Kon Tum speeds up the progress of key lake and dam projects

THANH TUẤN |

Kon Tum - Dams are being accelerated to ensure clean water for daily life and agricultural production.

On April 12, the People's Committee of Kon Tum province requested districts and investors to urgently complete documents, clear land and construct key lake and dam projects in the area.

Kon Tum Provincial People's Committee assigned the Management Board of Investment Projects for Construction of Agricultural Works and Rural Development to coordinate in speeding up compensation, site clearance and construction of works including: Dak Bla River Bank Landslide Treatment Project and Component Project No. 1 - Ia Tun Reservoir (belonging to the Dak Ro Gia - Ia Tun project cluster).

The Project Management Board needs to promptly complete the feasibility study report and procedures related to Component Project No. 2 - Dak Ro Gia Reservoir, according to the direction of the Ministry of Agriculture and Rural Development.

The above projects are key agricultural projects of the province, with a total investment of thousands of billions of VND, playing an important role in providing irrigation water, serving people's lives and responding to natural disasters and floods.

The Project Management Board is responsible to the Provincial People's Committee and the Ministry of Agriculture and Rural Development for the effectiveness of using the advance capital, and must focus on completing the workload to recover capital according to regulations.

The biggest difficulty at present is compensation and site clearance. The Provincial People's Committee assigned the People's Committees of Kon Tum City and Ngoc Hoi District to coordinate in handling; if problems arise, they should promptly report to the province for resolution.

In 2025, Kon Tum aims to disburse over 95% of public investment capital, while speeding up the progress of large-scale transportation, irrigation and agricultural infrastructure projects.

The province also directs the implementation of the motto "Liberation, compensation to where, construction go there".

For national-scale projects such as the Kon Tum - Quang Ngai expressway, the province is committed to completing site clearance before December 2026 to ensure construction progress.

THANH TUẤN
RELATED NEWS

Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30

|

Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.

The project to plant trees worth more than 4 billion VND has a series of dead trees

|

Ha Tinh - A tree planting project in Ky Anh town with a budget of more than 4 billion VND, but after planting, a series of trees died.

A series of key projects in Bac Kan will be completed in 2025

|

Bac Kan - Key projects with a total investment of hundreds of billions of VND are being accelerated, striving to reach the finish line in 2025.

Ho Chi Minh City University of Economics and Finance recruits 800 additional targets

|

On August 12, Ho Chi Minh City University of Economics and Finance (UEF) announced additional admissions for 800 full-time university level targets in 2026.

2 rescuers killed in cargo ship attack in Red Sea

|

The attack on the cargo ship hit rescue forces evacuating the crew, marking the first death since the regional conflict broke out.

19-year-old male student falls into a deep abyss on Son Tra mountain, Da Nang

|

Da Nang - A 19-year-old male student fell into a deep abyss on Son Tra mountain at night, and was urgently rescued by functional forces.

Drone intrusion incident at Tan Son Nhat airport: Plane changes direction, passengers disrupt schedule

|

Ho Chi Minh City - On the evening of August 11, it was recorded that at Terminal T1 of Tan Son Nhat airport, many Vietjet flights to Ho Chi Minh City were affected in take-off and landing operations after UAVs were detected.

Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30

Tạ Quang |

Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.

The project to plant trees worth more than 4 billion VND has a series of dead trees

TRẦN TUẤN |

Ha Tinh - A tree planting project in Ky Anh town with a budget of more than 4 billion VND, but after planting, a series of trees died.

A series of key projects in Bac Kan will be completed in 2025

Lam Thanh |

Bac Kan - Key projects with a total investment of hundreds of billions of VND are being accelerated, striving to reach the finish line in 2025.