Close-up of Hau River overpass about to close

PHƯƠNG ANH |

Soc Trang - Dai Ngai 2 Bridge is expected to close at the end of December 2024 or early January 2025, striving to basically complete the bridge by April 2025.

Cau Dai Ngai 2 la cau vuot song Hau noi tu bo huyen Long Phu sang huyen Cu Lao Dung (tinh Soc Trang). Day la 1 trong 2 cay cau chinh (cau Dai Ngai 1 va Dai Ngai 2) thuoc Du an dau tu xay dung cau Dai Ngai tren Quoc lo 60 thuoc dia phan Tra Vinh va Soc Trang.
Dai Ngai 2 Bridge is a bridge over Hau River connecting Long Phu District to Cu Lao Dung District (Soc Trang Province). This is one of the two main bridges (Dai Ngai 1 and Dai Ngai 2 Bridges) of the Dai Ngai Bridge Construction Investment Project on National Highway 60 in Tra Vinh and Soc Trang.
Giam doc Ban quan ly du an cau Dai Ngai (Bo Giao thong van tai), cau Dai Ngai 2 den nay da hoan thanh 37/46 dot duc hang, dang lao lap 01/13 nhip dam super-T. Toan bo phan cau Dai Ngai 2 co tong 91 nhip dam, moi dam cau nang 87 tan, dai 38,2 met. Du kien de hoan thanh lap dat 91 nhip dam nay se tien hanh trong 3 thang lien tuc va tien do nhanh cham con phu thuoc yeu to thoi tiet.
Dai Ngai 2 Bridge is 862m long, with a total of 13 spans and 91 bridge girders (each girder weighs more than 80 tons and is nearly 40m long). The main span, 330m long, is constructed as a cantilever structure.
Cong nhan khan truong thi cong cau Dai Ngai 2
Workers urgently construct Dai Ngai 2 bridge.
Dai dien Ban Quan ly du an 85 cho biet den nay da hoan thanh 37/46 dot duc hang, lao lap duoc khoang 2 nhip dam. Du kien hop long vao cuoi thang 12.2024 va dau thang 1.2025, hoan thanh lao lap dam vao thang 2.2025 va phan dau co ban hoan thanh cau vao thang 4.2025.
The representative of Project Management Board 85 said that up to now, 37/46 cantilever segments have been completed, and about 2 girder spans have been installed. It is expected to be closed at the end of December 2024 and early January 2025, girder installation will be completed in February 2025, and the bridge will be basically completed by April 2025.
Mua kho bat dau, nang nhieu tinh hinh thi cong cau thuan loi hon.
The dry season has begun, the sunny weather makes the bridge construction process more favorable.
San luong thi cong phan cau Dai ngai 2 den nay da dat 55% ke hoach thuc hien, vuot ke hoach so voi yeu cau.
The construction output of Dai Ngai 2 bridge section has so far reached 55% of the implementation plan, exceeding the plan compared to the requirements.
PHƯƠNG ANH
TIN LIÊN QUAN

Which contractor will build the second largest cable-stayed bridge in Vietnam

|

Soc Trang - Deo Ca Group consortium won the bid to construct Dai Ngai 1 bridge worth nearly 3,900 billion VND.

First girder of 8,000 billion VND bridge installed in the West

|

Soc Trang - On the afternoon of December 1, the first girder span of Dai Ngai 2 bridge was installed.

TPBank has problems from app to LiveBank

|

TPBank's banking application has been disrupted for hours, LiveBank is not working, and transaction offices are not receiving customers.

Ho Chi Minh City departments and branches work together to remove difficulties so that the Zoo can operate well

|

HCMC - Regarding the story of land tax debt, the Director of the Zoo felt warm when receiving attention from leaders, departments and people of HCMC.

Current state of My Dinh Stadium after the concert "Anh trai say hi"

|

My Dinh Stadium is being urgently cleaned up and scaffolding dismantled to prepare for upcoming events, including the 2024 ASEAN Cup.

Queuing up in the cold rain to buy tickets for the Vietnam - Indonesia match

|

Phu Tho - At Viet Tri Stadium (Viet Tri City), many people lined up to buy tickets to watch the match between Vietnam National Team and Indonesia taking place on December 15.

There are still shortcomings in issuing retail invoices for gasoline and oil

|

The issuance of electronic invoices for each sale at gas stations has been actively implemented by many businesses, but there are still shortcomings.

Audience spent tens of millions of dong to watch Anh Trai's concert in Hung Yen

|

As December 14 approaches, the audience is ready to burn out at the Call Me by Fire concert held in Hung Yen.

Which contractor will build the second largest cable-stayed bridge in Vietnam

PHƯƠNG ANH |

Soc Trang - Deo Ca Group consortium won the bid to construct Dai Ngai 1 bridge worth nearly 3,900 billion VND.

First girder of 8,000 billion VND bridge installed in the West

PHƯƠNG ANH |

Soc Trang - On the afternoon of December 1, the first girder span of Dai Ngai 2 bridge was installed.

2 tháng nữa sẽ lắp dầm cầu vượt sông Hậu cho cầu Đại Ngãi 2

PHƯƠNG ANH |

Dự kiến tháng 11.2024, nhà thầu sẽ tiến hành lắp dầm cầu Đại Ngãi 2.