On July 23, Hung Phu Commune People's Committee, Hung Yen province organized the payment of compensation and support for site clearance (GPMB) to implement the project to invest in building main roads connecting with functional areas in Thai Binh Economic Zone - route No. 3. The total payment amount this time is 193 billion VND.
The project to invest in building main roads connecting with functional areas in Thai Binh Economic Zone (Hung Yen province) includes 5 routes with a total investment of more than 3,000 billion VND. In which, route No. 3 has a length of more than 13km, playing an important role in completing transport infrastructure in coastal areas and creating motivation to attract investment.
In Hung Phu commune, the site clearance work in the Nga 6 intersection area (former Nam Hung commune) is the biggest bottleneck, directly affecting the project implementation progress. In this area, there are a total of 134 land plots of 116 households subject to site clearance.
To remove difficulties, Hung Phu Commune People's Committee launched the 30-day peak campaign to propagate and mobilize site clearance for Nga 6 intersection (former Nam Hung intersection) of road No. 3, starting from June 4 to July 3.