Intersection suspended for nearly 10 years in Hanoi is about to be rebuilt

SÓNG HỮU |

Hanoi - The Department of Construction requests localities to completely complete site clearance to complete the construction of Pham Tu - Road 70 intersection, deadline in April.

The road project surrounding the Chu Van An Memorial Area is implemented in the form of BT (build - transfer), including two main routes.

Line No. 1 is more than 2.5 km long, road surface width 53.5 m; line No. 5 is more than 1.1 km long, width 20.5 m.

Although most of the items have been completed and put into operation, the Pham Tu - Road 70 intersection has been stalled since 2017 due to site clearance problems.

According to Lao Dong's records, this area has become a traffic jam hotspot for many years, causing many difficulties for people's travel, especially during peak hours.

s
s
The intersection of road 70 - Pham Tu (Hanoi) has not been able to be built for many years due to site clearance issues. Photo: Song Huu
s
The overpass item at the 70 - Pham Tu intersection has been unfinished for many years. Photo: Song Huu

To speed up the implementation of the investment project according to the direction of the Hanoi City People's Committee, the Department of Construction has just issued a document requesting the People's Committees of Thanh Liet, Ha Dong and Kien Hung wards to urgently build detailed progress to definitively implement site clearance and resettlement work; clearly assign people, clearly work, and clearly responsibilities.

Have drastic solutions to accelerate the progress of site clearance work, completely complete site clearance work (including moving technical infrastructure works) in April 2026, and hand over the site to investors to implement the project.

The Chairmen of the People's Committees of the above-mentioned wards are responsible to the leaders of Hanoi City for the progress of site handover as required.

s
Some works within the project area have been demolished, recorded on April 15. Photo: Song Huu
s
Many households have moved assets and handed over land for the project. Photo: Song Huu

The Department of Construction requests investors and project enterprises to urgently review progress, review the scope of land handover, focus resources on constructing items that have received land, deploy construction to complete the project, ensure project completion progress in the second quarter of 2026; build detailed progress and send it to the City People's Committee and the Department of Construction for monitoring and urging.

The results of this project implementation are one of the important contents to consider and evaluate the capacity of investors in the coming time when participating in investment projects in Hanoi City.

The Hanoi Traffic Construction Investment Project Management Board coordinates with the People's Committees of Thanh Liet, Ha Dong and Kien Hung wards to accelerate the progress of completing site clearance work in April 2026; preside over and urge investors to accelerate the construction progress and complete the investment project in the second quarter of 2026.

SÓNG HỮU
RELATED NEWS

Hanoi informs about the implementation of the North-South high-speed railway project

|

Hanoi - For the North-South high-speed railway project, localities have implemented reviews and determined the scope of land recovery, reaching about 50-60% of the volume.

National Highway 6 upgrade project: Ward proposes solutions to handle cases of not handing over land

|

Hanoi - For cases of intentionally delaying the handover of land for the National Highway 6 upgrade project, Chuong My ward will apply handling measures according to regulations.

Well water turns purple-red, many households in Thanh Hoa worried

|

Thanh Hoa - Many households in Thach Quang commune are worried and uneasy about the situation of drilled well water and stream water changing to purple-red and smelly.

People wear ao dai to preserve meaningful moments towards April 30

|

Hanoi - Joining the atmosphere of celebrating April 30th, many people recorded meaningful moments at Ba Dinh Square, expressing national pride.

Trusting Lao Dong Newspaper to maintain its No. 1 position in protecting workers

|

Hanoi - At a working session with Lao Dong Newspaper on the morning of April 16, Chairman of the Vietnam General Confederation of Labor Nguyen Anh Tuan expressed his belief that Lao Dong Newspaper will continue to maintain its number 1 position in protecting workers.

Live football U17 Vietnam vs U17 Timor Leste at the Southeast Asian tournament

|

Live match between U17 Vietnam and U17 Timor Leste at the 2026 U17 Southeast Asian Championship, taking place at 3:30 PM today (April 16).

Dong Nai mobilizes and appoints officials

|

Dong Nai - April 16, the Provincial Party Committee and Provincial People's Committee organized a conference to deploy decisions on personnel work.

Collecting people's opinions on the draft Political Report at the XI National Congress of the Vietnam Fatherland Front

|

The 11th National Congress of the Vietnam Fatherland Front, term 2026 - 2031 will take place from May 11-13 in Hanoi Capital. This is an important socio-political event taking place immediately after the success of the 14th National Congress of the Party and the election of National Assembly deputies of the 16th term, People's Councils at all levels for the term 2026 - 2031.

Người dân ngồi kín nhà văn hóa nhận tiền bồi thường dự án 925.000 tỉ đồng ở Hà Nội

SÓNG HỮU |

Hà Nội - Xã Đại Thanh đã tổ chức nhiều đợt chi trả tiền bồi thường, hỗ trợ giải phóng mặt bằng cho người dân có đất thu hồi dự án Khu đô thị thể thao Olympic.

Hanoi informs about the implementation of the North-South high-speed railway project

HOÀI ANH |

Hanoi - For the North-South high-speed railway project, localities have implemented reviews and determined the scope of land recovery, reaching about 50-60% of the volume.

National Highway 6 upgrade project: Ward proposes solutions to handle cases of not handing over land

Anh Tuấn |

Hanoi - For cases of intentionally delaying the handover of land for the National Highway 6 upgrade project, Chuong My ward will apply handling measures according to regulations.