Can Tho - Ca Mau Expressway accelerates asphalt paving without holidays

Tạ Quang |

Hau Giang - Taking advantage of good weather, the contractor constructed the Can Tho - Ca Mau expressway with asphalt in each segment.

According to Lao Dong Newspaper at the IC5 intersection on the Can Tho - Ca Mau expressway, there are many workers and machinery concentrated at the construction site to speed up the progress.

Cao toc Can Tho - Ca Mau doan qua dia ban tinh Hau Giang. Anh: Ta Quang
Can Tho - Ca Mau Expressway section passes through Hau Giang province. Photo: Ta Quang

Mr. Nguyen Thanh Vinh - Deputy Executive Director of Truong Son Nam Board - informed that the construction unit has constructed 21km of road with 20 bridges, so far, the construction volume has reached about 71%.

According to Mr. Nguyen Thanh Vinh, currently, the contractor has arranged 5 construction teams for the route. The teams are focusing on the unloading and construction stages of crushed stone and asphalt concrete.

Ong Nguyen Thanh Vinh - Pho Giam doc dieu hanh Ban Truong Son Nam. Anh: Ta Quang
Mr. Nguyen Thanh Vinh - Deputy Executive Director of Truong Son Nam Board. Photo: Ta Quang

As for the bridge, over 90% of progress has been completed, and is currently in the process of paving the bridge deck with asphalt concrete and installing railings, completing the remaining stages.

Currently, there are about 150 engineers and workers working at the construction site with the spirit of "3 shifts, 4 teams", "not enough work during the day, take advantage of working at night". In particular, during this April 30 - May holiday, taking advantage of favorable sunny weather, the unit will continue to carry out construction through the holiday, focusing on construction at all construction sites, and will arrange time for repayment.

"From now until the occasion of April 30, the unit will conduct plastic carpet of paragraph KM49+400 (expected on 25.4).

May moc duoc tap trung trien khai thi cong. Anh: Ta Quang
Machinery is focused on implementing the construction. Photo: Ta Quang

According to Mr. Vinh, during holidays or overtime, the Corporation will go to the construction site to encourage the spirit and give gifts to engineers and workers, and at the same time have a full salary and overtime regime for everyone.

For the goal of the Prime Minister, on December 19, the Can Tho - Ca Mau highway must be completed, the unit has set specific timelines to strive. Accordingly, on the bridge, it must be completed on June 30, the work of the road and the unloading of roads must be completed on September 30, while the plastic carpet work must be completed before November 30. The remaining days of December will complete the paint line paint and items to ensure traffic safety.

Ong Nguyen Van Trieu - Cong nhan thi cong cao toc Can Tho - Ca Mau. Anh: Ta Quang
Mr. Nguyen Van Trieu - Workers constructing the Can Tho - Ca Mau Expressway. Photo: Ta Quang

Mr. Nguyen Van Trieu - a worker on the Can Tho - Ca Mau expressway shared that despite continuous overtime and teamwork, thanks to the close encouragement from the contractor, the spirit of dedication of the brothers is always burning, trying to speed up the project's progress.

"When we saw the expressway project passing through our locality, we were very excited, expecting the economy to develop much more. Therefore, the workers are trying to encourage each other and work hard to complete the project on schedule, said Mr. Trieu.

Thiet bi lu nen duong de chuan bi cho cong tac tham nhua be tong. Anh: Ta Quang
Roadbed rolling equipment to prepare for asphalt concrete paving. Photo: Ta Quang

According to My Thuan Project Management Board, to date, the construction output has reached 66/70% of the plan. The project has basically removed difficulties and obstacles in materials. In the coming time, all bridges on the route will be completed before April 30. Complete 100% of the work of reloading the entire route on April 30.

Previously, on April 20, Prime Minister Pham Minh Chinh and the working delegation inspected the Can Tho - Ca Mau expressway. At the inspection, the Prime Minister requested units to continue researching and applying science and technology to shorten loading and construction time, striving to complete it earlier, but must strictly comply with the design, ensure quality, technique, art, environmental protection and must be absolutely safe when putting the project into use.

Tạ Quang
TIN LIÊN QUAN

Investors inform about compensation for people in the dead rice crop next to the highway

|

My Thuan Project Management Board has coordinated with Hau Giang provincial authorities to help people affected by dead rice next to the Can Tho - Ca Mau expressway

Day and night construction of Can Tho - Ca Mau expressway after the Prime Minister's direction

|

In order for the Can Tho - Ca Mau expressway to be completed by December 19 at the latest, the contractor has proactively developed a detailed plan, with the goal of completing the asphalt paving by the end of November.

Urgently compensate people with dead rice next to the Can Tho - Ca Mau Expressway

|

The Deputy Prime Minister requested an urgent review, statistics and compensation for damages to people with dead rice next to the Can Tho - Ca Mau Expressway.

Director of "Southern Forest Land" Nguyen Quang Dung suffered a heart attack

|

Sharing with reporters, director Nguyen Quang Dung said that he had a heart attack. After a period of treatment, his health was stable and he was discharged from the hospital.

Be careful with peak season tour scams

|

The 30/1-5 holiday is approaching, causing fraud in travel combos, hotel rooms, air tickets, etc. to increase. Tourists need to be very vigilant.

sad ending for Ange Postecoglou at Tottenham

|

Despite his efforts in the Europa League this season, Ange Postecoglou may have to endure a bitter end regardless of the result.

Need to verify quickly, severely punish those who illegally dump waste

|

Hanoi - Stolen waste causes loss of urban beauty, environmental pollution and many other consequences.

From waste, electrical ash and slag are as expensive as fresh shrimp, must be auctioned

|

Quang Ninh - Once an environmental obsession, considered waste and ashes of thermal power plants, suddenly became a sought-after item.

Investors inform about compensation for people in the dead rice crop next to the highway

Tạ Quang |

My Thuan Project Management Board has coordinated with Hau Giang provincial authorities to help people affected by dead rice next to the Can Tho - Ca Mau expressway

Day and night construction of Can Tho - Ca Mau expressway after the Prime Minister's direction

Tạ Quang |

In order for the Can Tho - Ca Mau expressway to be completed by December 19 at the latest, the contractor has proactively developed a detailed plan, with the goal of completing the asphalt paving by the end of November.

Urgently compensate people with dead rice next to the Can Tho - Ca Mau Expressway

PHẠM ĐÔNG |

The Deputy Prime Minister requested an urgent review, statistics and compensation for damages to people with dead rice next to the Can Tho - Ca Mau Expressway.