Vinh Hung Ward mobilizes the remaining households to hand over land to expand Linh Nam road

SÓNG HỮU |

Hanoi - The Linh Nam road expansion project through Vinh Hung ward still has one household that has not handed over the site, the government is actively mobilizing and dialoguing.

Talking to a reporter of Lao Dong Newspaper, a representative of the Vinh Hung Ward Investment - Infrastructure Project Management Board (Hanoi) said that the site clearance work for the Linh Nam road upgrade and expansion project through the ward has recorded positive results to date.

To implement the project, Vinh Hung ward authorities must recover land from 253 households, individuals and 10 organizations.

Determining that site clearance for the Linh Nam road expansion project is an important political task, Vinh Hung ward has focused on leading and directing professional departments and divisions to be determined to complete land acquisition and site clearance to implement the project on schedule.

Thanks to doing a good job of propaganda, mobilization, and dialogue, the majority of organizations, households, and individuals have signed land handover minutes.

s
Linh Nam road is narrow, often congested, especially during rush hour. Photo: Song Huu

Currently, only one household in the project area through Vinh Hung ward has not agreed to hand over the land.

This household is dismantling the project, but has not signed the land handover minutes" - representative of the Vinh Hung Ward Infrastructure Investment Project Management Board said.

Local authorities are still maintaining propaganda, mobilization, and dialogue to get people's consensus to hand over land for the project.

Organizing coercion will be the last resort in case people intentionally do not comply.

Đường Lĩnh Nam đoạn qua phường Vĩnh Hưng và Hoàng Mai (Hà Nội). Ảnh: Sóng Hữu
Linh Nam Street passing through Vinh Hung and Hoang Mai wards (Hanoi). Photo: Song Huu

The Linh Nam road upgrade and expansion project has a total length of about 3.4km, starting point at Tam Trinh road intersection, ending point at Nguyen Khoai dike intersection.

The total area of land recovered for project implementation is about 98,345.94 m2, related to about 793 households, individuals and 34 organizations in 5 wards.

In Vinh Hung ward, the length of the route is about 2.2km (odd rows), of which about 1.9km coincides with the Ring Road 2.5 project (section from Vinh Hung street to Ring Road 3 intersection).

s
Some sections are corrugated iron, preventing re-encroachment. Photo: Song Huu

Regarding construction work, a representative of the Vinh Hung Ward Investment - Infrastructure Project Management Board said that the contractor is currently organizing simultaneous construction of 4 sites that have been cleared.

Construction site No. 1 from Nguyen Khoai slope to Ring Road 3 is about 200m long and will be completed in March.

Construction site No. 2 (Long Thuyen market area) with a length of 100m, 50m of piles have been pressed, drainage culverts and tunnels are being dug and placed.

Construction site No. 3 (No. 419 Linh Nam street) is 150m long, has completed the D1000 rainwater drainage culvert, the D300 wastewater drainage culvert is 100m long, and tunnels are under construction.

Construction site No. 4 from house number 87-93 Linh Nam (in front of the textile factory) is 400m long, 200m of drainage ditch has been built on the sidewalk, and drainage ditch construction is continuing.

The item of moving underground works is still under construction. The item of cutting down and moving green trees has been completed.

SÓNG HỮU
RELATED NEWS

More than 30 households in a village do not agree to hand over land, authorities organize dialogue

|

Hanoi - Phu Nghia Commune government dialogues with more than 30 households in Doi 1 village to remove obstacles in site clearance for the National Highway 6 expansion project.

Hanoi removes site bottlenecks, accelerates traffic congestion prevention projects

|

Hanoi drastically clears ground, focuses resources on accelerating key traffic projects, reducing congestion and improving traffic in the Southern region.

Inspectors point out many businesses exploiting exceeding capacity to serve expressways in Khanh Hoa

|

Khanh Hoa - Many mineral exploitation enterprises exceeding capacity to serve the construction of expressway projects have been pointed out by the inspection agency.

Quang Tri Inspectorate intervenes, identifying households building houses encroaching on neighbors' land

|

Quang Tri - After the reflection of Lao Dong Newspaper, the Provincial Inspectorate determined that the family of Ms. M.T. T. H (Dong Ha ward) built a house encroaching on adjacent land.

US bombers attacking Iran banned in Spain

|

Spain banned US bombers from operating in its airspace and bases after criticizing the operation in Iran as illegal.

Football prediction Vietnam vs Malaysia

|

The Vietnamese team aims for important goals in the rematch against Malaysia in the 2027 Asian Cup qualifiers.

Russia releases Bollywood-style movie: 1,000 people on screen, 100% filmed in India

|

A Russian Bollywood-style film, 100% filmed in India with thousands of participants - unprecedented - is about to be released.

Hand, foot and mouth disease appears in all communes and wards of Hanoi

|

Hanoi - Hand, foot and mouth disease has appeared in 126 communes and wards with 24 outbreaks, of which up to 21 outbreaks broke out in preschool and kindergarten educational institutions.

Phú Diễn gỡ điểm nghẽn dự án hạ tầng 3ha, 23 hộ bàn giao mặt bằng

Minh Hạnh |

Hà Nội - UBND phường Phú Diễn triển khai giải phóng mặt bằng, gỡ “điểm nghẽn” dự án hạ tầng 3ha, hoàn thiện hạ tầng đô thị.

More than 30 households in a village do not agree to hand over land, authorities organize dialogue

SÓNG HỮU |

Hanoi - Phu Nghia Commune government dialogues with more than 30 households in Doi 1 village to remove obstacles in site clearance for the National Highway 6 expansion project.

Hanoi removes site bottlenecks, accelerates traffic congestion prevention projects

Minh Hạnh |

Hanoi drastically clears ground, focuses resources on accelerating key traffic projects, reducing congestion and improving traffic in the Southern region.

Hàng trăm trường hợp phải bàn giao mặt bằng để cải tạo đường Quốc lộ 6

Thu Giang |

Ngày 15.11, tại buổi tiếp xúc cử tri trước kỳ họp thứ 14, HĐND TP Hà Nội khoá XVI, nhiệm kỳ 2021-2026, cử tri quận Hà Đông đã phản ánh về việc có 390 trường hợp phải bàn giao mặt bằng để cải tạo nâng cấp đường Quốc lộ 6.