Reasons for the trillion-dong road project in Thai Nguyen being flooded many times

Lam Thanh |

Thai Nguyen - Compensation, site clearance, and resettlement support at the extended Bac Son road project are facing many difficulties.

The extended Bac Son road project is a vital route connecting the center of Thai Nguyen province and the Nui Coc lake area. The project is 9.5km long, worth more than VND 2,100 billion under the PPP - BT Contract form invested by Xuan Truong Construction Enterprise.

The route started construction in July 2018 and is expected to be completed in December 2019. However, after many requests for an extension, the project has not been able to reach the finish line as planned.

Du an duong Bac Son keo dai dang duoc day nhanh thi cong. Anh: Lam Thanh
The extended Bac Son road project is being accelerated. Photo: Lam Thanh

Currently, contractors are focusing on construction, striving to complete the project in 2025. Compared to the original design, the contractor proposed to adjust some items to suit the reality such as: replacing Terrazzo tiles with Rheocore cast iron bricks, adjusting the type of trees and adding a layer of asphalt concrete to the cement concrete road surface.

In addition to difficulties due to construction conditions and rainy weather, site clearance is also affecting the progress of the project.

Report of the Branch of the Land Fund Development Center Region I, the compensation, support and resettlement work of the Bac Son Road Project is still facing many difficulties.

Some households have had compensation plans but have not been paid due to lack of funding. While some households have received money but have not yet handed over the site.

On the section from Km0+00 to Km3+500, the service road area in Phan Dinh Phung ward has 9 households affected. Up to now, there are 2 households that have not yet handed over the site because the project has a complex structure, and need a demolition plan to ensure safety. 7 households have approved compensation plans with a total amount of 3.62 billion VND, but there is no funding for payment.

Tuyen duong khi hoan thanh se ket noi trung tam tinh Thai Nguyen va khu vuc ho Nui Coc. Anh: Lam Thanh
When completed, the route will connect the center of Thai Nguyen province and Nui Coc lake area. Photo: Lam Thanh

In Quyet Thang ward, 8 households have compensation plans and are submitting for appraisal with a total cost of about 5.1 billion VND. However, the progress is still slow due to not being funded.

The section from Km3+500 to Km9+500, through Dai Phuc commune, has 6 households waiting for compensation approval. The total estimated cost is about 4.2 billion VND. At the same time, there are 3 households with legal documents and resettlement needs.

Faced with the above situation, Vice Chairman of Thai Nguyen Provincial People's Committee Nguyen Thi Loan requested Phan Dinh Phung Ward to establish a working group to dismantle and clear encroachment and expansion points in the area that has been compensated and cleared.

At the same time, the site will be arranged for a service road on both sides of the overpass, to be completed before August 29.

Quyet Thang ward and Dai Phuc commune need to develop a plan to protect the scene in the cleared sections. Completing compensation and site clearance soon.

The Department of Construction will preside over the plan to dismantle works subject to clearance. Reviewing the road design, especially the sections proposed by the investor to be reclaimed to build a protective embankment.

Lam Thanh
RELATED NEWS

Can Tho approves 16.43 billion VND project to support climate change mitigation

|

Can Tho - Can Tho approved a project worth more than VND 16.43 billion sponsored by Canada and CARE, to minimize the impact of climate change.

Landmarks for the implementation of the VND9,400 billion Phan Thiet coastal road and overpass project

|

Lam Dong - The coastal road and river overpass project is expected to complete the planning in 2025, and prepare a pre-feasibility report in early 2026.

Time to review and re- inventory public assets according to the new apparatus

|

The Prime Minister requested to conduct a review and re- inventory of public assets at 0:00 on January 1, 2026 according to the new organizational model.

Thailand - Cambodia border tense again ahead of negotiations

|

The Thai - Cambodian border has been tense in recent days after accusations of soldiers from both sides crossing the border and violating the ceasefire agreement appeared.

Verifying the incident of the principal singing karaoke when storm No. 5 made landfall

|

Thanh Hoa - Regarding the reflection on social networks about a principal singing karaoke when storm No. 5 was coming, the local government has stepped in to verify.

Opening of the Press Center for the 80th Anniversary of National Day, operating from August 26

|

The Press Center to celebrate the 80th Anniversary of the National Day of the Socialist Republic of Vietnam was officially opened and put into operation.

Bắc Ninh rà soát các thông tin liên quan dự án Ecohome Sông Thương

Trần Tuấn |

Bắc Ninh - Chủ tịch UBND tỉnh yêu cầu rà soát các thông tin liên quan dự án Ecohome Sông Thương, xử lý nghiêm đối với sai phạm của môi giới bất động sản (nếu có).

Can Tho approves 16.43 billion VND project to support climate change mitigation

PHƯƠNG ANH |

Can Tho - Can Tho approved a project worth more than VND 16.43 billion sponsored by Canada and CARE, to minimize the impact of climate change.

Landmarks for the implementation of the VND9,400 billion Phan Thiet coastal road and overpass project

Duy Tuấn |

Lam Dong - The coastal road and river overpass project is expected to complete the planning in 2025, and prepare a pre-feasibility report in early 2026.