Thanh Xuan Ward comprehensively hands over Ring Road 2.5 site

HOÀI ANH |

Hanoi - Thanh Xuan Ward is mobilizing all forces to achieve the progress of handing over the clean site of Ring Road 2.5 Project before May 15.

On May 8, in an exchange with Lao Dong Newspaper, a representative of Thanh Xuan Ward People's Committee said that, up to now, the ward has completed the payment of compensation for 340/472 cases in the land acquisition area for Ring Road 2.5 (reaching a rate of nearly 75%).

Previously, to ensure progress, the Compensation, Support and Resettlement Council established 4 payment teams, organizing the receipt of people's registrations before 8 pm every day, thereby arranging payments on the same day, minimizing waiting.

At the payment session, Ms. Nguyen Thi Oanh (Chinh Kinh street) - one of the households subject to site clearance, shared her biggest wish is to soon receive resettlement land to stabilize her life. When there is land, the family will be more assured to calculate long-term business.

The payment process takes place very quickly. We are also ready to coordinate to ensure that the government implements it on schedule" - Ms. Oanh affirmed.

Mr. Do Dinh Binh (Cu Loc 2 street) said that when receiving compensation money, not only his family but also most people in the area were very excited. Everyone wanted to receive the money soon to hand over the site for the project on schedule.

Người dân phấn khởi nhận tiền bồi thường Dự án Vành đai 2,5. Ảnh: Khánh An
People excitedly receive compensation money for Ring Road 2.5 Project. Photo: Khanh An

Regarding the progress of site clearance, it is expected that by May 11, the ward will hand over about 2.3/3.91ha of clean land to Hanoi City.

Thanh Xuan Ward is mobilizing all forces to strive to achieve the progress of handing over clean ground before May 15.

In order to ensure continuity and efficiency in field work, working groups are being maintained on duty in the area, ready to listen to and promptly remove arising problems related to procedures as well as the rights of households in the relocation area.

The dismantling work is carried out according to the motto "do as far as possible, be sure as possible; hand over as far as possible, dismantle as far as possible; dismantle as far as possible, hand over clean ground as possible" to ensure overall progress.

With narrow demolition ground, in small, deep alleys, functional forces quickly opened roads to bring demolition machinery and transport vehicles to access the works, ensuring progress according to the city's direction.

Chủ tịch UBND phường Thanh Xuân Đỗ Quang Dương làm việc với 6 tổ phá dỡ tại hiện trường. Ảnh: Khánh An
Chairman of Thanh Xuan Ward People's Committee Do Quang Duong works with 6 demolition teams at the scene. Photo: Khanh An
Phường Thanh Xuân tổng lực giải phóng mặt bằng Vành đai 2,5. Ảnh: Khánh An
Thanh Xuan Ward mobilizes forces to clear the site of Ring Road 2.5. Photo: Khanh An

Ring Road 2.5 section passing through Thanh Xuan ward is nearly 1km long, with a cross-section of about 50m, with a land area to be recovered of more than 39,000m2. The road passes through a densely populated residential area, involving 472 land plots and about 700 households.

HOÀI ANH
RELATED NEWS

Officials work until 8 pm to pay compensation for Ring Road 2.5 project

|

Hanoi - In order to speed up the progress of compensation payment for Ring Road 2.5 project, Thanh Xuan ward officials extended working hours to 8 pm.

Opening a road to bring machinery into small alleys, accelerating demolition to build Ring Road 2.5

|

Hanoi - For long, narrow alleys, Thanh Xuan ward opens roads to bring machinery to access and demolish works to make Ring Road 2.5.

Secretariat appoints personnel for the Inspection Committee of the Party Committee of Central Party Agencies

|

The Secretariat appointed the Inspection Committee of the Party Committee of Central Party Agencies for the term 2025-2030, including 9 personnel.

Stock market continues to set a new historical high

|

The stock market increased by more than 61 points and set a new peak in the first trading week of May.

Officials work until 8 pm to pay compensation for Ring Road 2.5 project

HOÀI ANH |

Hanoi - In order to speed up the progress of compensation payment for Ring Road 2.5 project, Thanh Xuan ward officials extended working hours to 8 pm.

Opening a road to bring machinery into small alleys, accelerating demolition to build Ring Road 2.5

HOÀI ANH |

Hanoi - For long, narrow alleys, Thanh Xuan ward opens roads to bring machinery to access and demolish works to make Ring Road 2.5.

Phường Thanh Xuân duyệt chi trả tiền bồi thường Vành đai 2,5 đạt gần 50%

HOÀI ANH |

Hà Nội - Công tác duyệt chi trả tiền bồi thường, tái định cư dự án Vành đai 2,5 tại phường Thanh Xuân đạt xấp xỉ 50%.