Sweet fruit from promoting site clearance work in Phu Tho

Tô Công - Minh Chuyên |

Phu Tho - Positive results in site clearance of projects contribute to promoting disbursement of public investment capital and socio-economic development.

Promoting site clearance work

Reality shows that site clearance plays an important role in the progress of public investment projects. Without clean ground for construction, projects may overrun, be behind schedule, not promote investment efficiency, cause waste of resources, and affect the disbursement of public investment capital and economic growth targets.

Site clearance is both directly related to the rights and livelihoods of people, and has complex procedures, with many steps such as: land acquisition, inventory of assets, development of compensation plans, payment, resettlement... Therefore, smooth coordination between many departments, branches and local authorities is required.

Along with the advantage of being close to the people and close to the people of the 2-level local government model, levels of Phu Tho province have proactively and strengthened dialogue, propaganda, mobilization, and full and timely implementation of compensation, support, and resettlement policies according to regulations during the site clearance process of projects.

Tuyen duong giao thong nong thon tai xa Thanh Uyen da nhanh chong duoc do betong kien co. Anh: To Cong.
The rural traffic road in Thanh Uyen commune has quickly been reinforced with concrete. Photo: To Cong

The project to renovate and upgrade rural roads in area 2, Thanh Uyen commune (now area 2 - Minh Duc, Hien Quan commune) was started on October 12. Right from the project implementation, the Party Committee, government, functional agencies of Hien Quan commune and residential area have proactively coordinated, promoted propaganda, mobilized people and removed obstacles early.

Immediately after being handed over the clean ground, the contractor quickly deployed construction. According to reporters of Lao Dong Newspaper in the last days of the year, just over 2 months after the commencement, the road has now been basically completed, the entire route has been concreted with spacious and beautiful road surface.

According to Mr. Nguyen Thanh Do - Secretary of the Party Cell, Head of Zone 2 - Minh Duc, the entire zone has about more than 50 households, all of whom are parishioners of the Minh Duc parish belonging to Thanh Uyen Parish. When propagated at all levels about the policy of expanding the road, people all agreed and voluntarily donated land and dismantled architectural structures so that the project could be implemented soon.

Nguoi dan dong thuan trong giai phong mat bang giup du an o noi day duoc trien khai nhanh hon. Anh: To Cong.
People agree in site clearance to help the project here be implemented faster. Photo: To Cong

With large projects such as the inter-regional traffic road project connecting Ho Chi Minh Road with National Highway 70B, National Highway 32C of Phu Tho province to Yen Bai province (now Lao Cai province), which is a key project of the province (total investment of 2,120 billion VND), previous districts and current communes have actively and proactively removed difficulties and promoted site clearance work.

To date, the main inter-regional road, more than 53km long, through the old districts of Tam Nong, Cam Khe, Ha Hoa, has been opened; the important branch connecting from the main road to Cam Khe industrial park and the extended inter-regional road connecting National Highway 32C are being accelerated in construction progress.

With the branch connecting Cam Khe industrial park, which was started at the end of 2024 with a total investment of more than 96 billion VND. In the early stages of project implementation, site clearance work faced many difficulties when some households did not agree to receive compensation funds, slow land handover, and difficulty in determining the origin of land...

Tuyen nhanh duong lien vung thi cong vuot doi cao ket noi khu cong nghiep Cam Khe. Anh: To Cong.
Inter-regional road branch construction crossing high hills connecting Cam Khe industrial park. Photo: To Cong.

Faced with the above situation, the authorities of the old communes of Cam Khe district (Xuong Thinh, Cap Dan, old Cam Khe town) and the current Cam Khe commune have made efforts to propagate and mobilize people to understand the purpose and meaning of the project and agree to implement it. Along with that, specialized agencies support the communes to determine the origin of land and soon complete compensation plans.

According to Mr. Nguyen Anh Tuan - Vice Chairman of Cam Khe Commune People's Committee, by October 2025, the site clearance of the inter-regional branch road has been completed, 428/428 households have been inventoried, reaching 100%; approved and paid compensation and support to 428/428 households; handed over the entire site length of the 3.083/3.083km route... From there, the project is being accelerated in construction progress.

Active disbursement of public investment capital

Right from the beginning of 2025, Phu Tho province has identified disbursement of public investment capital as a key and consistent task. In which, site clearance is an extremely important link and directly affects the progress of disbursement of public investment capital. If site clearance is slow, the project is stalled, and there is no construction volume, leading to no basis for payment and disbursement of capital.

