Terminal T3 is about to be completed, reducing the load at Tan Son Nhat airport

MINH QUÂN |

HCMC - The T3 terminal project at Tan Son Nhat airport has reached about 83% of the total volume, expected to be completed on April 30, 2025, 2 months earlier than the original plan.

On December 27, Vietnam Airports Corporation (ACV) and contractors signed a competition agreement to complete the project within 120 days and nights, with the goal of exceeding the schedule to put the project into operation on April 30, 2025, 2 months earlier than the original plan.

According to Mr. Nguyen Tien Viet - Deputy General Director in charge of ACV, the T3 Terminal project has achieved many important advances in terms of progress, construction quality and ensuring labor safety.

Currently, the rough construction of the project has been completed. The architectural finishing, interior finishing and equipment installation items are being accelerated. The entire project's electrical system has been closed, the expanded aircraft parking area has been exploited, and the interior finishing works are in the final stage.

“I request the Project Management Board and contractors to focus all resources and synchronously deploy solutions to speed up the equipment installation progress, ensuring that the operation and acceptance work is carried out safely, with quality and according to requirements. We must be determined to complete the project and put it into operation on April 30, 2025 as committed,” said Mr. Viet.

Cong nhan lap kinh nha ga T3.  Anh: Minh Quan
Workers install glass at T3 terminal. Photo: Minh Quan
Ga T3 dang duoc hoan thien kien truc ben trong.  Anh: Minh Quan
T3 Station is completing its interior architecture. Photo: Minh Quan

The T3 Terminal Project has a total investment of VND10,990 billion, including 4 main items: passenger terminal, multi-storey car park integrated with non-aviation services, overpass system in front of the terminal and aircraft parking lot. The capital for the project comes from ACV's equity and commercial loans.

Ga T3 se hoan thanh dip 30.4.2025.  Anh: Minh Quan
T3 Station will be completed on April 30, 2025. Photo: Minh Quan

According to Mr. Le Khac Hong - Head of the Project Management Board, the biggest challenge of the 120-day competition is the fact that there are only about 90 days left to complete the entire project, including the Lunar New Year holiday, making it difficult to mobilize enough personnel and materials.

"Completing the project on schedule requires high determination from the contractors' leaders, flexibility in solving financial, human resources and material difficulties. At the same time, the construction management board must closely monitor and promptly handle any problems arising during the construction process," Mr. Hong emphasized.

Thi cong cau vuot dan len nha ga T3.  Anh: Minh Quan
Construction of an overpass leading to Terminal T3. Photo: Minh Quan

When completed, T3 passenger terminal will be the largest domestic passenger terminal in the country with 20 million people, increasing the total capacity of Tan Son Nhat airport to 50 million passengers per year, along with the existing T1 and T2 terminals.

The architecture of T3 terminal is inspired by the traditional ao dai. The terminal is designed into two separate departure and arrival sections, with 90 check-in counters, 20 automatic bagdrop counters, 42 check-in kiosks, 27 boarding gates, 6 departure baggage handling islands and 10 arrival baggage return islands...

MINH QUÂN
RELATED NEWS

Appearance of Tan Son Nhat T3 terminal after nearly 2 years of construction

|

HCMC - After nearly two years of construction, Tan Son Nhat Airport's T3 terminal has been revealed with important items such as the roof, basements and above-ground floors, commercial area, and overpass.

Organizing a memorial service for 504 civilians massacred in Son My, Quang Ngai

|

Quang Ngai - Hundreds of people attended the memorial ceremony for the 58th anniversary of the Son My massacre (March 16, 1968 - March 16, 2026) that killed 504 innocent civilians.

Dong Nai approves component project of ring road connecting Ho Chi Minh City worth over 10,000 billion VND

|

Dong Nai - Ho Chi Minh City Ring Road 4 through the province is more than 46km long and is divided into 2 component projects.

Scene of a house fire in Ho Chi Minh City, rescuing 5 people trapped

|

Ho Chi Minh City - On March 16, the Fire and Rescue Team of Area 1 promptly rescued 5 people trapped in a fire that occurred at a resident's house in the central area.

Fire in Ecohome 1 apartment building in Hanoi at dawn

|

Hanoi - Functional forces have just promptly extinguished a fire that occurred at Ecohome 1 apartment building, Dong Ngac ward.

Fans stay up from 1 am at My Dinh stadium waiting to watch the Anh Trai Say Hi concert

|

Many young people were present very early at My Dinh stadium from the early morning of March 16th to wait for the "Anh Trai Say Hi" concert.

Stock market continues to bottom out

|

The stock market continues to face many risks from oil price fluctuations and global macroeconomic factors.

Poland faces risk of leaving the EU, Prime Minister Tusk warns

|

Prime Minister Donald Tusk warned that the possibility of Poland leaving the European Union EU (Polexit) is no longer a distant scenario.

Appearance of Tan Son Nhat T3 terminal after nearly 2 years of construction

MINH QUÂN |

HCMC - After nearly two years of construction, Tan Son Nhat Airport's T3 terminal has been revealed with important items such as the roof, basements and above-ground floors, commercial area, and overpass.

Hoàn thành lắp mái thép nhà ga T3 Tân Sơn Nhất sớm 2 tháng

MINH QUÂN |

TPHCM - Công tác lắp đặt mái thép của nhà ga T3 sân bay Tân Sơn Nhất đã hoàn thành sớm hơn dự kiến 2 tháng, giúp đẩy nhanh tiến độ dự án.

Đưa nhà ga T3 sân bay Tân Sơn Nhất khai thác dịp 30.4.2025

MINH QUÂN |

TPHCM - Tập trung nhân lực, thi công 3 ca 4 kíp, làm việc xuyên lễ, tết đưa ga T3 Tân Sơn Nhất vào khai thác dịp 30.4.2025.