The two expressway projects Tan Phu - Bao Loc and Bao Loc - Lien Khuong pass through Da Teh, Da Huoai, Bao Lam, Di Linh, Duc Trong districts and Bao Loc city (Lam Dong province) with a total length of the entire route. about 140 km.
Mr. Vo Ngoc Minh Phat - Deputy Head of the Transport Project Management Board of Lam Dong province - said that the unit is actively coordinating with investors and related agencies to speed up the progress of completing documents. Thereby, it will be possible to start construction on two expressway projects: Tan Phu - Bao Loc and Bao Loc - Lien Khuong in December 2024.
Up to this point, the feasibility study report and basic design of the Tan Phu - Bao Loc expressway project have been submitted to the Ministry of Transport by the Provincial People's Committee.
Tan Phu - Bao Loc and Bao Loc - Lien Khuong expressway projects are two component projects on the 200km long Dau Giay - Lien Khuong expressway. These projects connect Da Lat city, the center of Lam Dong province with Ho Chi Minh City and the Southeast provinces.
Lam Dong province's traffic project management board has just been assigned by the Provincial People's Committee to develop an implementation plan to launch a response to the peak emulation round "500 days and nights of high determination, great efforts, emulation to successfully complete projects." expressway project ".
In the immediate future, the Provincial People's Committee requires this agency to immediately develop plans, assign tasks, and determine specific timelines for each stage to urgently implement the Tan Phu - Bao Loc and Bao Loc Expressway Projects. Loc - Lien Khuong.
Phase 1 is 140 days and nights focusing on removing difficulties and obstacles and completing investment procedures. Phase 2 is 360 days and nights of construction and technical traffic opening.