New Year's Day at the Hau River Overpass Construction Site

PHƯƠNG ANH |

Soc Trang - Workers and engineers urgently worked through the New Year holiday to meet the bridge's completion schedule.

According to a reporter's observations at the Dai Ngai bridge construction site on the morning of the first day of 2025, although it was just after 8 a.m. and the sun was already harsh, more than 200 officers and workers were still at the construction site.

While welding at the girder joints, worker Phung Vu Phuong said: “Working on this bridge, we witnessed people crossing both sides of the river having to rely on ferries and wasting time waiting. Therefore, we are aware of our responsibility for this project, so we are trying our best to complete it soon so that people can travel more easily,” said Mr. Phuong.

Cong nhan thi cong hang muc cau dan phia bo huyen Long Phu, tinh Soc Trang. Anh: Phuong Anh
Workers construct the approach bridge on the bank of Long Phu district, Soc Trang province. Photo: Phuong Anh

Mr. Bach Huy Nam - manager of the bridge construction department of the Contractor Construction Corporation No. 1 - CC1 said that although today is the New Year holiday, in the spirit of speeding up the progress, the unit still maintains the number of staff, working in 3 shifts and 4 teams. Up to now, the output has reached about 90%, ensuring the plan to close the bridge in the next few days.

Mr. Nam said that working on Tet holiday, officers and employees also receive bonuses according to regulations, so most of them are happy and work enthusiastically.

Cong nhan tich cuc thi cong de dam bao tien do de ra. Anh: Phuong Anh
Workers are working hard to ensure the set progress. Photo: Phuong Anh

A representative of Project Management Board 58 (Ministry of Transport) - the investor of Dai Ngai Bridge project - said that currently, the construction contractors have mobilized 253 personnel, 91 machines and equipment of various types; deployed 19 construction teams. The total output of the project reached 59%.

Dai Ngai 2 Bridge alone has completed 46/46 cantilever segments, installed 49/91 girder slabs, and 8/13 super-T girder spans. It is expected to be closed between January 3 and 10, 2025 and strives to basically complete by June 2025.

Cau Dai Ngai 2 co chieu dai 862m, tong cong 13 nhip, 91 dam cau (moi dam nang hon 80 tan, dai gan 40m) rieng nhip chinh dai 330m duoc thi cong dang ket cau duc hang. Anh: Phuong Anh
Dai Ngai 2 Bridge is 862m long, with a total of 13 spans and 91 bridge girders (each girder weighs more than 80 tons and is nearly 40m long). The main span, 330m long, is constructed as a cantilever structure. Photo: Phuong Anh

Dai Ngai 1 Bridge also started construction in early December 2024. Dai Ngai 1 Bridge is more than 3km long, the main bridge is 2.59km long, 21.5m wide, crossing Dinh An channel of Hau River, near the East Sea estuary, connecting Tra Cu district (Tra Vinh province) to Cu Lao Dung district (Soc Trang province). The main cable-stayed bridge has 2 A-shaped towers 110m high (from the bridge deck), main span diagram (210+450+210)m. This is the 2nd largest cable-stayed bridge in Vietnam, after Can Tho bridge and equal to Vam Cong bridge.

The Dai Ngai Bridge project has a total length of more than 15 km. The total cost is nearly 8,000 billion VND. The starting point intersects with National Highway 54, in Hung Hoa Commune (Tieu Can District, Tra Vinh Province). The end point intersects with Nam Song Hau National Highway, in Long Duc Commune (Long Phu District, Soc Trang Province). The project includes 2 main bridge works: Dai Ngai Bridge 1 and Dai Ngai Bridge 2.

The Dai Ngai Bridge project, once completed, will help open the entire National Highway 60, helping the coastal provinces of the Mekong Delta shorten the distance from Ho Chi Minh City by about 80km.

PHƯƠNG ANH
RELATED NEWS

Close-up of Hau River overpass about to close

|

Soc Trang - Dai Ngai 2 Bridge is expected to close at the end of December 2024 or early January 2025, striving to basically complete the bridge by April 2025.

Harmful short video matrix in cyberspace: Addiction algorithm

|

Many users are stuck in the middle of negative information on social networks, where algorithms continuously push harmful videos, bad content...

Hanoi suddenly turns cold, increasing bone and joint pain, paralysis of the No. 7 nerve

|

Hanoi - The weather is changing rapidly from dry to cold, causing many elderly people to have joint pain, even paralysis of the 7th cranial nerve.

Road expansion project worth over 400 billion VND in Ho Chi Minh City is still messy after 10 years

|

Ho Chi Minh City - After more than 10 years of construction, the project to expand Hoang Huu Nam street, Long Binh ward, Ho Chi Minh City is still unfinished due to site clearance issues.

Mai Thu Huyen talks about "only rich people produce movies" in Vietnam

|

Producer and director Mai Thu Huyen has expressed her views on the fact that only rich people produce films and projects are losing money.

Tornadoes blew off roofs of hundreds of houses in mountainous Quang Ngai

|

Quang Ngai - A tornado lasting about 30 minutes occurred in Ba Vi, causing 116 houses to have their roofs blown off.

Voters in Da Nang industrial zone expect delegates to supervise to the end

|

Da Nang - Voters expect National Assembly deputies to be close to the people, supervise to the end and take practical actions for social security and justice for the people.

Hiện trạng nơi xây cầu vượt sông Hồng, sông Đuống trên Vành đai 4

NHÓM PV |

Có 3 cây cầu lớn trên Vành đai 4 sẽ được đầu tư xây dựng gồm Hồng Hà và Mễ Sở qua sông Hồng, cầu Hoài Thượng qua sông Đuống.

Close-up of Hau River overpass about to close

PHƯƠNG ANH |

Soc Trang - Dai Ngai 2 Bridge is expected to close at the end of December 2024 or early January 2025, striving to basically complete the bridge by April 2025.

2 tháng nữa sẽ lắp dầm cầu vượt sông Hậu cho cầu Đại Ngãi 2

PHƯƠNG ANH |

Dự kiến tháng 11.2024, nhà thầu sẽ tiến hành lắp dầm cầu Đại Ngãi 2.