Kon Tum speeds up the progress of key lake and dam projects

THANH TUẤN |

Kon Tum - Dams are being accelerated to ensure clean water for daily life and agricultural production.

On April 12, the People's Committee of Kon Tum province requested districts and investors to urgently complete documents, clear land and construct key lake and dam projects in the area.

Kon Tum Provincial People's Committee assigned the Management Board of Investment Projects for Construction of Agricultural Works and Rural Development to coordinate in speeding up compensation, site clearance and construction of works including: Dak Bla River Bank Landslide Treatment Project and Component Project No. 1 - Ia Tun Reservoir (belonging to the Dak Ro Gia - Ia Tun project cluster).

The Project Management Board needs to promptly complete the feasibility study report and procedures related to Component Project No. 2 - Dak Ro Gia Reservoir, according to the direction of the Ministry of Agriculture and Rural Development.

The above projects are key agricultural projects of the province, with a total investment of thousands of billions of VND, playing an important role in providing irrigation water, serving people's lives and responding to natural disasters and floods.

The Project Management Board is responsible to the Provincial People's Committee and the Ministry of Agriculture and Rural Development for the effectiveness of using the advance capital, and must focus on completing the workload to recover capital according to regulations.

The biggest difficulty at present is compensation and site clearance. The Provincial People's Committee assigned the People's Committees of Kon Tum City and Ngoc Hoi District to coordinate in handling; if problems arise, they should promptly report to the province for resolution.

In 2025, Kon Tum aims to disburse over 95% of public investment capital, while speeding up the progress of large-scale transportation, irrigation and agricultural infrastructure projects.

The province also directs the implementation of the motto "Liberation, compensation to where, construction go there".

For national-scale projects such as the Kon Tum - Quang Ngai expressway, the province is committed to completing site clearance before December 2026 to ensure construction progress.

THANH TUẤN
RELATED NEWS

Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30

|

Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.

The project to plant trees worth more than 4 billion VND has a series of dead trees

|

Ha Tinh - A tree planting project in Ky Anh town with a budget of more than 4 billion VND, but after planting, a series of trees died.

A series of key projects in Bac Kan will be completed in 2025

|

Bac Kan - Key projects with a total investment of hundreds of billions of VND are being accelerated, striving to reach the finish line in 2025.

Incentives and support for the development of social housing and public housing in the Capital

|

The draft revised Capital Law stipulates mechanisms and policies for housing development investment in the area. Especially incentives and support for social housing development.

Gold price update morning of March 20: Deep drop, breaking the 4,600 USD/ounce mark

|

Gold price update morning of March 20: World gold last night continued to plummet, falling by more than 280 USD/ounce.

Fire at a "singing for each other" shop, 3 people managed to escape

|

Hanoi - Fire at a "singing for each other" bar at the beginning of alley 60 Dinh Cong Ha street, Dinh Cong ward, 3 people escaped in time.

Opportunity for Man United stars to return to England

|

Harry Maguire is likely to be recalled to the England national team, alongside another Man United player, Kobbie Mainoo.

Selling civil servant exam preparation materials on social networks

|

Quang Tri - Many websites advertise and sell exam preparation materials for civil servants, the Department of Education and Training affirms that they are not official documents.

Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30

Tạ Quang |

Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.

The project to plant trees worth more than 4 billion VND has a series of dead trees

TRẦN TUẤN |

Ha Tinh - A tree planting project in Ky Anh town with a budget of more than 4 billion VND, but after planting, a series of trees died.

A series of key projects in Bac Kan will be completed in 2025

Lam Thanh |

Bac Kan - Key projects with a total investment of hundreds of billions of VND are being accelerated, striving to reach the finish line in 2025.