Metro No. 2 in Ho Chi Minh City simultaneously constructs 6 underground stations

MINH QUÂN |

HCMC - Metro No. 2 HCMC (Ben Thanh - Tham Luong) simultaneously constructs 6 underground stations, striving to bring TBM machines to drill tunnels from August 2027.

On September 21, the Ho Chi Minh City Urban Railway Management Board (MAUR) announced the progress of Metro Line 2 project (Ben Thanh - Tham Luong).

According to MAUR, construction is being deployed simultaneously at 6 underground stations including: Hoa Hung (ST04), Le Thi Rieng (ST05), Pham Van Hai (ST06), Bay Hien (ST07), Ba Queo (ST09) and Pham Van Bach (ST10).

At the same time, the contractor is urgently preparing the necessary conditions to deploy the construction of the remaining stations on the entire route.

Khu vực ga ngầm Tao Đàn của tuyến Metro số 2 đã tập kết thiết bị, chuẩn bị thi công. Ảnh: Minh Quân
The Tao Dan underground station area of Metro Line No. 2 has gathered equipment, preparing for construction in the near future. Photo: Minh Quan taken on September 17.

MAUR said that it is working with contractors to optimize the construction organization plan, striving to put TBM tunnel excavators into construction from August 2027.

The underground section of Metro Line 2 includes 2 single tunnels, with a total length of more than 9 km, stretching from Ben Thanh station to the Truong Chinh - Pham Van Bach intersection area.

Each tunnel has an outer diameter of 6.8 m and an inner diameter of 6.2 m. The maximum depth from the bottom of the tunnel to the natural ground is about 30 m.

According to the plan, Tham Luong depot will complete construction and receive the first train on July 30, 2029.

The project is expected to complete trial operation and system safety certification by December 31, 2030.

Metro No. 2 was started in January 2026, with a total investment of more than 55,000 billion VND from the Ho Chi Minh City budget.

The route has a length of nearly 11.27 km, of which about 9.3 km is underground and about 2 km is elevated. The entire route includes 10 underground stations, 1 elevated station and a depot in Tham Luong.

From Ben Thanh station, Metro Line 2 passes through 14 wards including Ben Thanh, Ban Co, Xuan Hoa, Hoa Hung, Vuon Lai, Nhieu Loc, Tan Hoa, Tan Son Nhat, Bay Hien, Tan Binh, Tan Son, Tay Thanh, Tan Son Nhi and Dong Hung Thuan before ending at Tham Luong depot.

In the initial phase of operation, Metro Line 2 is expected to use a 3-carriage train, with a maximum speed of about 80 - 110 km/h, and a transport capacity of about 14,400 passengers/hour/direction.

When put into operation, the Ben Thanh - Tham Luong Metro line is expected to create an additional large-volume public passenger transport axis, connecting the central area with the Northwest gateway of Ho Chi Minh City, and at the same time contributing to reducing traffic pressure on existing routes.

MINH QUÂN
RELATED NEWS

Metro line No. 2 barricades many roads, Ho Chi Minh City center at risk of congestion

|

Ho Chi Minh City - Many central roads will be converted to one-way or barricaded for Metro Line 2 construction, increasing the risk of congestion.

First day of traffic adjustment for Metro Line 2 construction: Some places are clear, some places are locally congested

|

Ho Chi Minh City - On the morning of September 16, the first day of Metro 2 traffic diversion, Tan Ky Tan Quy street was clear, while the Truong Chinh - Cong Hoa axis was heavily congested.

Ho Chi Minh City adjusts traffic at the Northwest gateway to construct Metro station No. 2

|

Ho Chi Minh City - From September 16, traffic on Truong Chinh, Tan Ky Tan Quy and Huynh Van Gam streets will be adjusted to construct Ba Queo station.

Metro No. 2 in Ho Chi Minh City simultaneously constructs 6 underground stations

|

HCMC - Metro No. 2 HCMC (Ben Thanh - Tham Luong) simultaneously constructs 6 underground stations, striving to bring TBM machines to drill tunnels from August 2027.

Live Vietnam women's team vs Thailand at ASIAD 20

|

Live broadcast of Vietnam women's team vs Thailand at ASIAD 20 taking place at 5:30 PM today (September 21).

Taluy Prenn Pass landslide due to heavy rain

|

Lam Dong - Prolonged heavy rain caused a large volume of soil and rock at the negative slope of Prenn Pass, near Datanla bridge, to landslide and drift into a ravine tens of meters deep.

Metro line No. 2 barricades many roads, Ho Chi Minh City center at risk of congestion

MINH QUÂN |

Ho Chi Minh City - Many central roads will be converted to one-way or barricaded for Metro Line 2 construction, increasing the risk of congestion.

First day of traffic adjustment for Metro Line 2 construction: Some places are clear, some places are locally congested

Ánh Tú |

Ho Chi Minh City - On the morning of September 16, the first day of Metro 2 traffic diversion, Tan Ky Tan Quy street was clear, while the Truong Chinh - Cong Hoa axis was heavily congested.

Ho Chi Minh City adjusts traffic at the Northwest gateway to construct Metro station No. 2

MINH QUÂN |

Ho Chi Minh City - From September 16, traffic on Truong Chinh, Tan Ky Tan Quy and Huynh Van Gam streets will be adjusted to construct Ba Queo station.