At the parallel road projects of Ring Road 5, the total implemented area is about 415.7ha, but so far only nearly 300ha has been cleared and handed over. Some resettlement areas of the project are being implemented slowly, especially the 2 resettlement areas of Cong Ly and Duc Ly in Nam Xang commune. In addition, the relocation of electricity systems and technical infrastructure works has not yet met the progress requirements.
Currently, the parallel road projects of Ring Road 5 have only reached about 50% of the construction volume according to the contract value. The total capital allocated for 4 projects is 2,777 billion VND, of which the disbursed value is only about 1,723 billion VND.
Similarly, at the investment project to build an overpass on T4 road at the intersection with route T1, DT. 495B. Up to now, only about 12/22.8ha of land has been handed over. The construction value of the project reached more than 250/742 billion VND. Meanwhile, the capital plan for 2026 has only disbursed more than 129/250 billion VND.
Mr. Dang Thai Son - Deputy Director of Ninh Binh Provincial Department of Finance - said that difficulties in compensation, site clearance, lack of filling material sources, fluctuations in raw material prices and adjustments to the scale and design of some projects are the reasons affecting the disbursement progress of public investment capital in 2026.
Ninh Binh province currently has more than 50 public investment projects facing difficulties and obstacles. Among them, more than 30 projects have been handled in forms such as completing finalization, determining technical stops or continuing to allocate capital for completion; and 20 projects are being focused on removing obstacles in 2026.
To remove difficulties, Ninh Binh province is promoting decentralization and authorization to grassroots authorities. The Provincial People's Committee has implemented 7 rounds of authorizing 13 communes and wards to perform tasks and authority of the level deciding on investment policies for 101 public investment projects.
Chairman of Ninh Binh Provincial People's Committee Nguyen Thanh Binh requested investors to regularly urge contractors and accelerate construction. Areas that already have land must organize construction of many items simultaneously, not letting machinery, equipment and manpower wait. For projects that are prolonged and low-efficiency, localities must review to reduce scale, determine technical stopping points or propose appropriate handling plans.
