On November 30, information from the Dak Nong Provincial People's Committee said that there are a number of key projects in the province that are facing difficulties in progress.
The Dao Nghia - Quang Khe Road Project, Dak Nong Province (Phase 2), has a total investment of VND 830 billion. The capital plan assigned in 2024 is VND 241.66 billion from the central budget. As of November 15, 2024, VND 6.25 billion has been disbursed, reaching 2.59%.
The biggest difficulty for this project is that the scope of the project overlaps with the bauxite exploration and exploitation planning. Therefore, the registration of the volume area, method, and land exploitation plan within the scope of the projects has not been carried out. It is expected that the project will not be able to disburse 147 billion VND.
Dak Nong General Hospital Upgrade Project, with a total investment of 753 billion VND. The capital plan assigned in 2024 is 150 billion VND, by November 15, 2024, 42.9 billion VND had been disbursed, reaching 28.6%.
The project is under construction, with the estimated completed volume reaching 23% of the construction contract value. There are some difficulties in renovating and repairing the existing hospital while maintaining medical examination and treatment activities.
In addition, the renovation and repair work must be adjusted a lot because the old hospital area has degraded such as the toilet system, water supply and drainage, leaking roof, ceiling...
Most of the main equipment of the project is imported. Ordering, purchasing and installing equipment at the construction site takes a lot of time, affecting the disbursement progress of the project.
However, the biggest reason is still the lack of coordination between contractors and investors. This leads to slow implementation and disbursement of public investment capital in 2024.
Gia Nghia City Central Square Project, with a total investment of 400 billion VND from the central budget. Project implementation period 2022 - 2025.
The capital plan assigned in 2023 to the reporting period is 54 billion VND. As of November 15, 2024, 14.46 billion VND/35 billion VND has been disbursed, reaching 41.3% of the assigned capital plan. The project is under construction at a standstill due to some items facing problems with the source of land for the project.
In addition, the project area that requires site clearance is about 10.59 hectares, but Gia Nghia City People's Committee has only handed over 2.78 hectares in the core area of the square for construction.
The project to relocate and resettle 212 households in the central area of Gia Nghia town (now Gia Nghia city) has a total investment of 400 billion VND from the provincial budget.
The capital plan assigned in 2024 by the reporting period is 116.4 billion VND. By November 15, 2024, the unit had disbursed 49.5 billion VND, reaching 42.5% of the assigned capital plan...
The project is implemented in Nghia Duc ward, Nghia Thanh ward and Nghia Trung ward, with a total project area of 12.5 hectares.
Up to now, the site clearance work for the core area of the project in Nghia Duc ward has been completed with a recovered area of 2.78 hectares and the number of affected households is 100 cases.
Construction volume up to now has reached 99% compared to the signed contract volume.