Therefore, levels, sectors, and localities of the province have upheld the spirit of proactiveness and actively resolving obstacles in site clearance for projects. When one of the biggest bottlenecks affecting the disbursement results of public investment capital has been removed, projects are implemented quickly, and public investment capital is allocated in accordance with the plan and progress.

Tuyen duong du an Cai tao, nang cap tuyen duong noi Tinh lo 325B, ket noi duong Ho Chi Minh di cau Ngoc Thap va tuyen cuu ho cuu nan vua duoc tham nhua (doan xa Xuan Lung). Anh: To Cong.
The project road to renovate and upgrade the road connecting Provincial Road 325B, connecting the Ho Chi Minh road to Ngoc Thap bridge and the rescue and relief route has just been asphalted (section of Xuan Lung commune). Photo: To Cong.

Up to now, the total public investment plan capital allocated is 36,496.219 billion VND; detailed allocation of 36,496.219 billion VND, reaching 100%.

For the whole province, accumulated disbursement in the first 11 months of 2025 is estimated at 18,816.760 billion VND, reaching 51.6% of the total capital plan. It is estimated that disbursement for the whole year 2025 will reach 95% of the total plan; of which, disbursement of the capital plan assigned in 2025 (excluding long-term capital) is 26,150 billion VND, reaching 140% compared to the capital plan assigned by the Prime Minister.

From the synchronous solutions that have been and are being implemented, along with the involvement of the entire political system, site clearance work in particular, and disbursement of public investment capital in general in Phu Tho have achieved many positive results, contributing to promoting economic growth, creating a foundation for the province to successfully implement the socio-economic development goals set out.

Tô Công - Minh Chuyên
RELATED NEWS

Dong Loc Commune People's Committee speaks out after reflecting on slow site clearance

|

Nghe An - Dong Loc Commune People's Committee explains the reason for the slow site clearance for the Hung Luan Scaffolding Factory project.

HCMC today: 5 communes urgently clear land for Moc Bai Expressway

|

HCMC speeds up land acquisition of more than 1,500 households in 5 communes to build expressways; HCMC Traffic Police use special vehicles to take the girl to the emergency room in time...

Morning news 25.12: Hanoi speeds up site clearance for the Ring Road 2.5 project

|

Morning news on December 25: A group of civil servants and public employees are about to receive a maximum allowance of 70% of their salary; Many wards are implementing site clearance for the construction of the Ring Road 2.5...

Russia warns Europe of strong retaliation if attacked

|

The Russian Foreign Minister said that the EU is not ready to negotiate the Ukraine conflict, continue to support Kiev and publicly prepare for a scenario of confrontation with Moscow.

U23 Vietnam trains for the first time in Qatar

|

U23 Vietnam trains for the first time in Qatar in the training camp towards the 2026 AFC U23 Championship finals.

Illegal sand gathering yard in Hue City to be handled after reflection from Lao Dong Newspaper

|

Hue - Businesses temporarily suspend the operation of illegal sand gathering yards in Hue City when there is a reflection from Lao Dong Newspaper.

Ho Van Cuong answers questions about himself after a 10-year journey

|

As an artist in Nhu Quynh's "Huong sac giai nhan" music festival, Ho Van Cuong shared his nearly 10-year journey since being crowned "Children's Music Idol 2016".

Hanoi requires leaders to declare all red books, money, precious metals, and foreign assets

|

Hanoi has just issued an official dispatch requesting declaration and control of assets and income for people with positions and powers in organizations and units in 2025.

Dong Loc Commune People's Committee speaks out after reflecting on slow site clearance

QUANG ĐẠI |

Nghe An - Dong Loc Commune People's Committee explains the reason for the slow site clearance for the Hung Luan Scaffolding Factory project.

HCMC today: 5 communes urgently clear land for Moc Bai Expressway

Nguyên Chân |

HCMC speeds up land acquisition of more than 1,500 households in 5 communes to build expressways; HCMC Traffic Police use special vehicles to take the girl to the emergency room in time...

Morning news 25.12: Hanoi speeds up site clearance for the Ring Road 2.5 project

Nhóm PV |

Morning news on December 25: A group of civil servants and public employees are about to receive a maximum allowance of 70% of their salary; Many wards are implementing site clearance for the construction of the Ring Road 2.5...