The first 4-storey intersection in Ho Chi Minh City still has 72 land clearance problems

MINH QUÂN |

HCMC - My Thuy intersection has a scale of 4 floors, the first in the city to be implemented since 2016 but has not yet been completed due to land clearance problems, with 72 households not yet handed over.

Started in 2016, the My Thuy intersection project (Thu Duc City) is divided into three investment phases. However, many items have been delayed for a long time due to problems in site clearance.

The project has a total investment of more than VND 3,400 billion, including two component projects: Construction and installation (VND 1,826 billion) and compensation and site clearance (VND 1,623 billion).

Recently, phase 3 has been started with an overpass on Ring Road 2 ( Vo Chi Cong Street) and the right branch of Ky Ha 3 Bridge.

Ho Chi Minh City aims to complete the entire My Thuy intersection project by April 30 next year, with the condition that the site clearance work in Thu Duc City must be completed in April this year.

Giai phong mat bang y ach lam anh huong tien do thi cong nut giao My Thuy. Ảnh: Anh Tu
Slow site clearance affects the construction progress of My Thuy intersection. Photo: Anh Tu

According to Vice Chairman of Thu Duc City People's Committee Mai Huu Quyet, the total land area to be reclaimed for the project is 166,277 m2, of which more than 112,644 m2 is traffic land and canals. The project affects 195 households.

To date, Thu Duc City has approved compensation and resettlement support plans for 182 cases, of which 169 households have received money with a total of more than 1.2 billion VND.

Currently, the site of 123 records has been handed over, reaching 63.1% of the total area to be recovered.

However, there are still 72 records that have not been handed over the site, accounting for nearly 37% of the total amount to be cleared. The main causes are land disputes, border overlaps, complaints, administrative litigations or waiting for resettlement land arrangement.

Nhieu can nha chua ban giao thi cong nut giao My Thuy.  Anh: Anh Tu
Many houses have not been handed over for construction at My Thuy intersection. Photo: Anh Tu

Mr. Mai Huu Quyet said that Thu Duc City is focusing on solving these problems and aiming to complete compensation and site clearance in the second quarter of this year to ensure the overall progress of the project.

Previously, My Thuy intersection was the intersection between Nguyen Thi Dinh Street - the main axis in and out of Cat Lai Port and Ring Road 2 ( Vo Chi Cong Street).

This is an area with a very large volume of freight vehicles, while the transportation system is only organized in a uniform manner, leading to frequent traffic congestion and accidents.

Phoi canh nut giao My Thuy quy mo 4 tang khi hoan thanh. Anh: Ban Giao thong TPHCM
Perspective of My Thuy intersection with a scale of 4 floors when completed. Photo: Ho Chi Minh City Traffic Department.

In order to solve this problem, in 2016, the My Thuy intersection project with a scale of 4 floors was approved by the Ho Chi Minh City People's Council for investment.

After 9 years of implementation, many items have been completed and put into operation, including: 4-lane overpass on Vo Chi Cong street across the intersection, left underpass from Vo Chi Cong street to Cat Lai, My Thuy 3 bridge, Ky Ha 3 bridge (left branch) and the underpass system.

These items have contributed to significantly improving the traffic situation in the area. However, the project still has some items under implementation and is facing difficulties due to the completion of site clearance.

MINH QUÂN
RELATED NEWS

HCMC will enforce 4 land plots for the construction of roads worth VND41,387 billion

|

Ho Chi Minh City - Thu Duc City plans to enforce land acquisition for 4 cases that have not yet handed over the site for the construction of the Ring Road 3 project with a total capital of more than VND 41,387 billion.

The largest intersection in Ho Chi Minh City is about to open the first underpass

|

HCMC - The underpass from the HCMC - Long Thanh Expressway to Mai Chi Tho is 760m long, with 4 lanes, part of the An Phu Intersection project (Thu Duc City) and will open to traffic before April 30.

The 14 km long elevated road connecting Ho Chi Minh City - Binh Duong is about to open

|

HCMC - The elevated road section of more than 14 km long, with 4 lanes passing through Thu Duc City, connecting with Binh Duong province (under Ho Chi Minh City Ring Road 3) will open to traffic at the end of 2025.

Ha Long canned goods temporarily suspend factory production in Hai Phong

|

Hai Phong - Ha Long Canned Food Joint Stock Company has just announced the short-term suspension of production operations at a factory in Hai Phong.

Bad news

|

Mrs. Ha Thi Trac, born in 1930, is the mother of comrade Nguyen Dinh Chuc - former Deputy Editor-in-Chief of Lao Dong Newspaper; hometown: Thai Hoa commune, Phu Tho province; passed away at 9:45 am on January 11, 2026 (ie, November 23rd of the year At Ty), at the age of 96.

White dolphins appear near Thanh Hoa beach

|

Thanh Hoa - A herd of dolphins suddenly appeared in the area near Sam Son beach, including white dolphins.

Drivers who have been driving ambulances without pay for more than 10 years in An Giang border area

|

An Giang - For more than 10 years, ambulance drivers have volunteered without pay to take people to medical facilities for treatment.

Scene of the fire at a row of houses in the riverside area at Binh Trung market

|

Ho Chi Minh City - Level 4 houses at the end of Binh Trung market, adjacent to the riverbank, burned down, functional forces blockade the scene.

HCMC will enforce 4 land plots for the construction of roads worth VND41,387 billion

MINH QUÂN |

Ho Chi Minh City - Thu Duc City plans to enforce land acquisition for 4 cases that have not yet handed over the site for the construction of the Ring Road 3 project with a total capital of more than VND 41,387 billion.

The largest intersection in Ho Chi Minh City is about to open the first underpass

MINH QUÂN |

HCMC - The underpass from the HCMC - Long Thanh Expressway to Mai Chi Tho is 760m long, with 4 lanes, part of the An Phu Intersection project (Thu Duc City) and will open to traffic before April 30.

The 14 km long elevated road connecting Ho Chi Minh City - Binh Duong is about to open

MINH QUÂN |

HCMC - The elevated road section of more than 14 km long, with 4 lanes passing through Thu Duc City, connecting with Binh Duong province (under Ho Chi Minh City Ring Road 3) will open to traffic at the end of 2025.