HCMC will enforce 4 land plots for the construction of roads worth VND41,387 billion

MINH QUÂN |

Ho Chi Minh City - Thu Duc City plans to enforce land acquisition for 4 cases that have not yet handed over the site for the construction of the Ring Road 3 project with a total capital of more than VND 41,387 billion.

On March 12, Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc inspected the construction site of Ring Road 3, the section passing through Thu Duc City and Binh Chanh District.

The section of Ring Road 3 through Ho Chi Minh City is more than 47 km long, with a total investment of about VND 41,387 billion, of which compensation and site clearance costs account for VND 18,975 billion.

The project through Ho Chi Minh City has 10 main construction packages, of which 4 packages will start construction from 2023, the remaining 6 packages will be implemented in 2024.

Chu tich UBND TPHCM Nguyen Van Duoc (bia trai) thi sat Vanh dai 3 qua Thu Duc.  Anh: Minh Quan
Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc (left cover) inspected Ring Road 3 through Thu Duc city. Photo: Minh Quan

According to Mr. Luong Minh Phuc - Director of the Ho Chi Minh City Traffic Construction Investment Project Management Board, up to now, the Ring Road 3 project through Ho Chi Minh City has reached 31.1% of the construction volume.

The road section through Thu Duc City is over 14km long, designed on high ground with 4 lanes in phase 1, expected to be technically open to traffic by the end of 2025. This route connects from the Ho Chi Minh City - Long Thanh - Dau Giay Expressway, passes through Thu Duc City and ends at the Tan Van intersection (Binh Duong).

The remaining sections through Binh Chanh, Cu Chi, and Hoc Mon districts will be technically open to traffic on April 30, 2026.

Vanh dai 3 qua TP Thu Duc (TPHCM) dai hon 14km se di tren cao, du kien thong xe ky thuat cuoi nam 2025. Anh: Anh Tu
The more than 14km long Ring Road 3 through Thu Duc City (HCMC) will travel elevately, expected to be technically open to traffic by the end of 2025. Photo: Anh Tu

Although the construction progress is being accelerated, the project is still facing obstacles due to land clearance problems in some areas.

The section through Thu Duc City still has 4 households that have not handed over the site, affecting the implementation of some overpasses. In Binh Chanh district, three locations have not been completely cleared, causing difficulties for construction.

4 can nha nam tren cong truong du an Vanh dai 3 TPHCM qua Thu Duc. Anh: Anh Tu
4 houses are located on the construction site of the Ho Chi Minh City Ring Road 3 project through Thu Duc. Photo: Anh Tu

Mr. Hoang Tung - Chairman of Thu Duc City People's Committee said that the locality has made efforts to persuade people to agree, but there are still some cases that have not agreed. If it cannot be resolved by agreement, the government will have to apply coercive administrative measures to complete site clearance in March 2025.

Thi cong Vanh dai 3 tren cao qua TP Thu Duc.  Anh: Minh Quan
Construction of the elevated Ring Road 3 through Thu Duc City. Photo: Minh Quan

At the construction site, Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc emphasized that the Ring Road 3 project passes through many localities, having a great impact on the transport infrastructure and economy of Ho Chi Minh City.

Mr. Nguyen Van Duoc highly appreciated the efforts of relevant units in site clearance and speeding up the project's progress.

Mr. Nguyen Van Duoc also said that the Ho Chi Minh City People's Committee has committed to Deputy Prime Minister Mai Van Chinh and the Government on site clearance and progress of the Ring Road 3 project.

The entire Ring Road 3 project through Ho Chi Minh City must be completed and put into operation on June 30, 2026.

Therefore, the Chairman of the Ho Chi Minh City People's Committee requested Thu Duc City and related localities to clearly commit to the progress of site handover. "Units need to take responsibility and commit to Ho Chi Minh City and the people about the project progress" - Mr. Nguyen Van Duoc emphasized.

MINH QUÂN
RELATED NEWS

The largest intersection in Ho Chi Minh City is about to open the first underpass

|

HCMC - The underpass from the HCMC - Long Thanh Expressway to Mai Chi Tho is 760m long, with 4 lanes, part of the An Phu Intersection project (Thu Duc City) and will open to traffic before April 30.

The 14 km long elevated road connecting Ho Chi Minh City - Binh Duong is about to open

|

HCMC - The elevated road section of more than 14 km long, with 4 lanes passing through Thu Duc City, connecting with Binh Duong province (under Ho Chi Minh City Ring Road 3) will open to traffic at the end of 2025.

Image of the largest bridge on Ho Chi Minh City Ring Road 3 about to reach the finish line

|

Ho Chi Minh City - Nhon Trach Bridge, an important item on Ho Chi Minh City Ring Road 3, is about to close the final span on March 9 and is expected to open to traffic on April 30.

The huge Mid-Autumn Festival lantern worth hundreds of millions of VND lights up the streets of Tuyen Quang ward

|

Tuyen Quang - The Mid-Autumn Festival in Tuyen Quang is famous for its giant lanterns.

Do not let power projects get stuck due to delayed administrative procedures

|

The Deputy Prime Minister requested 3 corporations and 1 military enterprise to resolutely implement the power project and not to let the power project stall due to delayed administrative procedures.

Husband goes to work far away, wife stays at home, has an affair and has a child with another person - Part 1

|

The 9th hour - Husband leaves home to work far away, sending money to support the family. But in loneliness, his wife had an affair and became pregnant with someone else. What will happen to this family?

Vietnam continues to contribute to bringing peace at the Thailand - Cambodia border

|

Vietnam welcomes the positive developments between Cambodia and Thailand, and will continue to strive to contribute to bringing peace at the border between the two countries.

Vietnam General Confederation of Labor guides on collecting union funds

|

Grassroots trade unions are allowed to use 75% of total trade union budget revenue, according to the guidance document of the Vietnam General Confederation of Labor.

The largest intersection in Ho Chi Minh City is about to open the first underpass

MINH QUÂN |

HCMC - The underpass from the HCMC - Long Thanh Expressway to Mai Chi Tho is 760m long, with 4 lanes, part of the An Phu Intersection project (Thu Duc City) and will open to traffic before April 30.

The 14 km long elevated road connecting Ho Chi Minh City - Binh Duong is about to open

MINH QUÂN |

HCMC - The elevated road section of more than 14 km long, with 4 lanes passing through Thu Duc City, connecting with Binh Duong province (under Ho Chi Minh City Ring Road 3) will open to traffic at the end of 2025.

Image of the largest bridge on Ho Chi Minh City Ring Road 3 about to reach the finish line

Anh Tú |

Ho Chi Minh City - Nhon Trach Bridge, an important item on Ho Chi Minh City Ring Road 3, is about to close the final span on March 9 and is expected to open to traffic on April 30.