Ca Mau provincial leaders go to the construction site to promote key projects

NHẬT HỒ |

Ca Mau - In the face of low public investment disbursement, on November 14 and 15, many provincial leaders went to the construction site to remove difficulties.

In the Bac Lieu area (old), Mr. Huynh Quoc Viet, Standing Deputy Secretary of the Provincial Party Committee, Chairman of the Vietnam Fatherland Front Committee of Ca Mau province, led a working delegation to inspect and survey the project to build a storm shelter and Cai Cung fishing port, along with a number of projects in Hiep Thanh ward, Bac Lieu ward and Vinh Trach ward.

Du an Ke hai ben bo song Bac Lieu, Ca Mau dang duoc thi cong. Anh: Nhat Ho
The project of Embankment on both sides of Bac Lieu River, Ca Mau is under construction. Photo: Nhat Ho

The delegation surveyed the project to repair the dike roof, overcome landslides and upgrade 7km of urgent dykes in Bac Lieu city (old), which has been basically completed and will be put into use in 2025.

In particular, the Bac Lieu River embankment investment project, including four packages, is under construction at 20 - 37% of the volume, but there are still problems with site clearance.

The delegation also inspected the project to build a storm shelter area and Cai Cung fishing wharf. The project has a total investment of 250 billion VND, currently, the construction progress is about 35% of the volume, including the following items: Ship anchor, ship crane, canal crane 130, part of the embankment protecting the fishing port area and the operator house.

Du an Benh vien Da khoa tinh Ca Mau day nhanh tien do thi cong. Anh: Nhat Ho
The Ca Mau General Hospital project speeds up construction progress. Photo: Nhat Ho

This project is expected to be completed in 2026. However, more than 30 cases in Dong Hai commune have not yet handed over the site, affecting the construction progress.

At the meeting, Mr. Huynh Quoc Viet requested the Project Management Board for Investment and Construction of Agricultural and Rural Development Works of Bac Lieu and related units to urgently speed up the progress.

In case the contractor does not meet the requirements, the contract will be resolutely terminated and replaced to complete the project as planned.

He also suggested that localities soon complete documents and procedures; increase propaganda and mobilize people to hand over land; have solutions to support affected households.

For cases where full measures have been applied but still do not comply, localities need to handle them according to regulations so as not to affect the overall progress of the project.

Previously, Vice Chairman of the Provincial People's Committee Nguyen Minh Luan visited the Ca Mau General Hospital Project to launch a 45-day and night competition peak here. The Ca Mau General Hospital project has a scale of 1,200 beds with a total investment of more than 3.3 trillion VND. The construction progress of this project is slower than planned.

Pho chu tich UBND tinh Ca Mau Nguyen Minh Luan phat dong thi dua 45 ngay dem tai Du an Benh vien Da khoa Ca Mau. Anh: Nhat Ho
Vice Chairman of Ca Mau Provincial People's Committee Nguyen Minh Luan launched the 45-day and night emulation campaign at the Ca Mau General Hospital Project. Photo: Nhat Ho

At the launching ceremony, Vice Chairman of the People's Committee of Ca Mau province Nguyen Minh Luan requested contractors to focus maximum on human resources, materials and equipment; organize continuous and scientific construction; work overtime, increase shifts according to weather conditions; and strictly comply with regulations on labor safety and construction quality. The teams need to clearly identify the projects and emulation work, commit to specific progress, and strive to exceed the set plan.

NHẬT HỒ
RELATED NEWS

Investing 96 billion VND to build and upgrade another section of the East Sea dike in Ca Mau

|

Ca Mau - The dike section is more than 2km long, with a total investment of up to 96 billion VND. Notably, the compensation and clearance for this project is equal to 50% of the actual construction cost.

Low public investment disbursement, Ca Mau adjusts capital for a series of projects

|

Ca Mau - On November 13, at the 4th session (special session), the People's Council of Ca Mau province passed a resolution to adjust the capital of a series of projects.

Removal of Vice Chairman of Ca Mau Provincial People's Committee

|

Ca Mau - The Provincial People's Council has reviewed and voted to dismiss Mr. Huynh Huu Tri from the position of Vice Chairman of the Provincial People's Committee due to receiving a new assignment.

Ca Mau determined to unblock power

|

As a coastal province, far from the center, Ca Mau is gradually becoming a bright spot in how to take advantage of natural potential to unblock power lines.

Ca Mau Provincial People's Committee works with EVNNPT on implementing transmission projects in the area

|

The People's Committee of Ca Mau province worked with EVNNPT on the investment and construction situation of power transmission projects, focusing on the Bac Lieu - Thot Not 500 kV LNG transmission line project.

Ca Mau still has civil servants and public employees who are not assigned to the right job positions

|

Ca Mau - Regarding personnel work, the provincial leaders frankly acknowledge that there are still shortcomings, limitations, difficulties and problems.

IVS teachers' journey to change the control of individual students, addicted to games, depression to find themselves

|

At IVS Boarding School, many students who have experienced games and become lost have changed thanks to the patience and support of teachers to help them find their way back.

Live football U22 Vietnam vs U22 Uzbekistan at Panda Cup 2025

|

Live football U22 Vietnam and U22 Uzbekistan at Panda Cup 2025, taking place at 2:30 p.m. today (November 15).

Investing 96 billion VND to build and upgrade another section of the East Sea dike in Ca Mau

NHẬT HỒ |

Ca Mau - The dike section is more than 2km long, with a total investment of up to 96 billion VND. Notably, the compensation and clearance for this project is equal to 50% of the actual construction cost.

Cán bộ Cà Mau đi công tác quá 15km được thanh toán đến 200.000 đồng/ngày/người

NHẬT HỒ |

Cà Mau - Ngoài việc được thanh toán tiền lưu trú, cán bộ nếu dự hội nghị còn được nhận thêm tiền giải khát 50.000 đồng/người.

Low public investment disbursement, Ca Mau adjusts capital for a series of projects

NHẬT HỒ |

Ca Mau - On November 13, at the 4th session (special session), the People's Council of Ca Mau province passed a resolution to adjust the capital of a series of projects.

Removal of Vice Chairman of Ca Mau Provincial People's Committee

NHẬT HỒ |

Ca Mau - The Provincial People's Council has reviewed and voted to dismiss Mr. Huynh Huu Tri from the position of Vice Chairman of the Provincial People's Committee due to receiving a new assignment.

Ca Mau determined to unblock power

NHẬT HỒ |

As a coastal province, far from the center, Ca Mau is gradually becoming a bright spot in how to take advantage of natural potential to unblock power lines.

Ca Mau Provincial People's Committee works with EVNNPT on implementing transmission projects in the area

Phương Anh |

The People's Committee of Ca Mau province worked with EVNNPT on the investment and construction situation of power transmission projects, focusing on the Bac Lieu - Thot Not 500 kV LNG transmission line project.

Ca Mau still has civil servants and public employees who are not assigned to the right job positions

NHẬT HỒ |

Ca Mau - Regarding personnel work, the provincial leaders frankly acknowledge that there are still shortcomings, limitations, difficulties and problems.