Phase 1 invested by ACV. Photo: HAC

ACV has directed contractors to have appropriate construction measures, mobilizing hundreds of construction teams, nearly 14,000 experts, engineers, workers, laborers and about 3,000 construction equipment to speed up the progress with the goal of basically completing the project by the end of 2025, putting it into operation and commercial exploitation in the first half of 2026.

To date, the entire project has 15 packages, of which 3 have been completed and 12 packages are under construction.

In particular, package 5.10 for the construction of the passenger terminal by Vietur consortium is the gantt road for the entire project. At the same time, it is also considered the heart of Long Thanh airport.

Package 5.10 started in August 2023 with a completion schedule of 39 months (until November 30, 2026). Then the progress was adjusted to strive to complete the basic construction and installation of equipment before December 31, 2025; Conduct acceptance, training and testing before May 31, 2026.

Currently, the construction of the main roof and the surrounding roof areas has been completed in August 2025.

The roof has also been basically completed in September 2025 and is expected to complete the central area roof layers before November 30, 2025.

The steel structure of the cable-stayed bridge will also be completed before October 30, 2025 and the roof of the cable-stayed bridge will be completed before November 30, 2025.

The runway has been completed, welcoming the first standard flight

Currently, ACV has made efforts and directed contractors to complete the installation of mechanical equipment for the baggage handling system in the western wing area before December 19, 2025; At the same time, ACV urged to urgently speed up production and transport all equipment to the construction site in December 2025 to complete the electricity construction and connection work, validation, trial operation and officially handover for operation in early June 2026.

Nha ga hanh khach duoc vi nhu trai tim du an san bay Long Thanh. Anh: HAC
The passenger terminal is considered the heart of the Long Thanh airport project. Photo: HAC

Complete the installation of luggage-centric screening machines before December 19, 2025, the security screening equipment installation items are ready for installation.

Complete the installation of 28/64 passenger bridges before December 19, 2025; the remaining passenger bridges will be completed and installed in the first quarter of 2026.

The aircraft mooring system will also complete the installation of 130 sets before December 31, 2025.

The escalator system, sidewalk elevators, and elevators are expected to be completed and installed in December 2025 when the construction site meets safety and waterproof conditions and the site is handed over promptly by the construction contractor.

Goi thau nhu goi thau 4.6 den nay co ban da hoan thanh hang muc duong cat ha canh. Anh: HAC
Package 4.6 has basically completed the runway item. Photo: HAC

In addition, packages such as package 4.6 have basically completed the runway item. On September 26, 2025, Long Thanh airport officially welcomed its first standard flight; Package 6.12 up to now, route No. 1 was technically opened to traffic on April 30, 2025, route No. 2 has paved 90% of asphalt concrete, aiming to complete the entire package 6.12 in November 2025.

Some images of Long Thanh airport construction in September 2025 in Dong Nai:

Co ban hoan thanh phan xay dung bao gom cong tac be tong cot thep, ket cau thep... truoc 19.12.2025. Anh: HAC
Basically complete the construction including reinforced concrete, steel structure... before December 19, 2025. Photo: HAC
Cong nhan lao dong thi cong tai goi thau 5.10 nha ga hanh khach san bay Long Thanh. Anh: HAC
Workers constructing at package 5.10 of Long Thanh airport passenger terminal. Photo: HAC
Nha thau da hoan thien co ban cac lop mai khu canh trong thang 9.2025 va du kien hoan thanh lop mai khu trung tam truoc ngay 30.11.2025. Anh: HAC
The contractor has basically completed the roof layers of the wing area in September 2025 and is expected to complete the roof layer of the central area before November 30, 2025. Photo: HAC
Cong nhan miet mai thi cong tai du an san bay Long Thanh. Anh: HAC
Workers are working hard at the Long Thanh airport project. Photo: HAC
Ket cau thep khu cau ong long hoan thanh truoc ngay 30.10 nay va phan mai khu cau ong long muc tieu se hoan thanh truoc ngay sau do 1 thang. Anh: HAC
The steel structure of the cable-stayed bridge will be completed before October 30 and the roof of the cable-stayed bridge will be completed 1 month later. Photo: HAC
Cong tac op lat da nha ga hanh khach san bay Long Thanh hoan thanh truoc 19.12.2025. Anh: HAC
The paving of the Long Thanh airport passenger terminal will be completed before December 19, 2025. Photo: HAC

Component project 3 - Essential works in the Airport under the Long Thanh International Airport Construction Investment Project Phase 1 invested by ACV. The scale of phase 1 of the project with 2 runways, 1 passenger terminal and synchronous auxiliary items with a capacity of 25 million passengers/year; 1.2 million tons of cargo/year. The project has a total investment of more than VND 99,000 billion, basically completed in 2025; put into operation and commercial exploitation in the first half of 2026.

HÀ ANH CHIẾN
RELATED NEWS

Dong Nai reclaims land to build bridges connecting the Central Highlands provinces to Long Thanh airport

|

Dong Nai - Ma Da Bridge forms an inter-regional traffic axis connecting the Central Highlands provinces to Long Thanh airport and Cai Mep - Thi Vai deep-water port.

International flight over 1,000km at Long Thanh airport, under 1,000km at Tan Son Nhat airport

|

The Ministry of Construction submitted to the Government a plan to exploit an international flight route of over 1,000km at Long Thanh airport and under 1,000km at Tan Son Nhat airport.

Long Thanh airport welcomes the first standard flight, approaching the inauguration target of December 19

|

Dong Nai - The standard flight at Long Thanh airport will last from September 26 to October 24, approaching the inauguration target on December 19, 2025.

Ho Chi Minh City Party Secretary Tran Luu Quang and hundreds of delegates experience Metro Line 1

|

HCMC - On the morning of October 12, Metro Line 1 welcomed a special delegation including Ho Chi Minh City Party Secretary Tran Luu Quang and delegates attending the Ho Chi Minh City Party Congress.

The billion-dollar construction site to upgrade National Highway 279 resumes construction after the storm

|

Lao Cai - After the storm and flood, machinery and workers have returned to the construction site of National Highway 279 through Van Ban district (old) to urgently construct to keep up with the project's progress.

La Nina returns, forecast of heavy rain and storms, increased risk of flooding

|

La Nina has returned to the Pacific Ocean, causing Southeast Asia - including both Vietnam and the Philippines - to face the risk of unusual storms and increased flooding.

Striker Xuan Son is about to return to play in the V.League

|

Striker Xuan Son returned to play in the friendly match between Nam Dinh club and PVF-CAND.

Dong Nai reclaims land to build bridges connecting the Central Highlands provinces to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Ma Da Bridge forms an inter-regional traffic axis connecting the Central Highlands provinces to Long Thanh airport and Cai Mep - Thi Vai deep-water port.

International flight over 1,000km at Long Thanh airport, under 1,000km at Tan Son Nhat airport

Xuyên Đông |

The Ministry of Construction submitted to the Government a plan to exploit an international flight route of over 1,000km at Long Thanh airport and under 1,000km at Tan Son Nhat airport.

Long Thanh airport welcomes the first standard flight, approaching the inauguration target of December 19

NHƯ QUỲNH |

Dong Nai - The standard flight at Long Thanh airport will last from September 26 to October 24, approaching the inauguration target on December 19, 2025.