Many difficulties and obstacles in disbursing public investment capital in Ninh Binh

NGUYỄN TRƯỜNG |

Difficulties and obstacles in site clearance (GPMB), lack of filling material sources, investment procedures and implementation capacity at the grassroots level... have affected the disbursement progress of public investment capital in Ninh Binh.

At the parallel road projects of Ring Road 5, the total implemented area is about 415.7ha, but so far only nearly 300ha has been cleared and handed over. Some resettlement areas of the project are being implemented slowly, especially the 2 resettlement areas of Cong Ly and Duc Ly in Nam Xang commune. In addition, the relocation of electricity systems and technical infrastructure works has not yet met the progress requirements.

Currently, the parallel road projects of Ring Road 5 have only reached about 50% of the construction volume according to the contract value. The total capital allocated for 4 projects is 2,777 billion VND, of which the disbursed value is only about 1,723 billion VND.

Similarly, at the investment project to build an overpass on T4 road at the intersection with route T1, DT. 495B. Up to now, only about 12/22.8ha of land has been handed over. The construction value of the project reached more than 250/742 billion VND. Meanwhile, the capital plan for 2026 has only disbursed more than 129/250 billion VND.

Mr. Dang Thai Son - Deputy Director of Ninh Binh Provincial Department of Finance - said that difficulties in compensation, site clearance, lack of filling material sources, fluctuations in raw material prices and adjustments to the scale and design of some projects are the reasons affecting the disbursement progress of public investment capital in 2026.

Ninh Binh province currently has more than 50 public investment projects facing difficulties and obstacles. Among them, more than 30 projects have been handled in forms such as completing finalization, determining technical stops or continuing to allocate capital for completion; and 20 projects are being focused on removing obstacles in 2026.

To remove difficulties, Ninh Binh province is promoting decentralization and authorization to grassroots authorities. The Provincial People's Committee has implemented 7 rounds of authorizing 13 communes and wards to perform tasks and authority of the level deciding on investment policies for 101 public investment projects.

Chairman of Ninh Binh Provincial People's Committee Nguyen Thanh Binh requested investors to regularly urge contractors and accelerate construction. Areas that already have land must organize construction of many items simultaneously, not letting machinery, equipment and manpower wait. For projects that are prolonged and low-efficiency, localities must review to reduce scale, determine technical stopping points or propose appropriate handling plans.

NGUYỄN TRƯỜNG
RELATED NEWS

Khanh Hoa needs to disburse 3,500 billion VND of public investment capital in September

|

Khanh Hoa - Site clearance continues to be the biggest bottleneck of the locality to achieve the target of disbursing 75% of the public investment capital plan by the end of the third quarter of 2026.

Da Nang disburses more than 9,200 billion VND of public investment capital in 8 months

|

Da Nang - In the first 8 months of 2026, Da Nang City disbursed more than 9,200 billion VND of public investment capital.

Accelerate disbursement, improve efficiency of using public investment capital

|

The Ministry of Finance believes that, along with accelerating the disbursement of public investment capital, it is necessary to improve investment efficiency, avoid prolonging progress and increasing costs.

Police break down to rescue 4 people trapped in a burning house at dawn

|

Da Nang - House fire at dawn, 4 people trapped were promptly broken down and rescued by the Fire and Rescue Police.

Exciting opening day, students eagerly enter the new school year

|

On the morning of September 5th, millions of students across the country together opened the school year, entering the school year with many good expectations.

Collision with train in Ho Chi Minh City, one person died

|

One person died after a collision with a train on the North-South railway line, passing through Hiep Binh ward, Ho Chi Minh City on the morning of September 5.

Functional agencies verify reports of grease in Bach Hoa Xanh showing signs of mold

|

Khanh Hoa - Functional agencies have inspected and verified reflections of grease powder showing signs of mold at Bach Hoa Xanh but there is not enough basis to determine violations.

Khanh Hoa needs to disburse 3,500 billion VND of public investment capital in September

Phương Linh |

Khanh Hoa - Site clearance continues to be the biggest bottleneck of the locality to achieve the target of disbursing 75% of the public investment capital plan by the end of the third quarter of 2026.

Da Nang disburses more than 9,200 billion VND of public investment capital in 8 months

Nguyễn Linh |

Da Nang - In the first 8 months of 2026, Da Nang City disbursed more than 9,200 billion VND of public investment capital.

Accelerate disbursement, improve efficiency of using public investment capital

Lục Giang |

The Ministry of Finance believes that, along with accelerating the disbursement of public investment capital, it is necessary to improve investment efficiency, avoid prolonging progress and increasing costs.