Terminal T3 is about to be completed, reducing the load at Tan Son Nhat airport

MINH QUÂN |

HCMC - The T3 terminal project at Tan Son Nhat airport has reached about 83% of the total volume, expected to be completed on April 30, 2025, 2 months earlier than the original plan.

On December 27, Vietnam Airports Corporation (ACV) and contractors signed a competition agreement to complete the project within 120 days and nights, with the goal of exceeding the schedule to put the project into operation on April 30, 2025, 2 months earlier than the original plan.

According to Mr. Nguyen Tien Viet - Deputy General Director in charge of ACV, the T3 Terminal project has achieved many important advances in terms of progress, construction quality and ensuring labor safety.

Currently, the rough construction of the project has been completed. The architectural finishing, interior finishing and equipment installation items are being accelerated. The entire project's electrical system has been closed, the expanded aircraft parking area has been exploited, and the interior finishing works are in the final stage.

“I request the Project Management Board and contractors to focus all resources and synchronously deploy solutions to speed up the equipment installation progress, ensuring that the operation and acceptance work is carried out safely, with quality and according to requirements. We must be determined to complete the project and put it into operation on April 30, 2025 as committed,” said Mr. Viet.

Cong nhan lap kinh nha ga T3.  Anh: Minh Quan
Workers install glass at T3 terminal. Photo: Minh Quan
Ga T3 dang duoc hoan thien kien truc ben trong.  Anh: Minh Quan
T3 Station is completing its interior architecture. Photo: Minh Quan

The T3 Terminal Project has a total investment of VND10,990 billion, including 4 main items: passenger terminal, multi-storey car park integrated with non-aviation services, overpass system in front of the terminal and aircraft parking lot. The capital for the project comes from ACV's equity and commercial loans.

Ga T3 se hoan thanh dip 30.4.2025.  Anh: Minh Quan
T3 Station will be completed on April 30, 2025. Photo: Minh Quan

According to Mr. Le Khac Hong - Head of the Project Management Board, the biggest challenge of the 120-day competition is the fact that there are only about 90 days left to complete the entire project, including the Lunar New Year holiday, making it difficult to mobilize enough personnel and materials.

"Completing the project on schedule requires high determination from the contractors' leaders, flexibility in solving financial, human resources and material difficulties. At the same time, the construction management board must closely monitor and promptly handle any problems arising during the construction process," Mr. Hong emphasized.

Thi cong cau vuot dan len nha ga T3.  Anh: Minh Quan
Construction of an overpass leading to Terminal T3. Photo: Minh Quan

When completed, T3 passenger terminal will be the largest domestic passenger terminal in the country with 20 million people, increasing the total capacity of Tan Son Nhat airport to 50 million passengers per year, along with the existing T1 and T2 terminals.

The architecture of T3 terminal is inspired by the traditional ao dai. The terminal is designed into two separate departure and arrival sections, with 90 check-in counters, 20 automatic bagdrop counters, 42 check-in kiosks, 27 boarding gates, 6 departure baggage handling islands and 10 arrival baggage return islands...

MINH QUÂN
RELATED NEWS

Appearance of Tan Son Nhat T3 terminal after nearly 2 years of construction

|

HCMC - After nearly two years of construction, Tan Son Nhat Airport's T3 terminal has been revealed with important items such as the roof, basements and above-ground floors, commercial area, and overpass.

The truck license plate was obscured, the driver blamed the manufacturer

|

Hanoi - Many trucks were stopped for inspection by the traffic police due to their license plates being obscured. The driver gave many reasons to justify.

Miss Universe President Prosecuted and crisis of 74-Year-Old pageant

|

Miss Universe 2025 ended in Bangkok (Thailand) with the crown belonging to the representative of Mexico Fatima Bosch, but the aftermath was a series of scandals surrounding it.

Thang Long Boulevard service road is deteriorating for a long time, people live miserably in the dust and flooding

|

Thang Long Boulevard service road is heavily degraded and is constantly dusty, causing people around the area to face many risks of insecurity.

AI sings Trinh's music, copyright issues are a headache

|

AI sings Trinh's music, AI covers a series of famous songs that have reached millions of views, but the author is "empty-handed", raising copyright issues.

3 large reservoirs in Ho Chi Minh City simultaneously release floodwaters

|

HCMC - Faced with complicated weather developments and rising water levels, 3 large reservoirs continue to release floodwaters to ensure the safety of the project.

Union Newsletter: Deadline for evaluating and classifying cadres and civil servants this year according to Decree 90

|

Abundant orders at the end of the year, workers are excited because of increased income; Time to evaluate and classify quality in 2025 for cadres, civil servants, public employees...

casualties in the horrific apartment fire in Hong Kong (China) increase rapidly

|

At least 44 people died, 279 are missing in an apartment fire in Hong Kong (China), 3 suspects were arrested overnight.

Appearance of Tan Son Nhat T3 terminal after nearly 2 years of construction

MINH QUÂN |

HCMC - After nearly two years of construction, Tan Son Nhat Airport's T3 terminal has been revealed with important items such as the roof, basements and above-ground floors, commercial area, and overpass.

Hoàn thành lắp mái thép nhà ga T3 Tân Sơn Nhất sớm 2 tháng

MINH QUÂN |

TPHCM - Công tác lắp đặt mái thép của nhà ga T3 sân bay Tân Sơn Nhất đã hoàn thành sớm hơn dự kiến 2 tháng, giúp đẩy nhanh tiến độ dự án.

Đưa nhà ga T3 sân bay Tân Sơn Nhất khai thác dịp 30.4.2025

MINH QUÂN |

TPHCM - Tập trung nhân lực, thi công 3 ca 4 kíp, làm việc xuyên lễ, tết đưa ga T3 Tân Sơn Nhất vào khai thác dịp 30.4.2025.