A 2,432 billion VND road project section in Hanoi will be temporarily opened to traffic in June

SÓNG HỮU |

Hanoi - Ring Road 2.5 section Nguyen Trai - Dam Hong is under construction, it is expected that about 500m at the end of the route will be temporarily opened to traffic in June.

According to Lao Dong's records on June 8 and 9, the shape of Ring Road 2.5 section Nguyen Trai - Dam Hong (Khuong Dinh ward, Hanoi) has been revealed after a series of projects were demolished.

Machinery is mobilized to dismantle the final works to hand over the site to the construction unit.

For the sections with site clearance, the joint venture of contractors Hugia Investment and Development JSC, Construction Service and Trading JSC 68 is implementing the construction of some items of the project.

s
Project starting point at the intersection with Nguyen Trai street. Photo: Song Huu
s
s
Many works are demolished to serve the construction of Ring Road 2.5 project, Nguyen Trai - Dam Hong section (Khuong Dinh ward, Hanoi). Photo: Song Huu

Talking to Lao Dong Newspaper, a representative of the construction unit said that the contractor consortium is divided into 3 construction teams stretching across the entire route.

In which, the construction front of the final section of the route (from alley 1 Bui Xuong Trach to Dam Hong) is having the best progress.

According to the plan, in June, the contractor will complete the single-layer asphalt paving in this section and temporarily open traffic for vehicles to travel. Other items such as sidewalks and drainage systems will continue to be implemented.

For the remaining construction teams, machinery has been mobilized to the construction site. Currently, the contractor is waiting for the unit to move waste to receive clean ground.

After the site is handed over, construction work will be deployed simultaneously throughout the route, instead of having to construct in a "rolling" style as at present.

s
Most of the works within the project area have been cleared. Photo: Song Huu
s
Machinery dismantling works on the route. Photo: Song Huu
s
The demolition of the remaining works is being carried out urgently. Photo: Song Huu
s
Ring Road 2.5 Nguyen Trai - Dam Hong section reveals its shape after a series of projects were demolished. Photo: Song Huu
s
s
Many machines are gathered to serve the construction of the final section of the route (from alley 1 Bui Xuong Trach to Dam Hong). Photo: Song Huu
s
Raw materials are gathered on the route to serve the project construction. Photo: Song Huu

The project to invest in the construction of Ring Road 2.5 Nguyen Trai - Dam Hong section in Khuong Dinh ward has a length of 1.52km, a cross-section scale of 50m, and a total investment of 2,432 billion VND.

To implement the project, Khuong Dinh ward must recover 60,902m2 of land from 736 cases (16 organizations and 720 households and individuals).

According to Mr. Vo Dang Dung - Secretary of the Party Committee, Chairman of the People's Council of Khuong Dinh ward, the local government sets a goal to clear the technical route of Ring Road 2.5, Nguyen Trai - Dam Hong section on October 10, 2026.

SÓNG HỮU
RELATED NEWS

Ring Road 2.5 Nguyen Trai - Dam Hong section accelerates construction after clear site clearance

|

Hanoi - After completing site clearance, the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, is being accelerated.

Hanoi Ring Road 2.5 accelerates construction of many sections

|

Hanoi - Ring Road 2.5 project is being accelerated for site clearance and construction. Many sections of the route have been handed over land, and some basic items have been completed.

586 projects in inner Hanoi are demolished to build Ring Road 2.5

|

Hanoi - Hundreds of works within the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, have been demolished to serve construction work.

Prolonged heavy rain, National Highway 55 in Lam Dong deeply flooded for many hours

|

Lam Dong - Prolonged heavy rain caused National Highway 55 through Bao Lam 3 commune to be deeply flooded from 0.5 - 0.7m for many hours, traffic was paralyzed, and many houses were flooded.

After review, Hue proposes to recover nearly 150ha of land lent for afforestation

|

After the reflection of Lao Dong Newspaper, Hue reviewed and discovered nearly 150ha of forestry land for collectives and individuals to borrow for afforestation.

Close-up of US re-attack on Iran

|

The US Central Command on July 12 released a video showing US forces deploying a third attack on Iran.

Infiltrating an electric motorcycle modification workshop, publicly unlocking speed in just 5 seconds

|

The electric motorbike tuning market is booming, many establishments publicly admit to unlocking speed, interfering with ICs, posing a potential risk of traffic unsafety.

Ring Road 2.5 Nguyen Trai - Dam Hong section accelerates construction after clear site clearance

Hữu Vũ |

Hanoi - After completing site clearance, the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, is being accelerated.

Hanoi Ring Road 2.5 accelerates construction of many sections

Minh Hạnh |

Hanoi - Ring Road 2.5 project is being accelerated for site clearance and construction. Many sections of the route have been handed over land, and some basic items have been completed.

586 projects in inner Hanoi are demolished to build Ring Road 2.5

HỮU CHÁNH |

Hanoi - Hundreds of works within the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, have been demolished to serve construction work.