A series of key projects in Dak Nong are behind schedule

BẢO LÂM |

Dak Nong – Despite many efforts, the locality is facing many difficulties in implementing 4 key projects.

On November 30, information from the Dak Nong Provincial People's Committee said that there are a number of key projects in the province that are facing difficulties in progress.

The Dao Nghia - Quang Khe Road Project, Dak Nong Province (Phase 2), has a total investment of VND 830 billion. The capital plan assigned in 2024 is VND 241.66 billion from the central budget. As of November 15, 2024, VND 6.25 billion has been disbursed, reaching 2.59%.

The biggest difficulty for this project is that the scope of the project overlaps with the bauxite exploration and exploitation planning. Therefore, the registration of the volume area, method, and land exploitation plan within the scope of the projects has not been carried out. It is expected that the project will not be able to disburse 147 billion VND.

Dak Nong General Hospital Upgrade Project, with a total investment of 753 billion VND. The capital plan assigned in 2024 is 150 billion VND, by November 15, 2024, 42.9 billion VND had been disbursed, reaching 28.6%.

The project is under construction, with the estimated completed volume reaching 23% of the construction contract value. There are some difficulties in renovating and repairing the existing hospital while maintaining medical examination and treatment activities.

In addition, the renovation and repair work must be adjusted a lot because the old hospital area has degraded such as the toilet system, water supply and drainage, leaking roof, ceiling...

Most of the main equipment of the project is imported. Ordering, purchasing and installing equipment at the construction site takes a lot of time, affecting the disbursement progress of the project.

However, the biggest reason is still the lack of coordination between contractors and investors. This leads to slow implementation and disbursement of public investment capital in 2024.

Du an Nang cap Benh vien Da khoa tinh Dak Nong la mot trong so nhung cong trinh trong diem cua tinh. Anh: Nguyen Luong
The Dak Nong General Hospital upgrade project is one of the province's key projects. Photo: Nguyen Luong

Gia Nghia City Central Square Project, with a total investment of 400 billion VND from the central budget. Project implementation period 2022 - 2025.

The capital plan assigned in 2023 to the reporting period is 54 billion VND. As of November 15, 2024, 14.46 billion VND/35 billion VND has been disbursed, reaching 41.3% of the assigned capital plan. The project is under construction at a standstill due to some items facing problems with the source of land for the project.

In addition, the project area that requires site clearance is about 10.59 hectares, but Gia Nghia City People's Committee has only handed over 2.78 hectares in the core area of ​​the square for construction.

The project to relocate and resettle 212 households in the central area of ​​Gia Nghia town (now Gia Nghia city) has a total investment of 400 billion VND from the provincial budget.

The capital plan assigned in 2024 by the reporting period is 116.4 billion VND. By November 15, 2024, the unit had disbursed 49.5 billion VND, reaching 42.5% of the assigned capital plan...

The project is implemented in Nghia Duc ward, Nghia Thanh ward and Nghia Trung ward, with a total project area of ​​12.5 hectares.

Up to now, the site clearance work for the core area of ​​the project in Nghia Duc ward has been completed with a recovered area of ​​2.78 hectares and the number of affected households is 100 cases.

Construction volume up to now has reached 99% compared to the signed contract volume.

BẢO LÂM
TIN LIÊN QUAN

Tuyen Quang issues bidding criteria for land use projects

|

Tuyen Quang province has just issued a resolution stipulating criteria for deciding to conduct bidding to select investors to implement projects using land in the area.

Stock market "red hot", selling pressure increases sharply

|

The Vietnamese stock market opened the first session of the year with red covering the whole market, VN-Index dropped sharply to the 1,250 point area due to increased selling pressure.

Grammy 2024: Taylor Swift, Ariana Grande are empty-handed

|

The 2024 Grammys saw the success of many artists such as Kendrick Lamar, Beyonce and young rookies. Taylor Swift, Billie Eillish, Ariana Grande... went home empty-handed.

Queue up to buy gold for good luck at the beginning of the year

|

On the morning of the 6th day of Tet (February 3), domestic gold prices increased sharply. However, many people still spent time lining up to buy gold with the hope of bringing more luck in the new year.

President of Vietnam General Confederation of Labor wishes a happy new year to Lao Dong Newspaper

|

On the morning of February 3, Party Central Committee member and President of the Vietnam General Confederation of Labor Nguyen Dinh Khang congratulated the staff, reporters, editors and employees of Lao Dong Newspaper on the New Year.

National Assembly Chairman offers incense in memory of President Ho Chi Minh at House 67

|

On the morning of February 3 (the 6th day of Tet), National Assembly Chairman Tran Thanh Man offered incense in memory of President Ho Chi Minh at House 67, President Ho Chi Minh Relic Site.

Actress Barbie Hsu suddenly passed away

|

According to Chinese media reports on February 3, Barbie Hsu's relatives confirmed that she died of seasonal flu.

Mr. Nguyen Thanh Nghi received a new assignment

|

Ho Chi Minh City - Mr. Nguyen Thanh Nghi - Standing Deputy Secretary of the Ho Chi Minh City Party Committee holds the position of Secretary of the Party Committee of Ho Chi Minh City Party agencies for the 2020 - 2025 term.

Dự án bệnh viện nghìn tỉ bỏ hoang trên đất vàng Hà Nội

Nhật Minh |

Hà Nội - Nằm trên địa bàn quận Cầu Giấy (Hà Nội), dự án bệnh viện quốc tế Hoa Kỳ - Hà Nội rơi vào tình trạng thi công dở dang, bỏ hoang suốt nhiều năm qua.

Người dân khốn khổ bên dự án cấp bách hơn 597 tỉ đồng thi công ì ạch

Minh Nguyễn - Đặng Tình |

Dự án cấp bách đê ngăn lũ chống ngập úng Pheo - Chẹ hạ du sông Đà (TP Hòa Bình, tỉnh Hòa Bình) với tổng mức đầu tư hơn 597 tỉ đồng đang thi công ì ạch do thiếu mặt bằng trong khi tuyến đường cũ đang xuống cấp nghiêm trọng khiến người dân bức xúc.

Tuyen Quang issues bidding criteria for land use projects

Việt Bắc |

Tuyen Quang province has just issued a resolution stipulating criteria for deciding to conduct bidding to select investors to implement projects using land in the area.