Ring Road 2.5 Project: Land recovery for households that do not comply with handover is about to be enforced

SÓNG HỮU |

Hanoi - By March 30, if households do not comply with handing over land for the Ring Road 2.5 project, Vinh Hung ward will enforce land recovery according to regulations.

The Linh Nam road upgrade and expansion project has a total length of about 3.4km, starting point at the Linh Nam road intersection, ending point at the Nguyen Khoai dike intersection.

The total area of land recovered for project implementation is about 98,345.94 m2, related to about 793 households, individuals and 34 organizations in 5 wards.

In Vinh Hung ward, the length of the route is about 2.2km (odd rows), of which about 1.9km coincides with the Ring Road 2.5 project (section from Vinh Hung street to Ring Road 3 intersection).

To implement the project, the government will have to recover land from 253 households, individuals and 10 organizations.

S
Ring Road 2.5 section passes through Hoang Mai and Vinh Hung wards (Hanoi). Photo: Song Huu
S
Vinh Hung ward is accelerating the progress of site clearance to construct the Ring Road 2.5 project. Photo: Song Huu

Identifying this as an important political task, over the past time, the Party Committee - People's Council - People's Committee of Vinh Hung ward has focused on directing the determination to complete the Linh Nam Road Upgrade and Expansion project to ensure progress.

Thanks to doing a good job of propaganda and mobilization, up to now, the site clearance for the Linh Nam road upgrade and expansion project (including the section belonging to Ring Road 2.5 project) has achieved many positive results.

Accordingly, 7/10 organizations have completed site clearance work; 2 organizations are working with the ward on land handover plans; the remaining land plot has been confirmed for origin, and a draft plan is being developed for public disclosure.

For land of 253 households and individuals: 200/253 households have issued decisions approving compensation, support and resettlement plans and paid money (194 households have received money and handed over land; 6 households have not received money and handed over land).

There are 53 households that have not issued Decisions approving plans (of which 45 households are approving plans; 1 household is adjusting the origin of land to approve plans; for the remaining 7 households, the Investment - Infrastructure Project Management Board has submitted to the Economic, Infrastructure and Urban Department to sign a draft plan for resettlement draw and approval of plans.

Up to now, Vinh Hung ward is still closely following the progress of site clearance as required by the City Party Committee and Hanoi City People's Committee for the Ring Road 2.5 project.

S
S
Some sections have been corrugated iron to prevent re-encroachment. Photo: Song Huu

Talking to Lao Dong Newspaper, a leader of Vinh Hung Ward People's Committee (Hanoi) said that for 6 households that have not complied with the handover of land, from now until March 30, the government will continue to propagate and mobilize compliance with the State's road construction policy, comply with receiving money, and hand over land according to the approved plan.

Leaders of Vinh Hung Ward People's Committee affirmed that all opinions and recommendations of people related to compensation, support, and resettlement work are listened to, received and answered publicly and transparently by the local government, ensuring maximum benefits for people whose land is recovered in accordance with regulations.

S
S
Some works have been dismantled and handed over land for the project. Photo: Song Huu

According to the plan, by March 30, if households do not comply with receiving money and handing over land, the government will organize land recovery enforcement according to regulations, ensuring the completion of land recovery and handover of land for the Ring Road 2.5 project on March 31 according to the direction of the City Party Committee and Hanoi City People's Committee.

Regarding the cases that have handed over the site, leaders of Vinh Hung Ward People's Committee said that the construction unit is urgently proceeding with demolition to deploy the 2.5 Ring Road project according to the set schedule.

SÓNG HỮU
RELATED NEWS

Request Phuong Liet and Dinh Cong wards to definitively handle the existence of site clearance for Ring Road 2.5

|

Hanoi requests Phuong Liet and Dinh Cong wards to urgently handle the existing problems in site clearance for the Ring Road 2.5 Project (Dam Hong - National Highway 1A section).

1.6km of Ring Road 2.5 risks missing handover deadline in March 2026

|

Hanoi - If the relevant parties do not promptly remove obstacles in site clearance, 1.6km of Ring Road 2.5 will miss the handover deadline in March 2026.

Positive signals about land acquisition and site clearance for Ring Road 2.5

|

Hanoi - 2 sections of Ring Road 2.5 through Cau Giay ward recorded many positive results in land acquisition and site clearance.

Proposing unexpected rewards for heroes in the fire in Hoang Mai

|

Hanoi - Amidst the rolling black smoke and the risk of fire spreading, some people did not mind the danger, climbed onto the roof, broke corrugated iron to open a way out, saving people trapped.

Ukraine locked gas valve by Hungary, forced to reopen Russian oil

|

Hungary suspends gas supplies to Ukraine until Kiev resumes Russian oil transit.

Detaining a young man for blocking and smashing a taxi on National Highway 20

|

Lam Dong - On March 25, the police temporarily detained the subject who smashed the taxi. The cause stemmed from the subject arguing with his wife and his wife calling a taxi to take him away.

Domestic gold prices are up to 31 million VND/tael higher than the world price

|

Bao Tin Minh Chau, Phu Quy, DOJI gold prices are currently significantly higher than the world price, with a difference of more than 29 million to 31.1 million VND per tael.

Proposal to raise the ceiling income for social housing purchases, increasing supply and demand pressure

|

Raising the ceiling on social housing purchase income is expected to help more people access policies.

Request Phuong Liet and Dinh Cong wards to definitively handle the existence of site clearance for Ring Road 2.5

SÓNG HỮU |

Hanoi requests Phuong Liet and Dinh Cong wards to urgently handle the existing problems in site clearance for the Ring Road 2.5 Project (Dam Hong - National Highway 1A section).

1.6km of Ring Road 2.5 risks missing handover deadline in March 2026

HỮU CHÁNH |

Hanoi - If the relevant parties do not promptly remove obstacles in site clearance, 1.6km of Ring Road 2.5 will miss the handover deadline in March 2026.

Positive signals about land acquisition and site clearance for Ring Road 2.5

SÓNG HỮU |

Hanoi - 2 sections of Ring Road 2.5 through Cau Giay ward recorded many positive results in land acquisition and site clearance.