More than 900 houses in Binh Dinh cracked due to traffic project

Hoài Phương |

Up to now, the project to renovate and upgrade National Highway 19 through Binh Dinh province has caused cracks in more than 1,200 houses. However, the investor has only compensated nearly 1/4 of the above figure. Currently, more than 900 houses are still struggling to wait for compensation.

Road construction, causing damage to thousands of houses

The Central Highlands Region Traffic Connectivity Enhancement Project (National Highway 19 Improvement and Upgrade Project) has a total length of over 143km (17km through Tay Son district, Binh Dinh province; 126.34km through Gia Lai province), with a total investment of over VND 3,650 billion, invested by Project Management Board 2 (Ministry of Transport).

It is expected that by the end of October 2024, the construction unit will complete the XL-01 package of this project. However, currently, site clearance work at some locations on the route is still "not yet completed" and compensation and support for houses that have been cracked due to project construction have not been completely resolved.

According to the People's Committee of Tay Son district, up to now, the progress of the land acquisition and clearance project to renovate and upgrade National Highway 19 still has 8 electric poles on the frontage road that need to be relocated. The capital plan for compensation and site clearance for the project in 2024 is 57,594 billion VND, but currently the investor has only transferred nearly 34 billion VND to the locality.

As of September 16, the total number of households whose houses and structures were cracked due to project construction was 1,201 (781 households in Tay Giang commune and 420 households in Tay Thuan commune), the number of households whose damages had been assessed was 1,054 (113 households had not agreed with the assessment results). Of which, the investor had paid compensation to 138 households, with an amount of more than 690 million VND; the number of households that had agreed to receive the money was 150 households, with a compensation amount of more than 1 billion VND.

Slow compensation

Speaking to Lao Dong, Mr. Nguyen Van Khanh - Vice Chairman of Tay Son District People's Committee - said that the locality is urging the investor and project unit to compensate the remaining households with cracked houses. Regarding land acquisition, the district has so far paid compensation to 46 households in the area from Bau Sen bridge to Ba La bridge.

"We are currently relocating the remaining electric poles on the road surface, and at the same time, we are requesting Project Management Board 2 to add a road in the Bau Sen bridge area. Regarding the complaints of households whose houses are cracked, I will work with Project Management Board 2 to resolve them this week. Recently, at a meeting with the province, Deputy Minister of Transport Le Anh Tuan promised to urge the investor to speed up compensation for households whose houses are cracked due to project construction" - Mr. Khanh said.

Previously, at the end of August 2024, Deputy Minister of Transport Le Anh Tuan had a working session with the People's Committee of Binh Dinh province and Project Management Board 2 to remove obstacles in the project to renovate and upgrade National Highway 19.

At the meeting, Deputy Minister Le Anh Tuan requested the investor and contractor to work with the insurance company to pay compensation to people whose houses were affected by the project. In case people complain or sue with profit motives, they should report to the Tay Son District People's Committee and the leaders of the Binh Dinh Provincial People's Committee for handling.

Besides, the Deputy Minister also requested Project Management Board 2 and the contractor to focus on completing the project on schedule.

Living miserably because of the project

According to households in Ta Giang 2 village (Tay Giang commune, Tay Son district), since the construction unit implemented the project, the national highway roadbed has been raised 3-4m higher than the houses, and people living along both sides of the national highway have had to live with dust year after year. What makes households even more fearful is the situation of houses with large cracks and broken connections, which can collapse at any time.

Hoài Phương
RELATED NEWS

Conservation of rare Hong Hoang individuals in Phong Nha - Ke Bang

|

Quang Tri - Rare Hong Hoang individuals are being rescued and cared for to continue their journey to return to nature in Phong Nha - Ke Bang.

Gold price update on the morning of December 9: Decreased due to selling pressure

|

Gold price update on the morning of December 9: World gold prices reversed and decreased last night. Domestic gold may decrease accordingly in today's trading session.

Live TV schedule of the opening ceremony of the 33rd SEA Games

|

The opening ceremony of the 33rd SEA Games will take place at 8:00 p.m. on December 9 at Rajamangala National Stadium, live on FPT Play.

Live football match between Vietnam and Philippines women's team at SEA Games 33

|

Live match between the Vietnamese and Philippine women's teams at the 33rd SEA Games, taking place at 6:30 p.m. today (December 8).

Suspending a "blood transplant" tubal treatment facility after a report from Lao Dong Newspaper

|

Hue - The interdisciplinary inspection team has temporarily suspended the operation of the Mb Center sewer treatment facility on To Huu Street after discovering many serious violations.

Dự án giao thông 400 tỉ đồng ở Lâm Đồng xin lùi tiến độ

PHAN TUẤN - PHẠM QUANG |

Lâm Đồng - Chủ đầu tư đường Cam Ly - Phước Thành có tổng mức đầu tư 400 tỉ đồng vừa xin chủ trương điều chỉnh thời gian hoàn thành dự án sau năm 2024.

Khổ vì dự án giao thông 1.300 tỉ chậm tiến độ

NHÓM PV |

Dự án giao thông 1.300 tỉ tại Điện Biên được kỳ vọng sẽ là “cú hích” để phát triển. Tuy nhiên, do dự án chậm tiến độ đã ảnh hưởng tới cuộc sống nhiều người.

3 dự án giao thông lớn ở Đồng Nai thi công xuyên lễ 2.9

HÀ ANH CHIẾN |

Đồng Nai - Các kỹ sư, công nhân vẫn thi công xuyên lễ trên công trường dự án giao thông trọng điểm sân bay Long Thành, Vành đai 3 TPHCM và Bến Lức - Long Thành.