Ho Chi Minh City residents get to cross the 700 billion bridge after 8 years of waiting

MINH QUÂN |

HCMC - On the morning of October 2, Nam Ly Bridge on Do Xuan Hop Street (Thu Duc City) was officially opened to traffic after more than 8 years of waiting.

The project with a total investment of more than 730 billion VND has attracted great attention from the people when it was finally completed after many delays.

At the opening ceremony organized by the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board), the bridge was considered one of the key traffic projects of Ho Chi Minh City.

With a length of 450m, Nam Ly Bridge is designed with two branches 20m wide, with an approach road more than 300m long and 30 to 37m wide.

Cau Nam Ly thong xe sau 8 nam khoi cong. Anh: Minh Quan
Nam Ly Bridge opens to traffic after 8 years of construction. Photo: Minh Quan

This project started in 2016, but after nearly 3 years of construction, when only 40% of the volume was completed, the project had to be temporarily suspended due to problems in site clearance.

After many efforts, by March 2023, when Thu Duc City basically completed compensation and site handover, the project was able to continue implementation.

Immediately after receiving the site, the Traffic Department and construction units promptly started working, from gathering materials and equipment to organizing the construction.

Thanks to the synchronous coordination, the main bridge and the approach roads at both ends of the bridge were completed and put into operation on time, serving the travel needs of the people.

The remainder of the project, including residential roads and remaining finishing work, is expected to be completed by December 2024.

Sau khi thong xe cau, don vi thi cong se dong duong hien huu ben hong de thi cong duong gom dan sinh va cac hang muc phu tro.  Anh: Minh Quan
After the bridge is opened to traffic, the construction unit will close the existing side road to construct the residential access road and auxiliary items. Photo: Minh Quan

Nam Ly Bridge is not only significant in terms of traffic connection but also plays an important role in the socio-economic development of Thu Duc City and Ho Chi Minh City.

By road, the bridge connects Do Xuan Hop Street, a main route running through An Phu, Binh Trung Tay, Phuoc Long A, Phuoc Long B and Phuoc Binh wards, facilitating traffic between neighboring residential areas and connecting directly with Vo Nguyen Giap Street and Ho Chi Minh City - Long Thanh - Dau Giay Expressway.

Regarding waterways, Rach Chiec - where Nam Ly Bridge crosses - has been planned as a level 4 river, qualified to meet the demand for waterway traffic after the waterway from Saigon River to Dong Nai River is opened. This further highlights the role of Nam Ly Bridge in supporting the transport of goods not only by road but also by waterway, contributing to promoting trade and the regional economy.

Xe chay qua cau Nam Ly.  Anh: Minh Quan
Cars running over Nam Ly bridge. Photo: Minh Quan

Along with the opening of Nam Ly Bridge, the Do Xuan Hop Street expansion project has also restarted after a long period of stagnation. The upgraded section is 1.8 km long, from Nam Ly Bridge to Nguyen Duy Trinh Street, with a total investment of more than 838 billion VND. After being expanded to 6 lanes, the road will be 27 to 30 m wide, expected to be completed in 2025.

When completed, together with Nam Ly Bridge, this route will enhance traffic connection from Ho Chi Minh City - Long Thanh - Dau Giay Expressway to Nguyen Duy Trinh Street.

In addition to the above project, Thu Duc City is speeding up the construction of the nearly 700 billion VND Tang Long Bridge on La Xuan Oai Street. It is expected to be completed by December 2024, opening the left branch of the bridge to traffic. After that, the old bridge will be dismantled and the right branch of the bridge will be constructed. By December 2025, the entire project will be completed.

MINH QUÂN
RELATED NEWS

Water rises rapidly at night, many houses along Ba Thon canal in Ho Chi Minh City are flooded

|

HCMC - On the evening of November 10, the water level of Ba Thon canal, An Phu Dong ward suddenly rose rapidly, overflowing into many houses along TL37 road, causing local flooding.

Landslides threaten residential areas, many households have to evacuate urgently

|

Thai Nguyen - Prolonged heavy rain caused tens of thousands of cubic meters of soil and rock to slide down to the residential area of Cho Ra commune, forcing the authorities to urgently evacuate 5 households.

Delegate Nguyen Thien Nhan: Support 9-13 million VND is only equal to 1-1.5% of the cost of raising a child

|

Delegate Nguyen Thien Nhan said that the support level of 9 - 13 million VND is only equal to 1-1.5% of the cost of raising a child, not enough to firmly maintain the replacement fertility rate.

"Doctor" ChatGPT suggests, prescription drugs are easy to buy

|

Many people prescribe themselves or ask ChatGPT to prescribe, while pharmacies freely sell prescription drugs without needing to prescribe a doctor. This poses a potential risk to public health.

Thailand suspends peace agreement with Cambodia, temporarily suspends return of prisoners

|

On November 10, the Thai Prime Minister issued an order to immediately suspend the peace agreement with Cambodia and stop the return of prisoners.

Hanoi FC shares Nam Dinh points in round 11 of V.League

|

On the afternoon of November 10, Nam Dinh Club and Hanoi FC drew 1-1 in round 11 of LPBank V.League 2025-2026.

People in the mountainous commune of Hue City are restless because the landslide is about to "swallow" their entire house

|

HUE - Landslides have torn apart the houses of a household and threatened the safety of many households living next to Thac Trinh (Khe Tre commune).

Nghe An Secretary becomes Deputy Secretary of Hanoi Party Committee

|

Mr. Nguyen Duc Trung, Secretary of Nghe An Provincial Party Committee, was assigned by the Politburo to hold the position of Deputy Secretary of Hanoi Party Committee for the 2025-2030 term.

TPHCM chốt thời điểm hoàn thành 2 cầu quan trọng ở Thủ Đức

MINH QUÂN |

TPHCM – Cầu Nam Lý thông xe kỹ thuật trước ngày 15.9 và cầu Tăng Long thông xe nhánh cầu bên trái trong tháng 12 năm nay.

Người dân dỡ nhà, bàn giao mặt bằng, mong cầu Nam Lý về đích đúng tiến độ

HỮU CHÁNH |

TP Hồ Chí Minh - Người dân sinh sống trên đường Đỗ Xuân Hợp tháo dỡ nhà, bàn giao mặt bằng phục vụ dự án cầu Nam Lý và mong công trình về đích đúng tiến độ vào năm 2024.

Cầu Nam Lý gần 1.000 tỉ đồng gấp rút thi công sau 4 năm tạm dừng

Anh Tú |

TP Hồ Chí Minh - Dự án đầu tư xây dựng cầu Nam Lý (thay thế đập Rạch Chiếc tại TP Thủ Đức) sau 4 năm dừng thi công vì vướng mặt bằng, đã được tái khởi động, dự kiến sẽ hoàn thành trong 14 tháng tới.