Kon Tum speeds up the progress of key lake and dam projects

THANH TUẤN |

Kon Tum - Dams are being accelerated to ensure clean water for daily life and agricultural production.

On April 12, the People's Committee of Kon Tum province requested districts and investors to urgently complete documents, clear land and construct key lake and dam projects in the area.

Kon Tum Provincial People's Committee assigned the Management Board of Investment Projects for Construction of Agricultural Works and Rural Development to coordinate in speeding up compensation, site clearance and construction of works including: Dak Bla River Bank Landslide Treatment Project and Component Project No. 1 - Ia Tun Reservoir (belonging to the Dak Ro Gia - Ia Tun project cluster).

The Project Management Board needs to promptly complete the feasibility study report and procedures related to Component Project No. 2 - Dak Ro Gia Reservoir, according to the direction of the Ministry of Agriculture and Rural Development.

The above projects are key agricultural projects of the province, with a total investment of thousands of billions of VND, playing an important role in providing irrigation water, serving people's lives and responding to natural disasters and floods.

The Project Management Board is responsible to the Provincial People's Committee and the Ministry of Agriculture and Rural Development for the effectiveness of using the advance capital, and must focus on completing the workload to recover capital according to regulations.

The biggest difficulty at present is compensation and site clearance. The Provincial People's Committee assigned the People's Committees of Kon Tum City and Ngoc Hoi District to coordinate in handling; if problems arise, they should promptly report to the province for resolution.

In 2025, Kon Tum aims to disburse over 95% of public investment capital, while speeding up the progress of large-scale transportation, irrigation and agricultural infrastructure projects.

The province also directs the implementation of the motto "Liberation, compensation to where, construction go there".

For national-scale projects such as the Kon Tum - Quang Ngai expressway, the province is committed to completing site clearance before December 2026 to ensure construction progress.

THANH TUẤN
RELATED NEWS

Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30

|

Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.

The project to plant trees worth more than 4 billion VND has a series of dead trees

|

Ha Tinh - A tree planting project in Ky Anh town with a budget of more than 4 billion VND, but after planting, a series of trees died.

A series of key projects in Bac Kan will be completed in 2025

|

Bac Kan - Key projects with a total investment of hundreds of billions of VND are being accelerated, striving to reach the finish line in 2025.

Trailer truck fire on Ho Chi Minh City - Long Thanh - Dau Giay expressway

|

Dong Nai - A tractor-trailer traveling on the Ho Chi Minh City - Long Thanh - Dau Giay expressway (Nhon Trach ward section) suddenly caught fire.

Collecting rocks overflowing into the Gianh River due to blasting, clearing the flow

|

Quang Tri - Businesses have mobilized human resources and equipment to handle the volume of limestone falling into the Gianh River area and reduce dust when mining stone.

Line disguised as a spa treating bone and joint diseases, deceiving nearly 300 people

|

Nghe An - A line disguised as a spa facility, subjects advertised bone and joint disease treatment to deceive nearly 300 people, transacting more than 9 billion VND.

5 fishing boats caught fire in Nghe An, damage of about 6 billion VND

|

Nghe An - The fire at the fishing port in Quynh Phu commune caused 3 fishing boats to be burned down, 2 other boats damaged, and estimated damage of about 6 billion VND.

Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30

Tạ Quang |

Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.

The project to plant trees worth more than 4 billion VND has a series of dead trees

TRẦN TUẤN |

Ha Tinh - A tree planting project in Ky Anh town with a budget of more than 4 billion VND, but after planting, a series of trees died.

A series of key projects in Bac Kan will be completed in 2025

Lam Thanh |

Bac Kan - Key projects with a total investment of hundreds of billions of VND are being accelerated, striving to reach the finish line in 2025.