Many traffic projects in Hanoi are speeding towards the finish line

SÓNG HỮU |

Hanoi - Ring Road 1 project, Hoang Cau - Voi Phuc section, many sections of Ring Road 2.5, and the expansion of alley 381 Nguyen Khang are expected to be completed in 2026.

The investment project to build Ring Road 1, Hoang Cau - Voi Phuc section has a total investment of 7,210 billion VND from the city budget.

The road is about 2.2km long, with a cross-section of 50m, starting point at the Cat Linh - La Thanh - Yen Lang intersection (Hoang Cau), ending point at the Voi Phuc intersection.

To date, site clearance work is basically completed.

The Hanoi Civil Works Construction Investment Project Management Board is coordinating with the People's Committees of O Cho Dua, Giang Vo, Lang wards to continue to handle existing problems, and at the same time urge contractors to organize continuous construction, including on holidays, to ensure progress.

Dự án đường Vành đai 1 hồi đầu tháng 6.2026. Ảnh: Sóng Hữu
Ring Road 1 project in early June 2026. Photo: Song Huu

According to the expected progress, the Hanoi Civil Works Construction Investment Project Management Board strives to complete the technical opening of the road section on September 2, 2026; 2 overpasses at Lang Ha and Nguyen Chi Thanh intersections will be completed before December 31, 2026.

According to Vice Chairman of Hanoi City People's Committee Do Anh Tuan, the opening of Ring Road 1 has both created a closed ring road and recognized the efforts of the investor and local authorities, and at the same time set a management model for implementing key investment projects being implemented in the city.

Recorded at the Ring Road 2.5 project section passing through Cau Giay, Yen Hoa, Thanh Xuan, Khuong Dinh wards, the construction unit is also urgently deploying tasks at the construction site.

In which, the section of Dich Vong - Duong Dinh Nghe New Urban Area is about 0.71km long, 50m wide; the Vu Pham Ham - Tran Duy Hung section is about 0.6km long, 40m wide; the Nguy Nhu Kon Tum - Nguyen Trai section is about 0.95km long, 40m wide; the Nguyen Trai - Dam Hong section is about 1.52km long, 40m wide.

s
Machinery and workers working at the Ring Road 2.5 project construction site. Photo: Song Huu

The above route sections are expected to be completed in 2026 with the aim of completing Ring Road 2.5 to handle traffic bottlenecks and emergencies; completing the transportation network, attracting investment, contributing to creating the face of the city along the route in particular and of the whole city in general, contributing to the socio-economic development of the Capital.

In Cau Giay ward, the project to expand alley 381 Nguyen Khang street with a length of 340m has restarted after many years of stagnation due to site clearance work.

To date, all 103 organizations, households, and individuals have agreed to hand over land for the project with a total land area of 7,328.2m2.

s
A series of works within the project to expand alley 381 Nguyen Khang have been demolished. Photo: Song Huu

The demolition and handover of the site have basically been completed. The project is expected to be started in September, completing the entire project in 2026.

SÓNG HỮU
RELATED NEWS

Rain and floods surround, more than 1,600 households in Lang Son must be urgently evacuated

|

Lang Son - Rain and floods caused by storm No. 4 killed one person, more than 2,600 houses were affected and over 1,600 households had to be relocated.

Strong earthquake causes shooking in Tokyo, at least 7 people injured in Japan

|

A 5.9 magnitude earthquake occurred in Ibaraki Prefecture, northeast of Tokyo (Japan), injuring at least 7 people and temporarily disrupting railway operations.

National highway connecting Cao Bang - Lang Son jammed at two points, vehicles have to take detours

|

Lang Son - Prolonged rain and floods caused National Highway 4A to be blocked in two sections passing through Na Sam and That Khe communes.

Hai Phong puts 5 traffic projects under special monitoring and supervision

|

Hai Phong - Secretary of the City Party Committee Le Ngoc Chau has just requested to put 5 key traffic projects under special monitoring and supervision, and weekly reviews.

Sea of people brave the rain to "go wild" to celebrate Vietnam's convincing victory over Thailand

|

Hanoi - After the victory in the first leg of the ASEAN Cup 2026 final, a large number of Vietnamese fans took to the streets, carrying red flags with yellow stars and joining the celebration atmosphere.

Bụi mù mịt từ hoạt động vận chuyển đất thải dự án đường Vành đai 2,5

SÓNG HỮU |

Hà Nội - Nhà thầu dự án đường Vành đai 2,5 mượn đường để phục vụ thi công nhưng không thực hiện đầy đủ biện pháp bảo đảm vệ sinh môi trường.

Mượn đường để thi công dự án Vành đai 2,5 nhưng gây ô nhiễm, ảnh hưởng giao thông

SÓNG HỮU |

Hà Nội - Hoạt động vận chuyển đất thải từ dự án đường Vành đai 2,5 đoạn Nguyễn Trãi - Đầm Hồng gây ô nhiễm, tiềm ẩn nguy cơ tai nạn giao thông.

Đủ kiểu "sống chung với bụi" quanh khu vực công trường Vành đai 2,5 Hà Nội

Dương Anh - Minh Châu |

Hà Nội - Sống gần khu vực vực thi công đường Vành đai 2,5, nhiều người dân phải tìm đủ cách để tránh bụi.